This text of DCX-CHOL Enterprises, Inc. (DCX-CHOL Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DCX-CHOL Enterprises, Inc., (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of --

DCX-CHOL Enterprises, Inc. ASBCA Nos. 61806, 61807

Under Contract Nos. SPE4A6-14-M-B838 _) SPE4A6-16-M-H907_ )

APPEARANCES FOR THE APPELLANT: Mark R. Thomas, Esq. Marcos Gonzalez, Esq.

Reid Law PC Denver, CO

APPEARANCES FOR THE GOVERNMENT: __ Daniel K. Poling, Esq. DLA Chief Trial Attorney

Robert E. Sebold, Esq. Trial Attorney DLA Aviation Richmond, VA

OPINION BY ADMINISTRATIVE JUDGE SHACKLEFORD ON THE GOVERNMENT’S MOTIONS FOR SUMMARY JUDGMENT

The government moves for summary judgment, arguing that appellant cannot, as a matter of law, prove that the government is liable for appellant’s failure to timely deliver on the contracts at issue herein, because in signing the bilateral modifications, which changed the initial delivery dates on both contracts, appellant waived any argument it had that the government caused the delay in delivery. Appellant opposes the motion, alleging that the government is at fault for its failure to timely deliver the contracted products and appellant requires additional discovery to prove this fact. The

Board denies the motions.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS

Facts Pertaining to ASBCA No. 61806, Contract No. SPE4A6-14-M-B838

1. On March 28, 2014, the government awarded purchase order SPE4A6-14-M-B838 to appellant for the production of 18 branched wiring harnesses (ASBCA No. 61806 R4, tab 1 at 10-11) (hereinafter referred to as 61806 R4). The contract obligated appellant to submit one branched wiring harness as a first article approval by September 24, 2014, and subsequently, a production quantity of 17 branched wiring harnesses 180 days after first article approval (61806 R4, tab | at 11, 13). 2. The contract contained various standard clauses, including Federal Acquisition Regulation (FAR) 52.233-1, DISPUTES (JULY 2002); FAR 52.249-8, DEFAULT (FIXED-PRICE SUPPLY AND SERVICE) (APR 1984); and FAR 52.209-04, FIRST ARTICLE APPROVAL-GOVERNMENT TESTING (SEP 1989) (61806 R4, tab 1 at 13, tab 5 at 7-8).

3. Appellant submitted the first article on March 23, 2015 (61806 R4, tab 9 at 4). By letter dated August 5, 2015, the government informed appellant that the first article test had been disapproved, but no deficiency report was included with the correspondence (61806 R4, tab 32 at 7-8). The deficiency report for the failed first article test was provided to appellant on January 26, 2016 (61806 R4, tab 31 at 1).

4. On February 26, 2016, the government requested an updated delivery date for a revised first article submission and appellant requested an updated technical data package (TDP) (61806 R4, tab 32 at 1). On April 29, 2016, appellant notified the government that they never received an updated TDP (61806 R4, tab 33 at 3). On May 4, 2016, the government provided updated information to appellant on how to access the current TDP (id. at 1).

5. On September 29, 2017, the government issued a show cause notice to appellant (61806 R4, tab 14 at 2-3). In response, on October 2, 2017, appellant requested the government update the TDP, so it could address the noted discrepancy (61806 R4, tab 15).

6. On October 25, 2017, the government proposed a no-cost cancellation of the contract, invoking the terms of a different contract between the parties (61806 R4, tab 16 at 4). Appellant replied on October 31, 2017, and indicated that it was not accepting this proposal and that it would provide a first article for testing within two weeks (id.). The government accepted this proposal on November 9, 2017, and proposed a post-award conference to clarify remaining questions (id. at 2-3).

