Meridian Engineering Company v. United States

CourtUnited States Court of Federal Claims
DecidedSeptember 23, 2019
Docket11-492
StatusPublished

This text of Meridian Engineering Company v. United States (Meridian Engineering Company v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meridian Engineering Company v. United States, (uscfc 2019).

Opinion

In the United States Court of Federal Claims No. 11-492C

(Filed: September 23, 2019)

) MERIDIAN ENGINEERING ) Post-remand decision on claims arising out of COMPANY, ) a contract for construction of a flood control ) project; accord and satisfaction; proper subject Plaintiff, ) matter; inapplicability of releases to preclude ) relief; damages v. ) ) THE UNITED STATES, ) ) Defendant. ) )

Michael H. Payne, Cohen, Seglias, Pallas, Greenhall & Furman PC, Philadelphia, Pennsylvania, for plaintiff.

John H. Roberson, Senior Trial Counsel, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, D.C., for defendant. With him on the briefs were Joseph H. Hunt, Assistant Attorney General, Civil Division, and Robert E. Kirschman, Jr., Director, and Allison Kidd-Miller, Assistant Director, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington D.C.

OPINION AND ORDER

LETTOW, Senior Judge.

This contract case returns to the court on remand from the United States Court of Appeals for the Federal Circuit. The parties’ dispute relates to a contract between Meridian Engineering Company (“Meridian”) and the United States Army Corps of Engineers (“Corps”) for the construction of a flood control project in Nogales, Arizona, near the border with Mexico. Numerous issues arose during construction that ultimately led to the project’s suspension after partial completion. The parties’ disagreement over costs led Meridian to file suit at this court in 2011 under the Contract Disputes Act (“CDA”), 41 U.S.C. §§ 7101-7109.

The court conducted two trials, one held in 2014 and one in 2016, on the issues of liability and damages respectively. See Meridian Eng’g Co. v. United States, 122 Fed. Cl. 381 (2015) (“Meridian I”) (liability); Meridian Eng’g Co. v. United States, 130 Fed. Cl. 147 (2016) (“Meridian II”) (damages). Following these two trials, the government was held to be liable on some counts of the complaint and Meridian was awarded damages in the amount of $983,771.10 plus interest. Meridian II, 130 Fed. Cl. at 172. Meridian appealed from the final judgment. See Meridian Eng’g Co. v. United States, 885 F.3d 1351 (Fed. Cir. 2018) (“Meridian III”). The Federal Circuit considered numerous issues on appeal, resulting in a mixed disposition of partial affirmance, partial vacatur, partial reversal, and remand. See id. at 1367. Specifically of relevance now, the court vacated and remanded the court’s findings in Meridian I with respect to Meridian’s flood-events claim (“Count 4”) and Meridian’s unpaid contract-quantities claim (“Count 6”) and reversed and remanded this court’s interest award in Meridian II. See id. When the remanded case returned to this court, it was transferred from the originally assigned judge to the undersigned.

The sole issues remaining for the court are Count 4, as to both liability and damages, and the interest calculation. 1 For Count 4, this court was instructed on remand “to consider whether the parties reached a meeting of the minds on the flood event claims in light of all of the evidence.” Id. at 1365 (citation omitted). Separately, the Federal Circuit instructed this court “to enter the correct accrual date [for interest] as January 7, 2011, and recalculate the amount of interest in accordance with the correct accrual date.” Id. at 1354 n.2. A hearing was held on September 4, 2019 to consider these remaining issues. Additionally, the court has reviewed the documentary and testimonial evidence adduced and addressed at trial, and the case is now ready for disposition. FACTS 2

On September 21, 2007, the United States Army Corps of Engineers awarded Meridian, an engineering and construction firm based in Tucson, Arizona, a $5.8 million contract to undertake and construct a flood control project for the Chula Vista Channel in Nogales, Arizona. JX193-1. 3 During the beginning stages of the project, Meridian requested electronic drawings and survey files from the Corps on multiple occasions, but failed to receive them. See, e.g., JX110 at 3 (requesting drawings on Oct. 29, 2007); DX726 at 4 (requesting again on Nov. 14, 2007); PX134 (explaining that the drawings had not yet been received as of Dec. 4, 2007). The drawings were sent by the Corps to Meridian on December 26, 2007. See JX110 at 9. Following receipt of the drawings, Meridian was able to commence construction in early January 2008. See JX78 at 531.

