King Fisher Marine Service, Inc. v. United States

35 Cont. Cas. Fed. 75,616, 16 Cl. Ct. 231, 1989 U.S. Claims LEXIS 10
CourtUnited States Court of Claims
DecidedJanuary 24, 1989
DocketNo. 569-85C
StatusPublished
Cited by23 cases

This text of 35 Cont. Cas. Fed. 75,616 (King Fisher Marine Service, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
King Fisher Marine Service, Inc. v. United States, 35 Cont. Cas. Fed. 75,616, 16 Cl. Ct. 231, 1989 U.S. Claims LEXIS 10 (cc 1989).

Opinion

OPINION

REGINALD W. GIBSON, Judge:

Introduction

The present action is before the court on the United States’ (government or defendant) motion for summary judgment based upon the affirmative defense of accord and satisfaction, and plaintiff’s cross-motion. Plaintiff, King Fisher Marine Service, Inc. (King Fisher) filed a complaint in this court on September 30,1985, alleging entitlement to an equitable adjustment for modifications (change orders) made by the government to contract no. DACW64-83-C-0041 (the contract), which required King Fisher to dredge a segment of the Gulf Intracoastal Waterway in Texas.

Jurisdiction of this court is based on the Contract Disputes Act, 41 U.S.C. § 601 et seq., and 28 U.S.C. § 1491.

After careful consideration of the merits of each party’s contentions, both in briefs and at oral argument, the court is constrained to grant defendant’s motion for summary judgment and to deny plaintiff’s cross-motion.

[232]*232 Statement of Facts

King Fisher, as the low bidder, was awarded government contract No. DACW64-83-C-0041, for the dredging of Gulf Intracoastal Waterway, Texas, Mile 297 to High Island in Jefferson, Chambers, and Galveston Counties, Texas, on June 24, 1983. Under said contract, King Fisher was to be paid $1,170,560.00. The contract also explicitly provided that modifications were unilaterally permitted to be made by the contracting officer on behalf of the United States. Construction began under the contract on October 13, 1983.

On February 3, 1984, the contracting officer ordered a change in the construction contract under General Provision #3, the contract provision which provides for such modification. This modification required King Fisher, with respect to Disposal Areas Numbers 22, 23, 24, and 25, to make the following changes:

1. Disposal Areas Nos. 22, 23 and 24
a. Shift the alignment of all perimeter levee construction, exclusive of the front levee adjacent to the waterway, approximately 6 feet to the interior of the disposal area to a position which abuts the existing levee’s interior edge of the crown.
* * * * * *
2. Disposal Area No. 25
* * * * * *
b. Provide 1 on 3 or flatter side slopes on the constructed borrow ditch between levee stations 20+00 and 44+25. Material excavated from providing the side slopes on the borrow ditch shall be placed within the borrow area.
c. Delete all fence repairs and construction.

This change was incorporated into Change Order FO-2, dated February 14, 1984, which was submitted to King Fisher by the contracting officer, who requested that King Fisher submit a proposal incorporating the changes. King Fisher submitted such a proposal on March 8, 1984, but was unable to reach an agreement with the contracting officer as to the price to be paid for such changes. Due to their inability to agree on an amicable price for such work, King Fisher submitted a formal claim to the contracting officer in the amount of $142,033.08 and a 29-day extension.

Performance under the contract was completed on October 28, 1984, while the claim was still pending. The contracting officer, notwithstanding, subsequently issued a decision denying King Fisher’s claim on January 21, 1985.

The parties continued to negotiate a price for the items in the change order, however, and on April 2, 1985, entered into an agreement with respect to same whereby King Fisher agreed to accept the sum of $33,-388.00 for all of the work performed under the change order. Said agreement enumerated, in great detail, the subject matter of the contract items encompassed therein. That is to say, the language of the modification agreement was in all material particulars identical to the language in the FO-2 change order. It also contained operative language indicating that the compensation paid, supra, was in full settlement of all claims. Defendant’s Motion for Summary Judgment (DMSJ) Appendix at 6.

