Kiewit Infrastructure West Co. v. United States

CourtUnited States Court of Federal Claims
DecidedMay 15, 2019
Docket16-45
StatusUnpublished

This text of Kiewit Infrastructure West Co. v. United States (Kiewit Infrastructure West Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kiewit Infrastructure West Co. v. United States, (uscfc 2019).

Opinion

In the United States Court of Federal Claims No. 16-45C (Filed: May 15, 2019)

************************************* * KIEWIT INFRASTRUCTURE WEST, * CO., * * Plaintiff, * * v. * * THE UNITED STATES, * * Defendant. * * *************************************

OPINION AND ORDER

DAMICH, Senior Judge.

This Contract Disputes Act (“CDA”) action arises from the design-build fixed-price construction contract between Kiewit Infrastructure West, Co. (“Plaintiff” or “KIWC”) and the United States (“Defendant”) acting through the Western Federal Lands Highway Division (“WFLHD”) of the United States Department of Transportation (“USDOT”) for a project known as AK PFH 43(10), Deweyville Trailhead to Neck Lake Road, Contract No. DTFH70-12-C-0017 (“the project”). The project involved the realignment of approximately 11 miles of a preexisting single lane logging road into a two-lane paved road in the Tongass National Forest on Prince of Wales Island in Southeast Alaska. The project consisted of clearing and grubbing the worksite, and waste excavation and disposal, among other things.

Plaintiff filed its complaint in this Court on January 11, 2016, seeking an equitable adjustment pursuant to the CDA, based on two counts. Count One of Plaintiff’s complaint alleges that the Defendant constructively changed the terms of the contract. Count Two alleges that the site conditions materially differed from the conditions actually encountered, notwithstanding Plaintiff’s reasonable site inspection conducted prior to the award of the contract. In light of this, Plaintiff did not include wetland mitigation costs related to the waste disposal areas in its bid. However, the waste disposal sites did in fact contain wetlands and Plaintiff was required to buy wetland mitigation credits. Therefore, Plaintiff requests that this Court award it an equitable adjustment in the amount of $490,387,40, together with interest and costs.

1 Defendant answered Plaintiff’s complaint on May 5, 2016. Thereafter, discovery commenced and concluded on February 28, 2018. At the conclusion of discovery, the parties proposed a schedule for summary judgment briefing. The Court 1 adopted the briefing schedule and in accordance with the schedule, on May 11, 2018, Plaintiff filed its motion for summary judgment pursuant to Rule 56(c) of the Rules of the Court of Federal Claims (“RCFC “) (“Pl. Mot.”).

Defendant timely responded on July 5, 2108, filing a partial motion to dismiss pursuant to RCFC 12(b)(1), response to Plaintiff’s motion for summary judgment, and cross-motion for summary judgment pursuant to RCFC 56(c) (“Def. Mot.”). For the first time, Defendant asserts that this Court lacks jurisdiction over Plaintiff’s differing site condition claim. In support, Defendant argues that the Plaintiff failed to submit a certified claim to the Contracting Officer with regard to its differing site condition claim and, accordingly, the Contracting Officer never issued a final decision regarding this issue. If, however, this Court finds jurisdiction, Defendant argues that it is entitled to summary judgment over the differing site condition claim because the contract did not contain an affirmative representation regarding the presence of wetlands in the waste disposal areas of the project and the presence of wetlands in the waste disposal areas was reasonably foreseeable. Defendant further argues that it is entitled to summary judgment on Plaintiff’s constructive change claim because the contract placed responsibility for the purchase of all wetland mitigation credits upon Plaintiff. Therefore, Plaintiff did not perform work beyond the contract requirements by paying for the mitigation credits regarding wetlands in the waste disposal areas.

The case was fully briefed on August 16, 2018. On December 4, 2018, pursuant to RCFC 40.1(c), the case was reassigned to the undersigned.