1 As the case was being briefed on remand, the parties settled Count 6 and that Count was voluntarily dismissed by the plaintiff and is no longer at issue. See Notice (Sept. 19, 2019), ECF No. 179 (payment of $225,000 received by Meridian in settlement of Count VI); Stipulation of Dismissal (Sept. 20, 2019) (ECF No. 180) (parties’ stipulation that Count VI be and is dismissed with prejudice). 2 The recitation of facts constitutes the court’s principal findings of fact in accord with Rule 52(a) of the Rules of the Court of Federal Claims (“RCFC”). Other findings of fact and rulings on questions of mixed fact and law are set out in the analysis. A more complete recitation of facts is described in Meridian I. See 122 Fed. Cl. at 385-97. 3 Citations to plaintiff’s exhibits are identified as “PX___,” defendant’s exhibits are identified as “DX___,” and the parties’ joint exhibits are identified as “JX___.”

2 Initial construction continued steadily until February and March, 2008 when Meridian encountered subsurface flows and soil issues causing stability problems for construction. See, e.g., PX17; JX57. Meridian alerted the Corps to these issues, see JX57, and in response, the Corps issued additional requests for proposals, see, e.g., JX159, and modifications, see, e.g., JX118 (referencing modification R3). 4 Problems continued to arise throughout the construction process, increasing the project’s scope and duration. See, e.g., PX146 at 1-6 (detailing the issues and revised project schedule). Additional modifications were issued by the Corps in the months following, including the addition of a new access ramp via Modification R6 on May 8, 2008, see JX121, that increased the contract price and eventually led to schedule delays, see PX389 at 18- 19. Following further issues, the Corps issued a subsequent bilateral modification, modification R8, on June 5, 2008, which extended the schedule by twelve calendar days but deleted the additional work on the access ramp originally added in R6. See JX123. Modification R8 also included the following release language: “[T]his adjustment constitutes compensation in full on behalf of the Contractor . . . for all costs and markups directly or indirectly attributable for the change ordered, for all delays related thereto, for all extended overhead costs, and for performance of the change within the time frame stated.” JX123 at 2.

Further modifications were issued, see, e.g., JX125, as construction continued into late June 2008 to the point that concrete could be poured for the channel invert, see, e.g., JX78 at 167-69. Flooding of the work site, beginning about this same time, led to numerous delays in the work plan. See JX78 at 158 (“Work was stop[p]ed because of the flood and the damage[] that resulted from it. Additionally, Meridian is unable to proceed with their work plans for the weekend.”). This flooding continued to adversely affect progress on the worksite, with Meridian reporting incidents of continued flooding, including from July 6 to 11, 2008 and on July 14, 2008, see PX56-61, and between August 3, 2008 and September 26, 2008, see PX62-102.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Holland v. United States
621 F.3d 1366 (Federal Circuit, 2010)
Brock & Blevins Company, Inc. v. The United States
343 F.2d 951 (Court of Claims, 1965)
Winn-Senter Const. Co. v. United States
75 F. Supp. 255 (Court of Claims, 1948)
Meridian Engineering Company v. United States
122 Fed. Cl. 381 (Federal Claims, 2015)
Meridian Engineering Company v. United States
130 Fed. Cl. 147 (Federal Claims, 2016)
Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)
A & K Plumbing & Mechanical, Inc. v. United States
30 Cont. Cas. Fed. 70,877 (Court of Claims, 1983)
King Fisher Marine Service, Inc. v. United States
35 Cont. Cas. Fed. 75,616 (Court of Claims, 1989)
John Massman Contracting Co. v. United States
37 Cont. Cas. Fed. 76,084 (Court of Claims, 1991)
Sikorsky Aircraft Corp. v. United States
105 Fed. Cl. 657 (Federal Claims, 2012)
Merritt-Chapman & Scott Corp. v. United States
528 F.2d 1392 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
Meridian Engineering Company v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meridian-engineering-company-v-united-states-uscfc-2019.