The Haskell Company

CourtArmed Services Board of Contract Appeals
DecidedFebruary 22, 2024
Docket63291
StatusPublished

This text of The Haskell Company (The Haskell Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Haskell Company, (asbca 2024).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) The Haskell Company ) ASBCA No. 63291 ) Under Contract No. N40085-17-C-8331 )

APPEARANCE FOR THE APPELLANT: James E. Krause, Esq. James E. Krause, PA Jacksonville, FL

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Devin A. Wolak, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE TAYLOR ON THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT

In this appeal, The Haskell Company (Haskell or appellant) seeks payment for costs incurred due to unusually severe weather and seasonal differences allegedly resulting from government project design changes on a joint reserve center that pushed construction into adverse weather periods. The Navy filed a motion for summary judgment asserting the Board should deny Haskell’s claim because the appellant signed Modification No. A00001 (Mod 1) containing a release that resolved all costs, impact effect, and delays and disruptions, arising out of or incidental to the project design changes. Haskell opposes the motion alleging a material factual dispute exists as to whether the parties intended the release to include appellant’s current claim. Haskell also contends the Navy’s subsequent conduct manifested an intent in contradiction of the release terms. Based upon the current record and drawing all reasonable inferences in appellant’s favor, we deny the Navy’s motion since a material factual dispute exists as to whether the parties had a meeting of the minds with regards to the substance of the release.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

The parties filed numerous statements of facts and responses. 1 We set out the relevant facts for the purpose of this motion below.

1 On January 13, 2023, the government filed “Respondent’s Statement of Undisputed Material Facts in Support of its Motion for Summary Judgment.” On February 13, 2023, appellant filed “Appellant’s Response to Respondent’s Statement of I. The Contract and Design Change Modification

1. On September 21, 2017, the Naval Facilities Engineering Systems Command, Mid-Atlantic (NAVFAC or Navy) awarded firm fixed-price Contract No. N40085-17-C-8331 (the contract) to Haskell to design and build a joint reserve center in Des Moines, Iowa. (R4, tab 2.4 at 7614) 2

2. Haskell submitted a proposed design that included a sheet flow drainage system (R4, tab 3.2 at 7752). NAVFAC accepted Haskell’s proposed design and awarded it the contract (R4, tab 2.4 at 7616). The contract included FAR clauses 52.233-1, DISPUTES (MAY 2014), 52.242-14, SUSPENSION OF WORK (APR 1984), 52.243-4, CHANGES (JUN 2007), 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984), and DFARS clause 252.243-7002, REQUESTS FOR EQUITABLE ADJUSTMENT (DEC 2012) (id. at 7623-24). In its original baseline schedule, Haskell indicated it intended to start construction on April 27, 2018 (R4, tab 3.2 at 7896).

3. On April 4-5, 2018, Haskell provided its final completed design drawings to the Navy for review (R4, tab 3.1 at 7723). During the design review process, the Navy decided it wanted a different drainage system than the proposed slope-based site drainage design (id. at 7723-24; app. supp. R4, tab 20 ¶ 7 (supplemental declaration of Mr. Kenneth Duncan)). The parties agreed Haskell would make several design changes and negotiated an estimated price for the changes with a 42-day time extension with 21-days being compensable (id. at ¶ 9).

