Al-Juthoor Contracting Co. v. United States

129 Fed. Cl. 599, 2016 U.S. Claims LEXIS 2117, 2016 WL 7469866
CourtUnited States Court of Federal Claims
DecidedApril 30, 2016
DocketNo. 14-5C
StatusPublished
Cited by3 cases

This text of 129 Fed. Cl. 599 (Al-Juthoor Contracting Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Al-Juthoor Contracting Co. v. United States, 129 Fed. Cl. 599, 2016 U.S. Claims LEXIS 2117, 2016 WL 7469866 (uscfc 2016).

Opinion

Contract Disputes Act; Partial Motion to Dismiss; Failure to State a Claim; Statute of Limitations; Equitable Tolling; Lack of Subject Matter Jurisdiction.

OPINION

HORN, J.

FINDINGS OF FACT

Plaintiff, Al-Juthoor Contracting Company, (Al-Juthoor), filed its original complaint in this court, alleging that defendant, the United States, had breached a contract between the parties by failing to pay plaintiff for work performed by plaintiff in furtherance of the contract. Alleging jurisdiction in this court is proper pursuant to the Tucker Act, 28 U.S.C. § 1491 (2012), and the Contract Disputes Act of 1978 (CDA), 41 U.S.C. § 7103 (2012), plaintiff requested damages on seven, separate claims in its original complaint, totaling $7,127,393.00 for the “changes, delays, interruptions, and extra repairs required to complete the contract.” In plaintiffs amended complaint, the damages sought were increased to a total amount of $8,061,647.00, in addition to an unspecified amount for a claim of the breach of the covenant of good faith and fair dealing. Plaintiff also seeks attorney’s fees and court costs. According to plaintiff, this action was filed after the contracting officer failed to respond to plaintiff’s certified claims within 60 days of the submission of a demand letter pursuant to 41 U.S.C. § 7104(b)(1) (2012) and 48 C.F.R. § 52.233-1(c).

Plaintiff asserts that the United States Army Corps of Engineers (Army Corps) awarded plaintiff task order 004 of Contract W916-QW-04-D-0014 (the contract) on September 18, 2004. Pursuant to the contract, plaintiff was to “construct and secure [a court] facility necessary to establish the rule of law in Iraq within the budgeted design/build amounts,” in the Al-Karkh neighborhood of Baghdad. Included within the contract was a Statement of Work which provided, “[t]he exact spot where the judicial facility will be built will be determined by PCO [the Procuring Contracting Officer].” Furthermore, the Statement of Work laid out the project requirements, including civil site [604]*604work, exterior/interior security needs, design criteria for the electrical power distribution system, how debris was to be removed, heating and air conditioning ventilation systems, plumbing, and other special requirements. Although the courthouse was scheduled to be completed by June 30, 2006, plaintiff alleges that a number of “difficulties arose during the course of the construction that delayed completion,”1 In its amended complaint,2 plaintiff indicates that construction was not completed, the courthouse was not handed over to the Iraqi government, and total contract performance was not completed until December 17, 2007.

Plaintiffs first alleged “difficulty” involved defendant’s delay in obtaining the required clearances for plaintiff to proceed with construction. Plaintiff maintains that defendant sent a Notice to Proceed on April 14, 2005, after which, time plaintiff began mobilizing its workers and equipment. Plaintiff asserts, however, that it could not begin construction on April 14, 2005, because the Iraqi Council of Judges had not yet authorized construction to begin. Plaintiff alleges that it did not request permission to begin construction from the Council of Judges because defendant instructed plaintiff that only the defendant could coordinate with the Council of Judges. On April 26, 2005, while awaiting approval, plaintiff claims it received a modification to the contract to build a “safe house” in the vicinity of the courthouse. Also on April 26, 2005, plaintiff claims it received a second3 Notice to Proceed. According to plaintiffs amended complaint, on May 21, 2005, “the Iraqi COJ [Council of Judges] approved the commencement of work on the courthouse” and the “Army Corps’ sent the third Notice to Proceed to Al-Juthoor in a letter from Daniel Hanas, Contracting Officer.” During the 37-day period between when the first and third notices to proceed were issued, plaintiff maintains it was forced to keep its equipment and personnel at the construction site, and was unable to undertake any replacement or additional work, because “at all times during this delay period, [plaintiff] was fully mobilized to begin work.” The amended complaint claims that the overhead costs caused by the delay totaled $682,860.00.

Plaintiffs second alleged “difficulty” involved defendant’s decision to relocate the site of the courthouse from the originally designated site. Although defendant appears to have retained the site responsibly under Statement of Work § 1.1, which states “[t]he exact spot where the judicial factory will be built will be determined by PCO [the Procuring Contracting Officer],” when the relocation order was issued, plaintiff claims it had already performed a site survey for the originally designated location, which cost $85,000.00. Plaintiff claims it then had to conduct a new site survey, at an additional expense of $85,000.00. Plaintiff maintains that “it is entitled to recover the costs it incurred in response to these directives from the PCO,” Furthermore, plaintiff claims that at the new location, the courthouse increased in size, which required “significantly more fill and grading to prepare for construction.” Plaintiff estimates the costs associated with the additional fill and brick work at $1,490,766.00.4 Plaintiff also claims a new mobilization area had to be created. Although Statement of Work § 5.7 states that “[a] mobilization area will be provided” for plain[605]*605tiffs use, defendant allegedly directed plaintiff to obtain a new mobilization area, which plaintiff did, at a cost of $5,000.00/month. Plaintiff maintains it also incurred additional expenses to build the necessary office facilities in that space. Plaintiff claims defendant was made aware of these additional expenses via email on November 27, 2005. Plaintiffs complaint alleges that, as a result of defendant’s decision to change the construction site’s location, plaintiff incurred $1,869,038.00 in total, additional expenses.5

Plaintiffs third alleged “difficulty” involved defendant’s delay in approving security upgrades to the courthouse mandated by the United States Marshals. In December 2005, seven months after initial construction began, plaintiff claims that defendant issued a notice of new requirements to upgrade the courthouse’s security measures. Plaintiff claims it informed defendant that these upgrades would “have an adverse impact on the Courthouse’s overall construction because certain portions of the .Courthouse could not progress until the proposed security modifications were installed.” Nevertheless, defendant allegedly waited until .February 23, 2006 to send plaintiff a “tentative” Statement of Work for the upgrade, and waited until April 1, 2006 to send out the initial Request for Proposal.6 Plaintiff states that this Request for Proposal for the upgrades specified that it was not a Notice- to Proceed.7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
129 Fed. Cl. 599, 2016 U.S. Claims LEXIS 2117, 2016 WL 7469866, Counsel Stack Legal Research, https://law.counselstack.com/opinion/al-juthoor-contracting-co-v-united-states-uscfc-2016.