Hardwick Bros. v. United States

41 Cont. Cas. Fed. 76,972, 36 Fed. Cl. 347, 1996 U.S. Claims LEXIS 138, 1996 WL 436428
CourtUnited States Court of Federal Claims
DecidedJuly 31, 1996
DocketNo. 702-88C
StatusPublished
Cited by25 cases

This text of 41 Cont. Cas. Fed. 76,972 (Hardwick Bros. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hardwick Bros. v. United States, 41 Cont. Cas. Fed. 76,972, 36 Fed. Cl. 347, 1996 U.S. Claims LEXIS 138, 1996 WL 436428 (uscfc 1996).

Opinion

OPINION

ROBINSON, Judge:

This case is before the court on remand from the U.S. Court of Appeals for the Federal Circuit. 72 F.3d 883, 886 (1995). This court had previously dismissed the case after trial for lack of jurisdiction. 26 Cl.Ct. 884 (1992). The Federal Circuit reversed that ruling, and the case is now ready for disposition.

The litigation arises out of a contract between the United States Army Corps Engineers (“the Corps”) and Hardwick Brothers Company II (“Hardwick” or “plaintiff”) for the construction of a system of levees described as Phase I of L-246, part of a three-phased comprehensive flood control project north of the Missouri River near Brunswick, Missouri (“the Project” or “the Palmer Creek job”) in the late 1970’s.1 The Corps designed [354]*354the Project, in part, to contain Palmer Creek, which flows southward into Cut-Off Lake, an oxbow lake, before flowing south into the Missouri River. The levee system was intended to protect agricultural lands in the Brunswick-Dalton Drainage District (“the District”) from flooding.2

As amended, the complaint seeks $3,797,-276.50 in equitable adjustments and other damages. Plaintiff bases its various monetary demands upon separately stated, but sometimes overlapping, claims for relief. These claims, in brief, allege that plaintiffs losses were due to defendant’s defective or deficient engineering in designing the Project, defective plans and specifications, differing site conditions, a breach of the implied covenant of good faith and fair dealing, spoliation of evidence, nondisclosure of superior knowledge, and over-inspection of plaintiffs work, all of which resulted in job inefficiencies and extra operating costs.

After a careful review of the transcript, exhibits, briefs and the respective oral arguments of the parties, the court finds that defendant is liable to plaintiff only with respect to one of plaintiffs claims based on over-inspection. All of plaintiffs remaining claims are denied. The court’s reasoning follows.

Factual Background

In 1976, when Hardwick won the contract here in dispute, plaintiff was a successful, experienced levee contractor with good credit and financial resources. During Hardwick’s prior fifty years in business (including all predecessor entities), the company had performed many similar excavation and levee projects. One predecessor entity, the S.W. Hardwick Company, had begun business in the 1920’s. Throughout their respective existences, all of these entities maintained their principal offices in Beardstown, Illinois.

The Corps designed the Project in keeping with it past practices. The design was based on various types of hydrologic data, including Missouri River flood frequencies, the amounts of water which would likely require containment, precipitation and runoff from the hills to the north of the Project site and from farms adjacent to the Project, releases from upstream lakes which serve flood control functions for the Missouri River, river hydrographs, rating curves, soil borings, other hydrologic data and other standard design factors. These design factors, in the aggregate, determined such features as the location of the levee’s centerline, height, width, slope ratio, the construction methods allowed, location and size of drainage structures, quantities of materials, haul roads and the location and size of borrow areas.

During the design phase the Corps determined that the Palmer Creek levee should be at a height lower than the Missouri River’s north bank levee because such a design feature would allow a savings in dirt quantities and, thus, result in lower construction costs. The design accounted for lowering the Missouri River levee (part of the subsequent phases of L-246) to a 25-year flood containment height from a 100-year flood height. Also, during the design phase the Corps’s Missouri River Division considered, but rejected for unknown reasons, an alternative design involving a ditch from Cut-Off Lake to the river with a bottom elevation of approximately 611.5 feet above mean sea level (MSL). However, the final design and location of the levee was a compromise which gave consideration to the interests of the [355]*355landowners and to other factors, including the availability of suitable fill materials and their location, foreseeable potential construction difficulties, economic factors such as the overall cost of the levee to the government, the amount of potential or existing fertile farmland that would be taken by the levee (if placed further to the west), possible interior drainage problems and the number of ditches that would be required with some other location.