Because the contractor refused to grant any further remuneration to plaintiff, in spite of its formal claim, King Fisher filed a complaint in this court on September 30, 1985, alleging that the government failed to make an equitable adjustment for the unilateral changes it ordered. Said complaint prays for $142,033.08 plus interest for additional costs incurred by King Fisher in performing under the contract modification and a 29-day extension, retroactive, to the time within which King Fisher had to complete performance under the contract.

The government has moved for summary judgment on the grounds that any and all of King Fisher’s claims with regard to the modification (change order) are barred by the doctrine of accord and satisfaction. King Fisher has cross-moved for summary judgment asking this court to hold that its claim is not barred by said doctrine.

Contentions of the Parties

Defendant

In support of its motion for summary judgment, the government’s argument is, [233]*233quite simply, that King Fisher’s claims filed in this court are identical to those which were the subject matter of an accord and satisfaction, signed by both parties, which expressly acknowledges compensation in full. Therefore, argues the government, King Fisher’s claim is forever barred by said doctrine, and summary judgment is appropriate.

Plaintiff

King Fisher, in opposition to defendant’s motion for summary judgment and in support of its cross-motion, argues that in accepting the $33,388.00 in settlement, it previously expressed an intent to reserve certain portions of the claim (certain items in the change order) for later resolution. As evidence of such an intent, plaintiff collaterally relies upon three letters dated November 9, 1984 (Ex. 14, Pltf’s Pre-Trial Submission), February 18, 1985 (Ex. 18, Pltf’s Pre-Trial Submission), and April 3, 1985, one day after the settlement agreement with the government had been executed (Ex. 13, Pltf’s Pre-Trial Submission). According to plaintiff, these three letters collectively evidence an express reservation of its rights with regard to a substantial portion of the items in the change order. Furthermore, says plaintiff, the parties also expressly reserved $100 from the settlement in order to preserve the existing claims by keeping the contract open, as contemplated in the letters.

Therefore, as plaintiff concludes, the settlement agreement entered into by the parties was merely a partial, not a full, settlement agreement. Plaintiff, therefore, cross-moves for summary judgment that its alleged reserved claims are not barred by accord and satisfaction.

Issue Presented

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pontchartrain Partners, LLC
Armed Services Board of Contract Appeals, 2025
The Haskell Company
Armed Services Board of Contract Appeals, 2024
WECC, Inc.
Armed Services Board of Contract Appeals, 2021
Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)
Jaynes v. United States
75 Fed. Cl. 218 (Federal Claims, 2007)
Axion Corp. v. United States
68 Fed. Cl. 468 (Federal Claims, 2005)
District of Columbia v. United States
67 Fed. Cl. 292 (Federal Claims, 2005)
AXA S.A. v. Union Pacific Railroad
269 F. Supp. 2d 863 (S.D. Texas, 2003)
W & F Building Maintenance Co. v. United States
56 Fed. Cl. 62 (Federal Claims, 2003)
Ryco Construction, Inc. v. United States
55 Fed. Cl. 184 (Federal Claims, 2002)
National Steel & Shipbuilding Co. v. United States
49 Fed. Cl. 579 (Federal Claims, 2001)
Starflight Boats v. United States
48 Fed. Cl. 592 (Federal Claims, 2001)
Safeco Credit & Fraley Associates, Inc. v. United States
44 Fed. Cl. 406 (Federal Claims, 1999)
Ed. Zueblin, A.G. v. United States
44 Fed. Cl. 228 (Federal Claims, 1999)
Green Management Corp. v. United States
42 Cont. Cas. Fed. 77,412 (Federal Claims, 1998)
TANO Automation, Inc. v. United States
939 F. Supp. 483 (E.D. Louisiana, 1996)
Thomas Creek Lumber & Log Co. v. United States
41 Cont. Cas. Fed. 76,971 (Federal Claims, 1996)
McLain Plumbing & Electrical Service, Inc. v. United States
39 Cont. Cas. Fed. 76,593 (Federal Claims, 1993)
CYR Construction Co. v. United States
27 Fed. Cl. 153 (Federal Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,616, 16 Cl. Ct. 231, 1989 U.S. Claims LEXIS 10, Counsel Stack Legal Research, https://law.counselstack.com/opinion/king-fisher-marine-service-inc-v-united-states-cc-1989.