H. J. Lyness Construction, Inc. v. United States

125 Fed. Cl. 387, 2015 WL 10606989
CourtUnited States Court of Federal Claims
DecidedJanuary 21, 2015
Docket11-129C
StatusPublished
Cited by2 cases

This text of 125 Fed. Cl. 387 (H. J. Lyness Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
H. J. Lyness Construction, Inc. v. United States, 125 Fed. Cl. 387, 2015 WL 10606989 (uscfc 2015).

Opinion

Cross-Motions For Summary Judgment; Genuine Issue of Material Fact

OPINION AND ORDER

DAMICH, Senior Judge:

Plaintiff, H.J. Lyness Construction, Inc. (“HJL”), seeks damages stemming from the termination for convenience by the General Services Administration (“GSA”) of HJL’s contract to renovate and provide security improvements to the lobby of a federal building. HJL has filed a motion for partial summary judgment for settlement costs in the amount of $563,792 associated with the termination for convenience. Defendant, The United States on behalf of GSA, (“the Government”), has filed a cross motion for complete summary judgment. The Government alleges that HJL has waived its right to seek settlement costs by executing a release of claims. In the alternative, the Government alleges that settlement costs should be limited to $30,180.59. Both motions are before the Court pursuant to Rule 56(c) of the Rules of the United States Court of Federal Claims (“RCFC”).

The Court finds that HJL’s continued negotiations regarding the settlement costs after the execution of the release may be sufficient to show that its claims for settlement costs are not barred. The Court further finds that the parties’ action and course of *388 conduct in this case create a genuine issue of material fact regarding whether the release constituted a full and final release of claims in exchange for final payment, or was simply one of a series of routine application forms for partial payments requested by HJL. Therefore, the Court denies in part Defendant’s cross motion for summary judgment. The Court further holds in abeyance Plaintiffs partial motion for summary judgment for damages until liability is established.

I. Facts

On August 15, 2006, HJL entered into Contract No. GS05P06SLC3014 with GSA. Compl. at ¶ 2. The contract was a firm-fixed price contract in the amount of $1,830,000 for lobby renovations and security improvements to the John Weld Peck Federal Building in Cincinnati, Ohio. Id. The performance bond, certificate of insurance and security clearances were thereafter reviewed and approved by GSA and on November 9, 2006, GSA issued the initial notice to proceed (“NTP”). Appendix to the Defendant’s Cross-Motion for Summary Judgment and Response to Plaintiffs Motion for Partial Summary Judgment (“DA”) 5. However, the NTP was rescinded by GSA on November 16, 2006, due to issues with the fire evacuation plan associated with the contract design. DA 159.

In 2007, HJL submitted its first pay application for its recoverable bond costs. The bond costs were reimbursed by this pay application in the amount of $14,976. DA 6-10. As part of the pay application form, a “Release of Claims” form (“release”) was attached to the pay application. The release stated that HJL was “releas[ing] the United States for any and all claims arising under or by virtue of said contract or any modification or change thereof.” DA 10. The release further contained space to exempt claims from the scope of the release. Harry J. Lyness, president of HJL, signed the pay application and did not exempt any claims. Id. According to HJL, the pay application was submitted to GSA on January 19, 2007. DA 6-9. The pay application and release of claims was signed by HJL on February 21, 2007. DA 7,10. Because there is a discrepancy between the date of the pay application and the date of the signing, the Court assumes that the date at the top of the document indicates (approximately) when the pay application form was either sent to HJL or was sent from HJL to GSA.

In order to resolve the fire safety issues that led to the rescission of the NTP in 2006 (as mentioned above) and to proceed with construction, GSA requested that HJL install an additional door in the rear of the building. DA 13-15. To accomplish this, on September 6, 2007, GSA issued a second NTP, together with a modification. DA 11T18. HJL completed the work and submitted a second pay application in the amount of $67,427.28, for costs associated with the change order. DA 24-28. This pay application contained the same release as attached to the first pay application and again, Mr. Lyness signed the pay application and did not exempt any claims. DA 28. This application is dated March 13, 2008, and both the pay application and release of claims were signed by HJL on April 23, 2008. DA 25, 28. This claim was paid as evidenced by the handwritten notation stating “paid 4-23-08.” DA 25.

On August 6, 2008, GSA again modified the contract and requested that HJL perform additional work, not to exceed $32,250. DA 29-31. The work was completed and the pay application, dated February 6, 2009, forwarded for payment on March 2, 2009, was signed by Mr. Lyness on May 6, 2009. DA 76-80, Plaintiffs Response to Cross Motion and Reply, Affidavit of Harry J. Lyness, dated August 8, 2014, Exhibit T (“Aff _.”) HJL was paid in the amount of $30,940. DA 76-80. This third pay application also contained the same release- as pay applications one and two. For a third time, Mr. Lyness did not exempt any claims (“May 6 release”). DA 80.

In addition to the pay applications, HJL also submitted partial requests for equitable adjustment. On November 28, 2008, HJL-submitted a request in the amount of $36,782.00 for alleged unabsorbed overhead costs for the fiscal year ending December 31, 2006. DA 32-39. HJL submitted a second request for equitable adjustment dated March 16, 2009, seeking $148,793.00 in unabsorbed overhead costs for the fiscal year *389 ending December 31, 2007. DA 40-63. GSA denied the first request on March 30, 2009, stating that it was partial, and instructed HJL to submit a “complete final request with all supporting documentation.” DA 64. The present record does not show that any action was taken on the second request either by HJL or GSA

On April 6, 2009, GSA terminated the contract for convenience. DA 65-68. (Although Mr. Lyness signed the third pay application and the accompanying release (May 6 release) after the termination for convenience, he alleges that it was submitted to GSA for review before the termination for convenience), i.e. on March 2, 2009. DA 76-80. On the same date, the contracting officer informed HJL that the contracting administration office would assign someone to the termination and that HJL could request the necessary settlement forms. DA 67. Specifically, the letter states:

(h) Administrative. The contract administration office named in the contract will identify the Contract Officer who will be in charge of the settlement of this termination and who will, upon request, provide the necessary settlement forms. Matters not covered by this notice should be brought to the attention of the undersigned.

DA 67. Subsequently, on April 10, 2009, HJL requested the settlement proposal form which was transmitted to HJL eighteen days later. DA 69-70.

Approximately ten months later, on February 24, 2010, HJL contacted GSA and again requested the settlement proposal form. DA 81. In response, on February 26, 2010, the contracting officer informed HJL that GSA viewed the May 6, 2009 release (submitted along with HJL’s third pay application) as a final release which closed out the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FLETCHER v. United States
Federal Claims, 2025
Ingham Regional Medical Center v. United States
126 Fed. Cl. 1 (Federal Claims, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
125 Fed. Cl. 387, 2015 WL 10606989, Counsel Stack Legal Research, https://law.counselstack.com/opinion/h-j-lyness-construction-inc-v-united-states-uscfc-2015.