Randa/madison Joint Venture III v. Gregory Robert Dahlberg, Acting Secretary of the Army

239 F.3d 1264, 2001 U.S. App. LEXIS 1736, 2001 WL 101957
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 7, 2001
Docket00-1129
StatusPublished
Cited by37 cases

This text of 239 F.3d 1264 (Randa/madison Joint Venture III v. Gregory Robert Dahlberg, Acting Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Randa/madison Joint Venture III v. Gregory Robert Dahlberg, Acting Secretary of the Army, 239 F.3d 1264, 2001 U.S. App. LEXIS 1736, 2001 WL 101957 (Fed. Cir. 2001).

Opinion

LINN, Circuit Judge.

Randa/Madison Joint Venture III (“Randa”) seeks review of a final decision of the Armed Services Board of Contract Appeals denying Randa’s appeal from a deemed denial of its claim by the United States Army Corps of Engineers (the “Corps”). Randa’s claim is that it encountered excessive groundwater in the performance of its contract with the government, constituting both a Type 1 and a Type 2 differing site condition, as defined by the contract. In re Randa/Madison Joint Venture III, No. 49452, 1999 WL 669546 (A.S.B.C.A. Aug. 27, 1999). Because the board’s determination that Randa did not prove either a Type 1 or Type 2 differing site condition is supported by substantial evidence and does not otherwise contain any reversible error, we affirm the board’s denial of Randa’s appeal.

BACKGROUND

The government, through the Corps, issued a solicitation on March 1, 1994 for work that included the construction of a sewage pumping station, also called a pump house. Id., slip op. at 1. The government retained a separate firm, CME Engineering, Inc. (“CME”), to prepare the design documents, which were to be “sufficiently detailed to permit construction contractors to submit responsive bids without the necessity to visit the project during bidding.” 1 Id. at 2. The Corps had agreed to perform the necessary geotechnical investigation, including drilling and testing *1267 to determine various characteristics of the subsurface, at CME’s direction. Id.

The pump house foundation was to extend forty feet below the surface and it was necessary to determine the extent, if any, of subsurface water at the pump house location. Any subsurface water would have to be removed during construction to a depth of five feet below the foundation, or forty-five feet below the surface. This process is called dewatering. Id. at 3.

The Corps drilled at least twelve holes, called soil borings, and performed specific tests on the soil that was removed. One of these soil borings, referred to as DH-11, was close to the pump house excavation and is, therefore, of particular relevance. Id. at 8. The specific tests performed on the soil borings are designed to allow contractors bidding on the contract to estimate the coefficient of permeability, referred to simply as permeability. A higher value of permeability indicates a soil type that allows water to flow more freely, which means that the dewatering process will be more difficult.

The first test was a blow count test, which is performed while drilling the soil borings. In drilling the soil borings, the Corps used a widely accepted boring methodology in which a soil sampler is driven into the earth by striking the sampler with a known and constant force. The number of strikes (blows), referred to as the blow count, required to drive the sampler each additional foot was measured and recorded. Blow count tests provide a measure of the soil density, with denser soil generally being less permeable. Id. at 4.

In addition, the soil samples were removed from the sampler, placed in jars, labeled, and classified. Id. at 4. The soil samples were classified using the Unified Soil Classification System, a widely accepted soil classification system having fifteen categories of different soil types, each with a two-letter symbol. Id. at 5. Published charts exist that correlate these different soil types with different permeability ranges. See id. Boring logs were created showing the blow count at various depths, along with the different soil types encountered. The boring logs also indicate the depth of the water table.

The Corps also performed additional tests, including a sieve test, which measures the percentage of the soil that passes each of a series of gradually finer sieves. Id. The results of the sieve test were plotted in a set of gradation curves. Id. Two variables that a sieve test can provide are the percentage of fine grained material and the grain size distribution of the soil samples. Id. These two variables, along with the soil density from the blow count test, typically provide a better estimate of the permeability than that provided by the looking only at the soil type. Id. at 6. It is well known in the industry that this estimate of permeability can be made by using a Moretrench chart. Id. Three different Moretrench charts are available, one each for loose, medium, and dense soils. Id. Because there is no separate Moretrench chart for very dense soils, the dense soil chart is also used for very dense soils. Id.

The actual contract documents included the boring logs, but not the gradation curves or other test results. Id. at 7. The gradation curves and other test results, as well as the soil samples themselves, were made available for inspection at a Corps office.

Randa and the Corps entered into a contract to perform the required dewater-ing work. Two clauses of the contract addressed the materials that were made *1268 available for inspection. The first is a standard clause, entitled “Site Investigation and Conditions Affecting the Work,” which is routinely included in government contracts and is standardized in the Code of Federal Regulations. The Site Investigation clause provided, in part, that:

The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.

Randa, slip op. at 2 (emphasis added); see also 48 C.F.R. § 52.236-3(a) (2000) (FAR 52.236-2(a)). This clause, at least facially, placed on Randa any risk associated with not inspecting the “exploratory work,” which Randa conceded at oral argument included the gradation curves.

The second clause is a standard clause entitled “Physical Data,” which is also routinely included in government contracts. Only a portion of the language in the “Physical Data” clause is standardized in the Code of Federal Regulations, with the remainder being left to the parties to determine. Section 2.2 of the “Physical Data” clause, entitled “Explorations” in the present contract, is part of that remainder left to the parties to decide. The “Physical Data” clause provided, in part, that:

2. PHYSICAL DATA

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meltech Corporation, Inc.
Armed Services Board of Contract Appeals, 2025
Skanska USA Civil Southeast, Inc.
Armed Services Board of Contract Appeals, 2025
Hamp's Construction LLC
Armed Services Board of Contract Appeals, 2024
L.C. Gaskins Construction Co., Inc.
Armed Services Board of Contract Appeals, 2017
Zafer Construction Company
Armed Services Board of Contract Appeals, 2017
Walsh Construction Co. v. United States
132 Fed. Cl. 282 (Federal Claims, 2017)
Columbia State Bank (formerly Appeal of Castle-Rose, Inc.)
Armed Services Board of Contract Appeals, 2016
Meridian Engineering Company v. United States
122 Fed. Cl. 381 (Federal Claims, 2015)
Old Veteran Construction, Inc. v. United States
121 Fed. Cl. 346 (Federal Claims, 2015)
Optimum Services, Inc.
Armed Services Board of Contract Appeals, 2015
C.R. Pittman Construction Co., Inc.
Armed Services Board of Contract Appeals, 2015
weston/bean Joint Venture v. United States
115 Fed. Cl. 215 (Federal Claims, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
239 F.3d 1264, 2001 U.S. App. LEXIS 1736, 2001 WL 101957, Counsel Stack Legal Research, https://law.counselstack.com/opinion/randamadison-joint-venture-iii-v-gregory-robert-dahlberg-acting-cafc-2001.