Hamp's Construction LLC v. Secretary of the Army

Court of Appeals for the Federal Circuit·Decided June 30, 2026·No. 24-1528·Published

Opinion

United States Court of Appeals for the Federal Circuit

HAMP'S CONSTRUCTION LLC,

Appellant

v.

SECRETARY OF THE ARMY,

Appellee

2024-1528

Appeal from the Armed Services Board of Contract Appeals in No. 62257, Administrative Judge J. Reid Prouty, Administrative Judge Owen C. Wilson, Administrative Judge Reba Page.

Decided: June 30, 2026

MATTHEW WAYNE WILLIS, Arnold, Willis & Conway, Dyersburg, TN, argued for appellant. Also represented by SAMMIE LEO ARNOLD.

BORISLAV KUSHNIR, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington , DC, argued for appellee. Also represented by PATRICIA M. MCCARTHY, CORINNE ANNE NIOSI, BRETT SHUMATE.

2 HAMP’S CONSTRUCTION LLC v. SECRETARY OF THE ARMY

Before LOURIE, REYNA, and CUNNINGHAM, Circuit Judges. CUNNINGHAM, Circuit Judge.

Hamp’s Construction LLC (“Hamp’s Construction”) appeals a decision of the Armed Services Board of Contract Appeals (“Board”) denying Hamp’s Construction’s Type I differing site condition claim. Hamp’s Construction LLC, ASBCA No. 62257, 2024 WL 669328 (Feb. 2, 2024) (“Decision ”) (App’x 1–33). 1 For the reasons explained below, we affirm.

I. BACKGROUND

This appeal concerns a Type I differing site condition claim related to a flood control project for the Trapp Canal in Jefferson Parish, Louisiana. Decision at 1–3. On July 12, 2012, the United States Army Corps of Engineers (“the Corps”) issued a solicitation for the Trapp Canal project . Decision at 3; S. App’x 1. As originally issued, the solicitation contained a default prohibition forbidding the use of barges, but on August 3, 2012, the Corps issued an amendment rescinding that provision. Decision at 3; S. App’x 3–4, 41. The solicitation incorporated by reference Federal Acquisition Regulation (“FAR”) clauses 52.236-2 Differing Site Conditions, and 52.236-3 Site Investigation and Conditions Affecting the Work. 2 Decision at 3;

1 We refer to the appendix filed by Hamp’s Construction , ECF No. 16, as “App’x” and the supplemental appendix filed by the Secretary of the Army, ECF No. 24, as “S. App’x.” Because the reported version of the Board’s decision is not paginated, citations in this opinion are to the version of the Board’s decision included in the Appendix. For example, Decision at 1 is found at App’x 1.

2 48 C.F.R. § 52.236-2(a) states, in relevant part: “The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the

HAMP’S CONSTRUCTION LLC v. SECRETARY OF THE ARMY 3

S. App’x 14; see 48 C.F.R. §§ 52.236-2, 52.236-3. The solicitation also included cross-sections of the canal and ten boring logs taken at various places along the canal in 2008. Decision at 3; S. App’x 43–64. 3 Mr. Jens Lorenz, an employee of Cheniere Construction , Inc. (“Cheniere”), performed two pre-bid site inspections of the Trapp Canal and took a number of photographs of the site. Decision at 4–5, 20–21; App’x 98–102. On August 21, 2012, Hamp’s Construction submitted a bid with Cheniere as its subcontractor. Decision at 5; S. App’x 65. Hamp’s Construction was awarded the contract on September 4, 2012, and work on the project began shortly thereafter . Decision at 5; S. App’x 65, 66.

The worksite consisted of four quadrants: northwest, northeast, southwest, and southeast. The canal divided the site between east and west, and a local road divided the site between north and south. Decision at 5–6. The first phase of the project involved the northern quadrants, and

Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract[.]”

48 C.F.R. § 52.236-3(b) states: “The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.”

3 Another set of borings was taken in 2000, but these boring logs were not included or specifically identified in the solicitation. Decision at 4.

