Walsh Construction Co. v. United States

132 Fed. Cl. 282, 2017 U.S. Claims LEXIS 612, 2017 WL 2374856
CourtUnited States Court of Federal Claims
DecidedMay 31, 2017
Docket16-845
StatusPublished
Cited by3 cases

This text of 132 Fed. Cl. 282 (Walsh Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walsh Construction Co. v. United States, 132 Fed. Cl. 282, 2017 U.S. Claims LEXIS 612, 2017 WL 2374856 (uscfc 2017).

Opinion

Contract Disputes Act (“CDA”), 41 U.S.C. §§ 7101-7109;

Federal Acquisition Regulation (“FAR”), 48 C.F.R, §§ 52.223-1, 52.243-5;

Rules Of the United States Court of Federal Claims (“RCFC”) 12(b)(1), 15(a)(2); -

Tucker Act Jurisdiction, 28 U.S.C. § 1491.

MEMORANDUM OPINION DENYING THE GOVERNMENT’S MOTION TO DISMISS COUNTS I AND II OF THE AMENDED COMPLAINT AND STAYING THE CASE FOR THREE MONTHS TO AFFORD THE CONTRACTING OFFICER THE OPPORTUNITY TO CONSIDER THE MERITS OF COUNT II

BRADEN, Chief Judge.

I. FACTUAL BACKGROUND. 1

On August 17, 2012, the United States Army Corps of Engineers (the “Army Corps”) awarded Contract No. W912DR-12-C-011 (the “Contract”) to Walsh Construction Company (‘Walsh”), to build a Defense Logistics Agency (“DLA”) facility in New Cumberland, Pennsylvania (the “Project”). Gov’t App’x at A3-30 (8/17/12 Contract). The August 17, 2012 Contract required Walsh to' construct a number of “drilled piers,” ie., concrete-filled columns drilled into the ground and used to support a building’s foundation. Gov’t App’x at A5-A21.

On November 26, 2012, Walsh entered into a subcontract with Ammero Construction Services, LLC (“Ammero”), under which Ammero was to furnish and install 272 drilled piers. Compl. Ex. A (11/26/12 Ammero Subcontract). On December 4, 2012, Ammero subcontracted that work to Richard Goettle, Inc. (“Goettle”). Compl. Ex. B (12/4/12 Goet-tle Subcontract). Goettle was required to drill shafts into the ground down to a certain depth, or “tip elevation.” Amend. Compl, ¶¶ 9-10. The “tip elevations,” however, were not calculated by the Army Corps until after the award of the August 17, 2012 Contract. Amend. Compl. ¶¶ 9-12. The Army Corps also inspected the “tip elevation” of each newly drilled shaft, to ensure it met the contract specifications prior to the installation of the drilled piers. Amend. Compl. ¶ 13.

Goettle drilled shafts down to the tip elevation, as specified by the Army Corps, and then moved its drilling equipment to the next shaft. Amend, Compl. ¶ 15. But, during inspection, the Army Corps began to recalculate and set new tip elevations, ie., “revised tip elevations.” Amend. Compl. ¶15. This required Goettle to move its drilling equipment back to previously drilled shafts in order to re-drill the shafts to the Army Corps’ new tip elevations, Amend. Compl. ¶ 15. The Army Corps continued to conduct additional re-inspections, requiring Goettle to continue to make additional equipment moves. Amend. Compl. ¶ 15. In fact, the Army Coi’ps’ inspections and re-inspections forced Goettle to make 471 additional moves to and from the drill shafts, resulting in *285 significant additional costs. Amend. Compl. ¶ 27. In order to adhere to the Project schedule, Goettle was required to acquire additional drilling equipment and personnel. Amend. Compl. ¶ 28.

In addition, Goettle encountered obstructions during the drilling of five of the required shafts, ie., shaft numbers L-2, L-3, L-4, N.8-3, and N.8-4 (collectively referred to as the “Five Problem Shafts”). Amend. Compl. ¶¶ 35-38. During the drilling of the Five Problem Shafts, Goettle encountered large slabs of rock, weathered rock, voids, open fractures, and open joints that caused the shafts to collapse. Amend. Compl. ¶37.

