Winn-Senter Const. Co. v. United States

75 F. Supp. 255, 110 Ct. Cl. 34
CourtUnited States Court of Claims
DecidedJanuary 5, 1948
Docket45999, 46592, 46593
StatusPublished
Cited by49 cases

This text of 75 F. Supp. 255 (Winn-Senter Const. Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winn-Senter Const. Co. v. United States, 75 F. Supp. 255, 110 Ct. Cl. 34 (cc 1948).

Opinion

MADDEN, Judge.

The plaintiffs made contracts with the Government to perform parts of the construction of the Cornhusker Ordnance Plant at Grand Island, Nebraska. The plaintiff in the first named suit had a separate contract, the plaintiff in the second named suit had two contracts and the two plaintiffs in the third named suit had, as joint contractors, two contracts. Each contract was a separate contract. The cases are treated together because the same findings of fact relate, in large partj to all of them, and the issues involved are, with exceptions that will be stated, the same.

All of the contracts here in suit were lump sum contracts. They were made after bids had been submitted pursuant to a public invitation for bids. Because of the necessity for haste in getting the work started, letter contracts rather than full formal ones were issued at first, late in April or in May 1942. Formal contracts were signed in May, June, or July. Work was begun on each of the contracts within 5 days after each letter contract was issued.

*257 Before the plaintiffs’ contracts were entered into, the Government had made a cost plus fixed fee contract with a corporation and an individual whereby those contractors jointly agreed to perform all architectural, engineering, and management services necessary in the construction of the plant to which the plaintiffs’ contracts, later made, related. In the findings and in this opinion, the joint contractors in that contract are called the A. E. M. That contract contemplated that most of the actual construction of the plant would be done by other contractors, but it provided that the A. E. M. should assemble a force of supervisors and skilled workmen to perform any work which was not awarded to other contractors. It provided that the A. E. M. should direct and supervise the work of all the construction contractors. The A. E. M. employed a force of carpenters and laborers to perform any work not contracted out to others, and to take over and complete any work on which other contractors were delayed. It operated a personnel and labor procurement office, and all labor, except supervisory labor, which the plaintiffs and other contractors used, was obtained by requisitions on the A. E. M. All labor, with the same exception was cleared by the A. E. M. through the offices of the United States Employment Service.

The contracts of the plaintiffs and the A. E. M. with the Government required them to pay not less than the prevailing wage in the area as determined by the Secretary of Labor and stated in the specifications. These provisions of the plaintiffs’ contracts are set out in finding 6. In the A. E. M.’s contract and the plaintiffs’ contracts the prevailing wage for carpenters was stated to be $1.12i^ per hour and for unskilled labor $.50 per hour.

The A. E. M. arrived on the project about April 8, 1942. Investigation of the labor .market and supply showed that other projects which drew labor from the same sources were paying higher wages than those stated above, and the A. E. M. thought that its project could not be adequately manned at these wages. It immediately asked the Area Engineer, who was the Contracting Officer, to obtain an increase in the wage rates. On May 30, it sent a letter to the Area Engineer pressing for action on this request and asking that the rates be set at $1.25 for carpenters and $.60 for laborers. This letter, quoted in finding 11 describes the situation as the A. E. M. found it. The letter was sent by the Area Engineer, who was the Contracting Officer, to the District Engineer, whose office was at Omaha, together with a recommendation that the increases be authorized. By telephone and teletype the question was presented to the Chief of Engineers who sent to the Division Engineer, who was also at Omaha, a teletype message, which we have quoted in finding 13, authorizing the increases requested and saying “Wage adjustment order in process of issuance.” This message was sent down through channels to the Contracting Officer, whose office notified the A. E. M. and said “Please inform all interested parties.” On June 11 the A: E. M. wrote the plaintiffs giving them the information. On June 19 the Area Engineer’s Office wrote the plaintiffs stating that the wage rates had been increased and saying “It is requested that you change your rates accordingly.” On June 20 and 22 the Office of the Area Engineer sent letters to the plaintiffs returning pay rolls to them for correction and requiring that they pay the increased rates retroactively to carpenters to June 1 and to laborers to June 8. The plaintiffs made the retroactive increases, and paid the increased rates during their entire performances of their contracts.