4 HAMP’S CONSTRUCTION LLC v. SECRETARY OF THE ARMY

Hamp’s Construction did not encounter any major problems while working in those areas. Decision at 6–7.

However, in May 2013, Hamp’s Construction’s troubles began while preparing for work on the southern quadrants. Decision at 7. At that time, it discovered that part of the bank of the southwest quadrant had collapsed, and there was a depression measuring approximately 100 to 200 feet by 25 feet. Decision at 7. Hamp’s Construction found four additional areas of failure and determined it would not be safe “to operate loaded construction trucks on the southwest bank,” instead opting to use equipment operating from barges. Decision at 8. These problems with bank stability and need to change means of construction significantly delayed completion of the project. Decision at 8, 25.

Hamp’s Construction communicated its concerns about the southwest bank to the Corps. Decision at 8, 24. On November 6, 2018, Hamp’s Construction submitted a request for equitable adjustment (“REA”) of $3,948,833 and an extension of 237 calendar days to complete the project based on “encounter[ing] differing site conditions and defective specifications on the west bank of Trapp Canal, south of Harvey Blvd.” Decision at 25 (internal quotation marks omitted); S. App’x 69–73. On March 1, 2019, the contracting officer denied the REA, citing an absence of proof “that a differing site condition existed” under the FAR 52.236-2 criteria. Decision at 25; S. App’x 74–75. Hamp’s Construction responded, requesting that its REA be converted to a claim pursuant to the Contract Disputes Act, certifying its proposal under the Disputes clause of the contract, and requesting a final decision from the contracting officer. Decision at 25; S. App’x 76. On August 30, 2019, the contracting officer denied Hamp’s Construction’s claim. Decision at 25; S. App’x 77–96.

Hamp’s Construction appealed to the Board, which held a hearing in December 2022. App’x 36, 39, 42. On February 2, 2024, the Board denied the appeal, concluding that

HAMP’S CONSTRUCTION LLC v. SECRETARY OF THE ARMY 5

“[t]hough [Hamp’s Construction] undoubtedly encountered conditions on the southwest bank of the Trapp Canal that it did not expect and which caused it delays and increased costs,” the Board “[did] not find that [Hamp’s Construction] proved a necessary element of a Type I differing site condition , that the conditions found were contrary to the representations in the contract documents—primarily because . . . there were no representations in those documents for the area where [Hamp’s Construction] encountered its problems.” Decision at 33.

Hamp’s Construction timely appealed. We have jurisdiction under 41 U.S.C. § 7107(a)(1)(A) and 28 U.S.C. § 1295(a)(10).

II. STANDARD OF REVIEW

“We review de novo the Board’s conclusions of law, including . . . the interpretation of a government contract.” Cooper/Ports Am., LLC v. Sec’y of Def., 959 F.3d 1373, 1377 (Fed. Cir. 2020) (internal quotation marks and citations omitted). “[T]he decision of the [Board] on a question of fact is final and conclusive and may not be set aside unless the decision is—(A) fraudulent, arbitrary, or capricious ; (B) so grossly erroneous as to necessarily imply bad faith; or (C) not supported by substantial evidence.” 41 U.S.C. § 7107(b)(2); see Boeing Co. v. Sec’y of Air Force, 983 F.3d 1321, 1333 (Fed. Cir. 2020).

III. DISCUSSION

Free access — add to your briefcase to read the full text and ask questions with AI

Hamp's Construction LLC v. Secretary of the Army, (Fed. Cir. 2026).

Hamp's Construction LLC v. Secretary of the Army (Hamp's Construction LLC v. Secretary of the Army) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Renda Marine, Inc. v. United States
509 F.3d 1372 (Federal Circuit, 2007)
Pacific Alaska Contractors, Inc. v. The United States
436 F.2d 461 (Court of Claims, 1971)
H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)
Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)
cooper/ports America, LLC v. Secretary of Defense
959 F.3d 1373 (Federal Circuit, 2020)
The Boeing Company v. Secretary of the Air Force
983 F.3d 1321 (Federal Circuit, 2020)