By order dated March 7, 2019, the Court ordered supplemental briefing on two issues raised in Defendant’s briefs. Specifically, the Court ordered the parties to address: (1) whether the fact that the Plaintiff spent less on its purchase of wetland mitigation credits than the amount included in its bid affects Plaintiff’s claim for relief; and (2) whether the fact that Kiewit expanded the waste disposal sites affects Plaintiff’s cause of action. 2

For the reasons set forth below, the Court DENIES Plaintiff’s Motion for Summary Judgment. The Court further DENIES Defendant’s Partial Motion to Dismiss and GRANTS Defendant’s Cross-Motion for Summary Judgment.

I. Background and Relevant Statutes

The project involved designing and reconstructing a road in the Tongass National Forest. Due to the fact that the project was a Federal project in a national forest, environmental statues were implicated. Specifically, the project implicated two separate and distinct statutes: the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4321, and section 404 of the Clean Water Act, 33 U.S.C. § 1344.

1 The Honorable Margaret M. Sweeney, presiding. 2 In light of this opinion, the Court need not address these issues. 2 A. The National Environmental Policy Act

Pursuant to NEPA, federal agencies are required to:

incorporate environmental considerations in their planning and decision-making through a systematic interdisciplinary approach. Specifically, all federal agencies are to prepare detailed statements assessing the environmental impact of and alternatives to major federal actions significantly affecting the environment. These statements are commonly referred to as Environmental Impact Statements (EIS) and Environmental Assessments (EA).

“What is the National Environmental Policy Act?”, available at https://www.epa.gov/nepa/what- national-environmental-policy-act; see also 42 U.S.C. § 4332(C). This statute requires federal agencies to prepare detailed statements analyzing the impact of federal projects that significantly affect the environment.

NEPA further requires agencies to develop procedures to stay in compliance with it and requires that those procedures include identification of, and criteria for, a class of action which would not normally require an environmental impact statement or environmental assessment. 40 C.F.R. § 1507.3. This class of action is titled by the regulations as a “categorical exclusion.” Id.; 40 C.F.R. § 1508.4. A categorical exclusion is:

a category of actions which do not individually or cumulatively have a significant effect on the human environment and which have been found to have no such effect in procedures adopted by a Federal agency in implementation of these [NEPA] regulations and for which, therefore, neither an environmental assessment nor an environmental impact statement is required.

40 C.F.R. § 1508.4. If, after analysis, it is determined that a proposed project will not have a significant effect on the environment and falls within the category of actions covered by the categorical exclusion regulation, 40 C.F.R. § 1508.4, a categorical exclusion document is issued summarizing the potential environmental impacts and the agency’s conclusion. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McNutt v. General Motors Acceptance Corp.
298 U.S. 178 (Supreme Court, 1936)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
International Data Products Corp. v. United States
492 F.3d 1317 (Federal Circuit, 2007)
Louise J. Hamlet v. The United States
873 F.2d 1414 (Federal Circuit, 1989)
Richard James Booth v. The United States
990 F.2d 617 (Federal Circuit, 1993)
Engage Learning, Inc. v. Salazar
660 F.3d 1346 (Federal Circuit, 2011)
H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)
The Hunt Construction Group, Inc. v. United States
281 F.3d 1369 (Federal Circuit, 2002)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)
Scott Timber Company v. United States
333 F.3d 1358 (Federal Circuit, 2003)
Banks v. United States
741 F.3d 1268 (Federal Circuit, 2014)
Hardwick Bros. v. United States
41 Cont. Cas. Fed. 76,972 (Federal Claims, 1996)
Croman Corp. v. United States
44 Fed. Cl. 796 (Federal Claims, 1999)
Baldi Bros. Constructors v. United States
50 Fed. Cl. 74 (Federal Claims, 2001)
Kiewit Construction Co. v. United States
56 Fed. Cl. 414 (Federal Claims, 2003)
M.A. DeAtley Construction, Inc. v. United States
75 Fed. Cl. 575 (Federal Claims, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Kiewit Infrastructure West Co. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kiewit-infrastructure-west-co-v-united-states-uscfc-2019.