Undisputed Material Facts in Support of Respondent’s Motion for Summary Judgment.” Appellant, however, did not file a “Statement of Genuine Issues of Material Fact” in accordance with Board Rule 7(c)(1). The government then filed “Respondent’s Reply in Support of its Statement of Undisputed Material Facts in Support of Its Motion for Summary Judgment” and “Respondent’s Supplemental Statement of Undisputed Material Facts Concerning the Defenses Raised in Appellant’s Response to Defendant’s Motion for Summary Judgment.” On April 7, 2023, appellant filed “Appellant’s Supplementary Response to Respondent’s Statement of Undisputed Material Facts” and “Appellant’s Statement of Genuine Issues of Material Facts to Respondent’s Supplemental Statement of Undisputed Material Facts.” On May 12, 2023, the government filed “Respondent’s Surreply in Support of its Statement of Undisputed Material Facts in Support of its Motion for Summary Judgment” and “Respondent’s Reply in Support of its Supplemental Statement of Undisputed Material Facts Concerning the Defenses Raised in Appellant’s Response to Defendant’s Motion for Summary Judgment.” 2 The government’s Rule 4 file is Bates numbered with a six-digit number proceeded by “GOV.” Here, we delete the prefix and the leading zeroes. 2 4. On April 10, 2018, the Navy requested Haskell submit updated pricing to complete the various design changes (R4, tab 4.1 at 8065-66). On April 11, 2018, Haskell provided the Navy with its updated pricing and a request for a time extension, with compensable days, due to the estimated increased costs resulting from the Navy’s 27 design changes (R4, tab 4.1 at 8064-65). Haskell’s estimate of probable cost included a detailed cost summary for each of the 27 changes (R4 tab 2.6 at 7664-77). The probable cost estimate did not include any costs for future unanticipated weather impacts resulting from those changes (id.).

5. In an email dated April 20, 2018, the Navy informed Haskell it intended to issue a modification without further negotiations (R4, tab 4.1 at 8064). The Navy indicated the modification should include “a statement to the effect that this captures the cost and time of all changes, delays, and extra effort expended in the design phase” and Haskell should let the Navy know if that was not the case (id.). Mr. Kenneth Duncan, Haskell’s Director of Project Development on the contract, declares the parties did not discuss any release of rights regarding future changes or claims during any of the discussions surrounding the design change (app. supp. R4, tab 20 ¶ 11).

6. The Navy provided Haskell authorization to proceed with the design changes on May 1, 2018 (R4, tab 3.1 at 7736). Haskell agreed to proceed with the work even though the government had not yet issued the formal modification (app. supp. R4, tab 20 ¶ 12). Haskell began construction work on May 10, 2018 (R4, tab 3.2 at 7974).

7. On July 12, 2018, Mr. Duncan sent an email to the new Navy contracting officer, Mr. Alex Wingert, reminding him that the Navy had not yet issued the design-change modification (R4, tab 3.2 at 7958). NAVFAC brought Mr. Wingert on as a new hire in July 2018 (app. supp. R4, tab 20 ¶ 12). Mr. Duncan further advised Mr. Wingert that Haskell intended to submit a request for equitable adjustment (REA) for “weather delays” due to the “excessive amount of rain since we mobilized” (R4, tab 3.2 at 7958).

8. On August 23, 2018, the Navy issued Mod 1 pursuant to the changes clause, FAR 52.243-4, CHANGES, to address the site drainage design phase and other changes (R4, tab 2.6). The modification included the phrase “Design Phase Changes” in its description paragraph (id. at 7659) and incorporated all the changes identified in Haskell’s April 11, 2018, estimated model of probable cost (id. at 7660). The modification granted Haskell a 42-day time extension to the contract completion date due to the change (id. at 7660). The modification also increased the total contract price by $485,217 from $19,080,569 to $19,565,786 (id.).

3 The modification included the following “Modification Acceptance” language:

Acceptance of this modification by the contractor constitutes an accord and satisfaction and represents payment in full for both time and money and for any and all costs, impact effect, and for delays and disruptions arising out of, or incidental to, the work as herein revised.

(Id.).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Diebold, Inc.
369 U.S. 654 (Supreme Court, 1962)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Holland v. United States
621 F.3d 1366 (Federal Circuit, 2010)
Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Koules v. Euro-American Arbitrage, Inc.
689 N.E.2d 411 (Appellate Court of Illinois, 1998)
Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)
King Fisher Marine Service, Inc. v. United States
35 Cont. Cas. Fed. 75,616 (Court of Claims, 1989)
Collazo Contractors, Inc. v. Winter
221 F. App'x 993 (Federal Circuit, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
The Haskell Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-haskell-company-asbca-2024.