The Corps’s design carried the levee’s cen-terline for a substantial distance alongside the western boundary of Cut-Off Lake. The lake was formed in the late 1880’s as an oxbow lake when a section of the Missouri River shifted its channel. Generally, oxbow lakes such as Cut-Off Lake fill up over time with alluvium from the hillsides above them. These alluvium deposits tend to be clay soils while deposits from rivers during floods tend to be sand and silts which generally are not as cohesive in nature. Groundwater in a river valley usually migrates both with the river and toward the river, intercepting the river about the river’s water level. In floodplains, materials are deposited and redeposited and in the process become “reformed” materials. They are not, however, homogeneous. Consequently, their deposition does not result in predictable layers of coarse and fine materials in the same areas.

The soils at the Project site have been reformed and some of the clays have been washed out of them making them more pervious and able to more freely transmit water from nearby or adjacent sources. Thus, the river at the Project site is, in essence, a “penetrating” river. However, the Project site was not unique in this respect because all river floodplains have the same general deposition history and generally exhibit this same characteristic of relatively quick adjacent soil penetration.

Over the years of its study of this proposed project, the Corps had accumulated a significant amount of data to assist it in designing the levee including the following:

(1) Old Missouri River maps dating from 1885. Such maps were usually maintained in the Hydrologic Engineering Branch for purposes of studying the impact of navigational projects on the environment. These maps, showing the location of the old Missouri River channel, revealed that the levee’s alignment, as ultimately located and designed, would pass directly over the old channel in some places. The Corps had survey data of the course of the river dating from 1879. These data showed that the lake was formed when the Missouri River cut through a large meander near Bushwhacker Bend. The Corps also had aerial photographs showing that, as late as 1945, there were low areas at the site corresponding to the old channel which had not yet been filled in by deposition and which still held water.

(2) Piezometric study data. Corps data showed the presence of a water-saturated piezometric mound under the lake. This type of mound is one which naturally occurs under lakes and drops off as the distance from the lake increases. It derives its name from the use of a particular instrument called a piezometer, a device hydrologists and geo-technical engineers use to measure the change of pressure of a material subjected to hydrostatic pressure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meltech Corporation, Inc.
Armed Services Board of Contract Appeals, 2026
NALTNER v. United States
Federal Claims, 2024
Chapman Law Firm, LPA v. United States
113 Fed. Cl. 555 (Federal Claims, 2013)
Public Service Co. v. United States
88 Fed. Cl. 250 (Federal Claims, 2009)
United Medical Supply Co. v. United States
77 Fed. Cl. 257 (Federal Claims, 2007)
Daewoo Engineering & Construction Co. v. United States
73 Fed. Cl. 547 (Federal Claims, 2006)
Universal Construction, Inc. v. United States
71 Fed. Cl. 179 (Federal Claims, 2006)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
Renda Marine, Inc. v. United States
58 Fed. Cl. 57 (Federal Claims, 2003)
Columbia First Bank, FSB v. United States
58 Fed. Cl. 54 (Federal Claims, 2003)
Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)
Cavalier Clothes, Inc. v. United States
51 Fed. Cl. 399 (Federal Claims, 2001)
Comtrol, Inc. v. United States
49 Fed. Cl. 294 (Federal Claims, 2001)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Slattery v. United States
46 Fed. Cl. 402 (Federal Claims, 2000)
CTA Inc. v. United States
44 Fed. Cl. 684 (Federal Claims, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
41 Cont. Cas. Fed. 76,972, 36 Fed. Cl. 347, 1996 U.S. Claims LEXIS 138, 1996 WL 436428, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hardwick-bros-v-united-states-uscfc-1996.