On November 30, 2015, Walsh, acting on behalf of Goettle, submitted a Request For Equitable Adjustment (“REA”) for the “additional work at drilled shafts due to differing site conditions and disruption of work flow due to unnecessary inspections,” and requested costs in the amount of $8,763,119.00 Gov’t App’x at A45. The November 30,' 2015 REA incorporated two documents Goettle provided Walsh: Goettle’s July 30, 2014 Request for Change Order (“RCO”), in the amount of $7,047,220.00, and Goettle’s revised March 19, 2015 RCO, in the amount of $7,100,112.00. Compl. Ex. C. (7/30/14 RCO); see also Gov’t App’x at A47 (3/19/15 Revised RCO). 2

Together, the November 30, 2015 REA, and RCOs incorporated therein, provided two bases for an equitable adjustment. First, Walsh requested an equitable adjustment for the “Five Problems Shaft Issue,” that presented a “differing site condition” under Federal Acquisition Regulation (“FAR”) 52.243-5. 3 Gov’t App’x at A54-A60. Next, Walsh requested an equitable adjustment for the “Downhole Inspection Issue,” ie„ reimbursement for additional work undertaken by Goettle as a result of the Army Corps’ inspections and re-inspections of the drill shafts. Gov’t App’x at A60-A62. Walsh described the “Downhole Inspection Issue” as a differing site condition. Gov’t App’x at A60.

On April 18, 2016, an Army Corps Contracting Officer (the “CO”) issued a final decision that denied the November 30, 2015 REA in its entirety. Compl. Ex. D at 31. With respect to the Five Problem Shafts, the CO found that the conditions encountered were not materially different from those stated in the August 17, 2012 Contract, Compl. Ex. D. at 36-41. With respect to the Down-hole Inspection claim, the CO found that the Army Corps’ inspection program was a contract requirement and therefore could not be considered a differing site condition under FAR 52.243-5. Compl. Ex. D at 49-50. In addition, the CO found that the Downhole Inspection claim failed because the August 17, 2012 Contract included an “Inspection of Construction” clause, providing that all work was “subject to Government inspection ... to ensure strict compliance with the terms of the contract.” Compl. Ex. D at 50.

II. PROCEDURAL HISTORY.

On July 19, 2016, Walsh, acting on behalf of Ammero and Goettle (“Plaintiffs”), filed a Complaint in the United States Court of Federal Claims. Compl. ¶ 1. The July 19, 2016 Complaint alleged three counts: Count One alleged that the “Downhole Inspection *286 Issue” resulted in Government-caused delay and “additional costs” in the amount of $6,415,974.00; Count Two alleged that the Army Corps breached the duty of good faith and fair dealing by “subjecting Goettle to a myriad of unnecessary and abusive additional equipment, tooling and labor costs,” for which damages in the amount of $6,415,974.00 were owed; and Count Three alleged a differing site conditions claim related to the “Five Problems Shafts,” for which damages in the amount of $631,247.00 were owed. Compl. ¶¶ 21-41.

On October 19, 2016, the Government filed an Answer. EOF No. 6. On December 12, 2016, the parties submitted a Joint Preliminary Status Report. EOF No. 7. On December 20, 2016, the court convened a telephone status conference. On January 12, 2017, the parties submitted a Joint Proposed Trial Schedule and on January 13, 2017, the court entered a Scheduling Order. ECF Nos. 8-9.

On February 13, 2017, Plaintiffs filed an Amended Complaint, wherein Plaintiffs restated all three counts, but revised the damages sought under Counts One and Two, so that $2,897,367.00 was due for each Count. Amend. Compl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
132 Fed. Cl. 282, 2017 U.S. Claims LEXIS 612, 2017 WL 2374856, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walsh-construction-co-v-united-states-uscfc-2017.