7. At the post-award conference on December 5, 2017, the government and appellant discussed problems with contract performance and outstanding questions on the TDP (61806 R4, tab 34 at 3-4). On January 5, 2018, the government provided answers to the questions from the post-award conference; appellant asked for further clarification on January 23, 2018, and then asked for further clarification on one question on January 25, 2018 (61806 R4, tab 35 at 21-22, tab 18 at 1-5). Following continued back and forth regarding a continuing ambiguity on the remaining technical issue, the government advised appellant to resubmit the first article with the technical data it had (61806 R4, tab 23 at 1).

8. Modification No. P00001, issued May 23, 2018, reset the delivery date to August 22, 2018 (61806 R4, tab 2). It also specified that if the first article re-submission was not delivered by the new delivery date, or was disapproved, the contract might be terminated in its entirety at no cost to the government. Appellant signed the modification. (61806 R4, tabs 2, 24) Appellant did not deliver the first article by the August 22, 2018 delivery date (61806 R4, tab 27).

9. On August 27, 2018, the government issued Modification No. PO0002 and terminated the contract for default (61806 R4, tabs 3-4).

10. Appellant filed a timely appeal to the Board on September 21, 2018, which was docketed as ASBCA No. 61806.

Facts Pertaining to ASBCA No. 61807, Contract No. SPE4A6-16-M-H907

11. On August 3, 2016, the government awarded purchase order SPE4A6-16-M-H907 to appellant for the supply of 12 radio frequency cable assemblies (cable assembly). The contract obligated appellant to submit one cable assembly for production lot testing by January 3, 2017, and to submit the remaining 11 cable assemblies by May 1, 2017. (ASBCA No. 61807 R4, tab 1 at 1-3, 7-8) (hereinafter referred to as 61807 R4)

12. The contract contained various standard clauses, including FAR 52.233-1, DISPUTES (MAY 2014); FAR 52.249-8, DEFAULT (FIXED-PRICE SUPPLY AND SERVICE) (APR 1984); and FAR 52.209-04, FIRST ARTICLE APPROVAL— GOVERNMENT TESTING (SEP 1989) (61807 R4, tab 1 at 9, tab 6 at 7, 20).

13. Appellant did not deliver the first cable assembly for production lot testing by the due date. On January 3, 2017, appellant emailed the government to request that production lot testing for the first cable assembly be submitted by April 15, 2017, and production of the remaining cable assemblies be submitted by September 25, 2017. On January 26, 2017 and February 16, 2017, appellant sent follow-up requests to the government for an extension of the delivery date. (61 807 R4, tab 9)

14. In bilateral Modification No. P00001, signed February 22, 2017, the delivery dates were extended to May 1, 2017 for the initial cable assembly production lot testing and September 25, 2017 for production of the 11 remaining cable assemblies. (61807 R4, tab 2 at 2, tab 10 at 1-4, 7-8)

15. Appellant did not deliver by May 1, 2017, and on May 2, 2018, the government issued a show cause notice to appellant (61807 R4, tab 14 at 2-3).

16. On May 10, 2018, appellant responded that it would present a first article for approval by the end of June 2018 (61807 R4, tab 15). The government issued Modification No. P00002 to establish a new delivery date of July 13, 2018. The modification noted that “if the contractor is delinquent in meeting the delivery schedule of the contract . . . the contract could be terminated for default.” (61807 R4, tab 3 at 2)

17. On July 10, 2018, the government received notice that appellant had cancelled source inspection and would not meet the delivery date of July 13, 2018 (61807 R4, tab 17 at 1).

18. On July 16, 2018, the government issued Modification No. P00003, terminating the contract for default for failure to timely deliver (61807 R4, tabs 4, 19).

19. Appellant filed a timely appeal to the Board on September 21, 2018, which was docketed as ASBCA No. 61807.

DECISION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Arko Executive Services, Inc. v. United States
553 F.3d 1375 (Federal Circuit, 2009)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
DCX-CHOL Enterprises, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/dcx-chol-enterprises-inc-asbca-2020.