A Mr. Knox, General Manager of the A. E. M. held weekly meetings in his office at the project, attended by the Contracting Officer, the various contractors, and the supervisory personnel of the A. E. M. At a meeting about June 11, the plaintiffs complained about the additional costs they would incur in paying the increased rates, and asked what action would be taken to reimburse them. Mr. Knox said, in the presence of the Contracting Officer, that when the contracts were completed and the additional costs could be determined, each contractor would be reimbursed by being given a change order.

After some telephone conversations which are shown in our findings and not repeated here, the wage adjustment order *258 promised in the Chief of Engineers teletype of May 30 came through to the Contracting Officer on July 16. It made authorized increases applicable only to the A. E. M. contract. The plaintiffs were so notified. However, they continued to pay the increased wages, and it would not have been possible for them to do otherwise.

The communication of May 30 from the Chief of Engineers referred to the Com-husker Ordnance Plant, and the wage “rate for this project.” By its plain meaning and as it was interpreted by everyone who read it, it applied to all the carpenters employed by all contractors at the project.

The statements of wage rates in the plaintiffs’ contracts and the A. E. M. contract were made pursuant to the Davis Bacon Act, 54 Stat. .399, 40 U.S.C.A. § 276a. That act requires that a contractor with the Government bind himself to pay not less than the wages found by the Secretary of Labor to be the prevailing wages in the area where the contract is performed. The act expresses the purpose of the Government not to profit by using a contractor who keeps costs down by paying sub-standard wages. Neither it, nor any other law force at the time here in question, put any ceiling on wages to be paid by lump sum Government contractors such as the plaintiffs. They, by making their contracts agreed to pay whatever wages they had to pay to get the labor necessary to do the job.

The A. E. M., a cost-plus contractor, on the other hand, had agreed in its contract, as shown in finding 11, that it could not include in its costs any wages paid in excess of those approved in writing by the Government Agency with which it contracted. It was, therefore, necessary for it, to avoid an actual out-of-pocket loss of money, to secure the approval of the Chief of Engineers before it began to pay higher wages. The A. E. M. must have realized that whatever wages it paid to its direct employees, if higher than the contract minimum, would, in the circumstances, become the standard wages for the project which other contractors would have to pay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Satterfield & Pontikes Construction, Inc.
Armed Services Board of Contract Appeals, 2021
Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)
Carol D. Jones
Armed Services Board of Contract Appeals, 2017
H. J. Lyness Construction, Inc. v. United States
125 Fed. Cl. 387 (Federal Claims, 2015)
Raytheon Co. v. United States
96 Fed. Cl. 549 (Federal Claims, 2011)
IMS Engineers-Architects, P.C. v. United States
92 Fed. Cl. 52 (Federal Claims, 2010)
Alliant Techsystems Inc. v. United States
74 Fed. Cl. 566 (Federal Claims, 2007)
Westfed Holdings, Inc. v. United States
52 Fed. Cl. 135 (Federal Claims, 2002)
Cavalier Clothes, Inc. v. United States
51 Fed. Cl. 399 (Federal Claims, 2001)
Bighorn Lumber Co. v. United States
49 Fed. Cl. 768 (Federal Claims, 2001)
National Steel & Shipbuilding Co. v. United States
49 Fed. Cl. 579 (Federal Claims, 2001)
Northrop Grumman Corp. v. United States
47 Fed. Cl. 20 (Federal Claims, 2000)
George Hyman Construction Co. v. United States
39 Cont. Cas. Fed. 76,601 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
75 F. Supp. 255, 110 Ct. Cl. 34, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winn-senter-const-co-v-united-states-cc-1948.