Lear Siegler Management Services Corporation v. The United States

867 F.2d 600, 35 Cont. Cas. Fed. 75,622, 1989 U.S. App. LEXIS 1183, 1989 WL 8725
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 8, 1989
Docket88-1469
StatusPublished
Cited by14 cases

This text of 867 F.2d 600 (Lear Siegler Management Services Corporation v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lear Siegler Management Services Corporation v. The United States, 867 F.2d 600, 35 Cont. Cas. Fed. 75,622, 1989 U.S. App. LEXIS 1183, 1989 WL 8725 (Fed. Cir. 1989).

Opinion

FRIEDMAN, Circuit Judge.

This is an appeal from a decision of the Armed Services Board of Contract Appeals rejecting a contractor’s appeal from a contracting officer’s decision denying the contractor a price increase under the contract. The ground of the Board’s decision was that the contractor had failed to prove that it relied on its interpretation of an ambiguous contract provision in preparing its bid. Lear Siegler Inc. Management Servs. Div., 88-2 B.C.A. (CCH) ¶ 20,642 (Feb. 26, 1988) [1988 WL 44423], We affirm.

I

In September 1983, the Air Force issued a solicitation for the maintenance and operation of the motor pool at Tinker Air Force Base. The successful bidder would be required to “furnish all personnel, equipment, repair parts and supplies ... [and] to manage and operate vehicle maintenance, vehicle operations and transportation analysis” at the base.

The solicitation contained a number of technical exhibits that provided detailed information on the nature of the maintenance work that would be required under the contract. Technical exhibit 8 contained the Air Force’s “Estimated Workload Data For Maintenance Including Vehicle Parts.” The exhibit described the number of monthly work orders processed over a given 12-month period for each of the different types of vehicles at Tinker, the manhours needed to maintain the vehicles over that period, and the monthly cost of the parts used in making the repairs. The solicitation also included a special provision, entitled “Variation in Workload,” which provided in part:

If at the end of a contract period the number of vehicle maintenance work orders, ... varies above or below 15 percent from the total estimated contract workload, negotiations for an equitable price adjustment may be initiated by either party. Any increases or decreases in price shall be based on the net of all increases or decreases in this workload. Adjustment to the contract price shall be made only for that portion of the total net increase or decrease in excess of 15 percent.

The solicitation did not define the term “maintenance work orders,” and no explicit distinction was made between major and minor maintenance work orders. The solicitation referenced a number of Air Force manuals, including volumes I — III of Air Force Manual (AFM) 33-710, that were to serve as a guide in construing the terms of the solicitation. Portions of these manuals are pertinent to this appeal.

Volume II of AFM 33-710 defined “work order” as “[a] specific or blanket authorization to perform certain work.... [which] is usually broader in scope than a job order, but is sometimes used synonymously with job orders.” Chapter 4 of Volume II defined major maintenance and minor maintenance. In general, minor maintenance is work that “take[s] one direct labor-hour or less, and that use[s] only low-cost bench stock parts or material,” and major maintenance is maintenance work that is not minor in nature. Chapter 6 of Volume II required that all maintenance work be “entered on a work order, AF Form 1823 or 1827.”

Air Force (AF) Form 1823, entitled “Vehicle and Equipment Work Order,” was the form used to record major maintenance work, and AF Form 1827, entitled “Minor Maintenance Work Order,” was the form used to record minor maintenance work. AF Form 1827 contains 18 horizontal lines to be used for the recording of minor maintenance work. Minor maintenance that was performed on anywhere from 1 to 18 *602 different vehicles could be recorded on AF Form 1827.

At a pre-bid conference, attended by the appellant, a bidder asked the Air Force representative whether the work order data in technical exhibit 8 included both major and minor work orders. The Air Force response was “Yes, minor maintenance work orders are included.” 88-2 B.C.A. (CCH) H 20,642 at 104,341.

There were 10 bidders on the Tinker contract. The appellant was the second lowest bidder. In preparing its bid, the appellant drew on the experience it had gained in performing a similar motor pool maintenance contract at another Air Force Base, the Warner Robins Air Force Base. Except for the number of vehicles, the Tinker motor pool “was an exact replica” of the one at Warner Robins.

To determine its bid, the appellant performed a comparison analysis between the Warner-Robins motor pool and the one at Tinker. The appellant reviewed the workload data in technical exhibit 8 for indications of fluctuation in workload due to “dumping” — a situation where the Army deferred certain work and submitted it to the motor pool all at one time. The appellant found the workload at Tinker to have been fairly uniform over the period exhibit 8 covered.

The appellant was awarded the Tinker contract on November 16, 1983, after the low bidder withdrew. The appellant began performance of the contract on January 1, 1984, and almost immediately began experiencing problems in meeting its maintenance schedule due to the high backlog of vehicles that needed repair. The appellant filed a request, which the Air Force denied, for an extension of the time allowed under the contract for it to bring the Tinker fleet to an acceptable quality level.

On February 28, 1984, the appellant informed the Air Force contracting officer that the number of major and minor work orders processed in January 1984 was almost twice the number shown in technical exhibit 8. On March 28, 1984, the appellant informed the contracting officer that the number of work orders processed during the first three months of the contract was nearly double the number in technical exhibit 8.

On May 30,1984, the appellant submitted a proposed price adjustment, as provided for under the contract’s Variation In Workload clause, to cover the increased cost associated with the extra workload. The appellant claimed that the number of work orders issued between January 1 and March 31,1984, exceeded by 2,453 the average number of work orders set out in technical exhibit 8, increased by 15 percent. The appellant had calculated this number by counting each line-item on the Form 1827 as a separate minor maintenance work order.

The Air Force asked the appellant to provide a breakdown of its work order count into major maintenance work orders and minor maintenance work orders. Appellant submitted a list of all work orders it had processed over the three-month period but did not provide a breakdown of the list into major and minor categories.

At a July 15, 1984 meeting with the Air Force contracting officer, the appellant asked the contracting officer for her definition of what constituted a minor maintenance work order. The contracting officer replied that a minor maintenance work order was a work order which takes “one hour or less of maintenance time and cost [less] than 20 dollars.” The contracting officer took the position that only major maintenance work orders would be counted for purposes of invoking the Variation In Workload provision.

After consulting with the Vehicle Transportation Chief at Warner Robins Air Force Base, the contracting officer learned that, at Warner Robins, each 1827 form, and not each line-item on the form, was counted as one minor maintenance work order.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jemison & Partners, Inc.
Armed Services Board of Contract Appeals, 2022
Corinthian-WBCM, a Joint Venture
Armed Services Board of Contract Appeals, 2021
Brantley Construction Services, LLC
Armed Services Board of Contract Appeals, 2021
Coy/Superior Team v. BNFL, Inc.
174 F. App'x 901 (Sixth Circuit, 2006)
PCL Construction Services, Inc. v. United States
47 Fed. Cl. 745 (Federal Claims, 2000)
Cray Research, Inc. v. United States
44 Fed. Cl. 327 (Federal Claims, 1999)
Hardwick Bros. v. United States
41 Cont. Cas. Fed. 76,972 (Federal Claims, 1996)
North Country Associates v. United States
22 F.3d 1102 (Federal Circuit, 1994)
Fry Communications, Inc. v. United States
22 Cl. Ct. 497 (Court of Claims, 1991)
Maintenance Engineers, Inc. v. United States
36 Cont. