Cerberonics, Inc. v. United States

34 Cont. Cas. Fed. 75,384, 13 Cl. Ct. 415, 1987 U.S. Claims LEXIS 191
CourtUnited States Court of Claims
DecidedOctober 29, 1987
DocketNo. 630-85C
StatusPublished
Cited by60 cases

This text of 34 Cont. Cas. Fed. 75,384 (Cerberonics, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cerberonics, Inc. v. United States, 34 Cont. Cas. Fed. 75,384, 13 Cl. Ct. 415, 1987 U.S. Claims LEXIS 191 (cc 1987).

Opinion

OPINION

FUTEY, Judge.

This government contract case comes before the court on defendant’s motion to dismiss for lack of jurisdiction. Plaintiff, who initiated this action under the direct access provision of the Contract Disputes Act of 1978, 41 U.S.C. § 609(a)(1) (1982), seeks monetary relief from the Government under the terms of a service contract with the Department of the Navy. Defendant asserts that this court lacks jurisdiction because the claim(s) at bar differ from the claim(s) previously presented to and decided by the contracting officer. For the reasons discussed hereinafter, defendant’s motion to dismiss is denied.

Factual Background

Plaintiff entered into a contract (no. N68520-83-D-9033) with defendant, acting through the Department of the Navy’s Naval Aviation Logistics Center, on August 19, 1982, whereby plaintiff was to provide services to Navy and Air Force C-9 aircraft. Fixed-price line item services included operating material storerooms at specified sites, performing engine overhauls, repairs and inspections as required, furnishing a logistics management system at specified sites, and providing home office logistics support for material procurement. The contract also provided that plaintiff was to open and operate additional storerooms, as well as furnish the necessary support services, as the Navy might require.

In July 1983 defendant advised plaintiff to open an additional storeroom at the Naval Air Station (NAS) in Glenview, Illinois. By contract modification no. A00094, dated July 27, 1983, defendant issued an unpriced order to plaintiff to procure a spare jet engine for use in C-9 aircraft at Glenview NAS at a maximum price of $780,000. The engine was duly purchased, and on September 23, 1983, plaintiff submitted a price proposal to defendant in the total amount of $779,220. This proposal consisted of the following: $720,000 (engine cost), $1,500 (freight cost), and $57,720 (profit/fee).

On February 24, 1984, however, the Navy’s contracting officer issued a unilateral priced order definitizing the unpriced modification no. A00094 in the total amount of $722,391.50. This contract modification, no. A00139, reimbursed plaintiff for the following: $720,000 (engine cost), $417.50 (insurance), and $1,974 (freight cost). No amount was allowed the plaintiff for a profit or fee.

On May 21, 1984, plaintiff submitted a claim to the Navy contracting officer (CO) in the sum of $36,120. Plaintiff described this figure as “a fair and equitable fee to cover (1) finance charges incurred as a result of late payment by the Government as well as (2) CERBERONICS’ successful efforts to obtain the best available price.” On October 25, 1984, the contracting officer disallowed the claim. With respect to the two items of recovery sought by plaintiff, the contracting officer held that (1) “interest on borrowings and costs of financing capital are unallowable” under Defense Acquisition Regulation (DAR) 15-205.17, and (2) “Cerberonics is tasked by [417]*417virtue of the contract to obtain for the Government the best price available.”1

The current action, appealing the above decision, was filed in this court on October 25, 1985. Plaintiff seeks an equitable adjustment of the home office logistics support line item in the contract of $36,120, based on three alternative causes of action: (1) contract section H-6, entitled “Change of Base Location or Operational Requirements,” specifically provided for the equitable adjustment of fixed price items and award fee, such as “home office logistics support” for material procurement, affected by the establishment of an additional storeroom and changed requirements; (2) the work ordered by modification no. A00094 constitutes a change within the contract’s changes clause, entitling plaintiff to an equitable adjustment for additional costs and a reasonable profit thereon; (3) the work ordered by modification no. A00094 constitutes a constructive change of the contract, entitling plaintiff to an equitable adjustment for additional costs and a reasonable profit thereon.

On defendant’s motion, proceedings were suspended in December 1985 as the parties pursued negotiations toward a settlement. These negotiations were unavailing, however, and in March 1987 defendant filed its motion to dismiss. Oral argument was held on September 22, 1987.

Discussion

The direct access provision of the Contract Disputes Act of 1978 reads, in pertinent part, as follows: "... in lieu of appealing the decision of the contracting officer ... to an agency board, a contractor may bring an action directly on the claim in the United States Claims Court ...” (Such action) ... shall proceed de novo in accordance with the rules of the appropriate court.” 41 U.S.C. § 609(a)(1) and (3) (1982). Thus, an action in this court brought under the foregoing provision must be based on the same claim previously presented to and denied by the contracting officer. This jurisdictional requirement is spelled out in Mark Smith Construction Co., Inc. v. United States, 10 Cl.Ct. 540, 546 (1986):

A basic prerequisite to direct action in this court is that the contractor-plaintiff first must present its claim, in writing, to its duly designated contracting officer. 41 U.S.C. § 605(a), 609. Absent an ap-pealable decision (actual or deemed) by the contracting officer on the claim preferred here, the direct access provision found at 41 U.S.C. § 609 is not applicable by its own terms.

Defendant argues that the “claim preferred here” is not the same as that presented to the contracting officer, so that no appealable decision of the contracting officer underlies the case at bar. As such, plaintiff’s action would fail to satisfy the jurisdictional requirements of the direct access provision.

In determining whether a claim is properly before this court for the purpose of de novo review under the Contract Disputes Act (CDA), the Claims Court has generally looked to its “operative facts.” If the complaint brought here is based on the same set of operative facts underlying the claim presented to the contracting officer, then this court has jurisdiction under the CDA. Kunz Construction Co. v. United States, 12 Cl.Ct. 74, 79 (1987); J.F. Shea Co., Inc. v. United States, 4 Cl.Ct. 46, 54-55 (1983). Agency boards of contract appeals, to whom negative decisions of contracting officers can be appealed under 41 U.S.C. § 607 and 608, have looked variously to the “ultimate character”2 or “essential nature”3 of the original claim, or whether the operative or legal facts have [418]*418been changed on appeal.4 The critical test appears to be whether the scheme of adjudication prescribed by the CDA is undermined by the contractor’s claim on appeal— that is, by circumventing the statutory role of the contracting officer to receive and pass judgment on the contractor’s entire claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,384, 13 Cl. Ct. 415, 1987 U.S. Claims LEXIS 191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cerberonics-inc-v-united-states-cc-1987.