Simulation Technology, LLC v. United States

103 Fed. Cl. 105, 2012 U.S. Claims LEXIS 25, 2012 WL 234417
CourtUnited States Court of Federal Claims
DecidedJanuary 25, 2012
DocketNo. 11-408C
StatusPublished
Cited by5 cases

This text of 103 Fed. Cl. 105 (Simulation Technology, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simulation Technology, LLC v. United States, 103 Fed. Cl. 105, 2012 U.S. Claims LEXIS 25, 2012 WL 234417 (uscfc 2012).

Opinion

OPINION

DAMICH, Judge:

This action involves a contract to build training simulation equipment for the United States Air Force (“USAF”). Plaintiff Simulation Technology, LLC, has filed an appeal under the Contract Disputes Act (“CDA”), 41 U.S.C. §§ 7101-7109, contesting the final decision of the Contracting Officer (“CO”) to reduce the amount due under the contract from $93,000 to $70,000 in consideration for Plaintiffs belated delivery of the equipment. In its complaint, Plaintiff alleges that it experienced excusable delays in the performance of critical activities, and therefore, its delivery was not late and it is entitled to the full amount under the contract.

The Government has filed a Motion to Dismiss for lack of subject matter jurisdiction. The Government alleges that the only claim Plaintiff made to the Contracting Officer was that the Government agreed to modify the delivery schedule and waived its right to demand consideration for the modification. The Government asserts that jurisdiction is improper because Plaintiff never presented the excusable delays claim to the Contracting Officer for a final decision, a prerequisite to this Court’s jurisdiction over the appeal.

Under the CDA, this Court has jurisdiction over a claim only if it is the same claim as presented to the contracting officer. This standard does not require exact identity between the claims, but only that they be sufficiently similar to give the contracting officer notice of the amount of and basis for the claim. The Court finds that it does not have jurisdiction over Plaintiffs appeal because its claim that the Government agreed to waive consideration for late delivery was insufficient to put the CO on notice of a claim that Plaintiff experienced excusable delays. Accordingly, the Government’s Motion to Dismiss must be granted.

I. Background

In September 2008, Plaintiff won a firm-fixed-price contract for $93,000 to build a High Mobility Multi-Purpose Wheeled Vehicle (“HMMWV” or humvee) Egress Assis[107]*107tance Trainer (“HEAT”). The HEAT is a humvee cab that is attached to a mechanical frame. The frame rotates the humvee cab to simulate a rollover so that military personnel inside the cab can practice escaping from an overturned vehicle. Def.’s Mot. Dismiss at 1. Under the contract, Plaintiff was to deliver the HEAT on or about January 24, 2009.

According to its complaint, after being awarded the contract Plaintiff immediately experienced problems that delayed its performance. Compl. ¶¶ 6-7. Plaintiff alleges that it was expecting a humvee cab that was ready to insert into the simulation. Plaintiff asserts that the cab the USAF provided was not ready to insert, but instead had significant amounts of equipment attached to the cab and some interior damage. Compl. ¶ 7. On February 26, 2009, Plaintiff advised USAF that the delivery schedule would need to be revised because it had been unable to obtain certain parts and supplies. Compl. ¶ 8. On March 18, 2009, Plaintiff advised USAF that it still was awaiting some parts. Compl. ¶ 9. Plaintiff and USAF continued to communicate in June and July 2009. At that time, the USAF requested consideration for the delivery delay, but the parties did not reach an agreement on what would be appropriate consideration. Compl. ¶ 10. On September 1, 2009, a USAF representative visited Plaintiffs facilities to see the progress of construction. Compl. ¶ 11. On December 23, 2009, the HEAT was delivered to the USAF, 11 months after the delivery date specified in the contract.

In March 2010, the Contracting Officer requested a $23,000 reduction in price as consideration for late delivery. Plaintiff rejected the offer, and on April 19, 2010, Plaintiff submitted a claim for the full balance due on the contract. In its claim to the Contracting Officer, Plaintiff asserted that the Government waived its right to consideration by agreeing to modify the delivery schedule without requiring consideration. Final Decision at 5 (filed under Pl.’s Notice, Sept. 21, 2011). It also asserted that the Government “waived any issues relating to delivery delays” by “formally accepting delivery.” Id.

On June 21, 2010, the Contracting Officer issued her final decision on Plaintiffs claim. The CO found that the Government did not waive consideration because it requested and discussed consideration with Plaintiff many times throughout the period of delay. Final Decision at 6. She concluded that the Government was entitled to an equitable price reduction of $23,000, which was equal to the costs incurred as a result of the delay.

On June 21, 2011, Plaintiff filed this complaint. Plaintiff alleges that it experienced excusable delays in the performance of critical activities under the contract, and therefore, its delivery of the HEAT complied with the contractual terms. Plaintiff claims it is entitled to the full $93,000 under the contract.

The Government has filed a Motion to Dismiss under Rules 12(b)(1) and 12(h)(3) of the Rules of the Court of Federal Claims (“RCFC”). The Government asserts that Plaintiff neither explicitly asserted an excusable delays claim to the Contracting Officer nor impliedly asserted it because Plaintiff did not present facts sufficient to establish an excusable delay claim. Because an appeal of a contracting officer’s decision must arise from the same claim, the Government argues that jurisdiction is improper.

II. Discussion

A. Standard of Review

A plaintiff bears the burden of establishing jurisdiction by a preponderance of the evidence. See Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 748 (Fed.Cir.1988) (“[O]nce the [trial] court’s subject matter jurisdiction [is] put in question, it [is] incumbent upon [the plaintiff] to come forward with evidence establishing the court’s jurisdiction”). When deciding a motion to dismiss pursuant to RCFC 12(b)(1), the Court is “obligated to assume all factual allegations to be true and to draw all reasonable inferences in [the] plaintiffs favor.” Henke v. United States, 60 F.3d 795, 797 (Fed.Cir.1995); see Folden v. United States, 379 F.3d 1344, 1354 (Fed.Cir.2004).

If subject matter jurisdiction is challenged, the plaintiff cannot rely merely on allegations in the complaint, but must instead bring forth relevant, competent proof to establish [108]*108jurisdiction. See McNutt v. Gen. Motors Acceptance Corp., 298 U.S. 178, 189, 56 S.Ct. 780, 80 L.Ed. 1135 (1936); Reynolds, 846 F.2d at 747-48. When ruling on a motion to dismiss for lack of subject matter jurisdiction, a court may consider evidence and resolve factual disputes over the jurisdictional facts. Reynolds, 846 F.2d at 747; see also Rocovich v. United States, 933 F.2d 991, 994 (Fed.Cir.1991); Int’l Mgmt. Servs., Inc. v. United States, 80 Fed.Cl. 1, 2 n. 2 (2007).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walsh Construction Co. v. United States
132 Fed. Cl. 282 (Federal Claims, 2017)
K-Con Building Systems, Inc. v. United States
131 Fed. Cl. 275 (Federal Claims, 2017)
E & E Enterprises Global, Inc. v. United States
120 Fed. Cl. 165 (Federal Claims, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
103 Fed. Cl. 105, 2012 U.S. Claims LEXIS 25, 2012 WL 234417, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simulation-technology-llc-v-united-states-uscfc-2012.