Meridian Engineering Company v. United States

885 F.3d 1351
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 20, 2018
Docket2017-1584
StatusPublished
Cited by20 cases

This text of 885 F.3d 1351 (Meridian Engineering Company v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meridian Engineering Company v. United States, 885 F.3d 1351 (Fed. Cir. 2018).

Opinion

Wallach, Circuit Judge.

Meridian Engineering Company ("Meridian") appeals two final decisions of the U.S. Court of Federal Claims determining, inter alia, that (1) Meridian did not meet standards of proof to show that the United States ("Government") breached certain contractual obligations and its duty of good *1354 faith and fair dealing in a dispute under the Contract Disputes Act, 41 U.S.C. §§ 601 - 613 (2006) ("CDA") related to the construction of a flood control project in Nogales, Arizona, see Meridian Eng'g Co. v. United States (Meridian I) , 122 Fed.Cl. 381 , 384, 400 n.25, 426 (2015) ; J.A. 3000-53 (Second Amended Complaint), and (2) Meridian was owed certain monies for equitable adjustment and interest on the payments running from the date Meridian submitted its claim, January 7, 2014, see Meridian Eng'g Co. v. United States (Meridian II) , 130 Fed.Cl. 147 , 172 (2016). We have jurisdiction pursuant to 28 U.S.C. § 1295 (a)(3) (2012). We affirm-in-part, vacate-in-part, reverse-in-part, and remand.

BACKGROUND 1

In 2007, Meridian entered into a contract with the Government to construct flood control structures, referred to as the Chula Vista Project. Meridian I , 122 Fed.Cl. at 385-86 . The Project contemplated construction of several concrete channels, relocation of a sewer line, and dewatering and water diversion. See J.A. 1044-627 (Contract). After commencing the Project, Meridian encountered a series of problems relating primarily to what it deemed "subsurface organic/unsuitable material," specifically, "a layer of dripping saturated dark clay material under which a clean layer of sand is producing water" that had "the potential for serious structural damage." J.A. 1810; see Meridian I , 122 Fed.Cl. at 388 (describing "softer-than-anticipated soils"), 390-92 (describing modifications pursuant to discovery of "saturated soils"). Meridian notified the Government about these problems, and the Government issued several Contract modifications in response. See Meridian I , 122 Fed.Cl. at 388-90 (describing modifications for increase in allotted funds for larger pipe size, addition of a reinforced concrete access ramp, investigation of soil properties, remediation of saturated soils, and additional sheet piling). Eventually, the Government directed Meridian to suspend work on the Project in January 2009 following a series of structural failures, see J.A. 3127-28, and, while minor work continued, the Government ultimately terminated the Project following a September 2009 final inspection of the Project site, see Meridian I , 122 Fed.Cl. at 394-96 .

Following the parties' disagreements over payment owed to Meridian, Meridian filed suit in the Court of Federal Claims for breach of contract, breach of the duty of good faith and fair dealing, and a violation of the CDA. See J.A. 127, 3000-53. The Government conceded liability for costs relating to three counts of Meridian's Second Amended Complaint (Counts VII-IX), which were the subject of a separate damages trial. See J.A. 3032-36 (Count VII (Suspension of Work), Count VIII (Channel Fill), Count IX (Interim Protection) ). See generally Meridian II , 130 Fed.Cl. 147 . Because the Government now concedes the only issue with respect to Meridian II , 2 the remainder of this opinion addresses determinations from Meridian I .

DISCUSSION

I. Standard of Review

We review the Court of Federal Claims' legal conclusions de novo and its *1355 factual findings for clear error. See John R. Sand & Gravel Co. v. United States , 457 F.3d 1345 , 1353 (Fed. Cir. 2006), aff'd 552 U.S. 130 , 128 S.Ct. 750 , 169 L.Ed.2d 591 (2008). "A finding may be held clearly erroneous when the appellate court is left with a definite and firm conviction that a mistake has been committed." Ind. Mich. Power Co. v. United States , 422 F.3d 1369 , 1373 (Fed. Cir. 2005) (internal quotation marks, ellipsis, and citation omitted).

II. CDA Claims

Meridian asserts that the Court of Federal Claims erred when it "reasoned that only Meridian's breach of contract and breach of good faith and fair dealing claims presented a viable cause of action," because "Meridian's CDA claims should have been analyzed under the framework contemplated by the CDA, and not under the rubric of a 'breach' claim." Appellant's Br. 23, 24 (capitalization modified). However, Meridian does not explain the alternate CDA framework to which it refers, nor does it state how analysis under a different hypothetical framework would result in a finding in its favor. See id. at 22-25 (stating only that the use of the breach of contract standard "skewed" the Court of Federal Claims' analysis).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Group III Mgt., Inc.
Armed Services Board of Contract Appeals, 2026
First Street Contractors, LLC
Armed Services Board of Contract Appeals, 2026
HECO Pacific Manufacturing, Inc.
Armed Services Board of Contract Appeals, 2025
Pontchartrain Partners, LLC
Armed Services Board of Contract Appeals, 2025
Owens v. Bean
D. Nevada, 2025
The Haskell Company
Armed Services Board of Contract Appeals, 2024
Korte Construction Company
Armed Services Board of Contract Appeals, 2023
WECC, Inc.
Armed Services Board of Contract Appeals, 2021
Barlovento, LLC v. AUI, Inc.
D. New Mexico, 2021
200428-80604
Board of Veterans' Appeals, 2021
Baley v. United States
942 F.3d 1312 (Federal Circuit, 2019)
Rustler Construction, Inc. v. District of Columbia
211 A.3d 187 (District of Columbia Court of Appeals, 2019)
Walsh Construction Company
Federal Claims, 2018

Cite This Page — Counsel Stack

Bluebook (online)
885 F.3d 1351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meridian-engineering-company-v-united-states-cafc-2018.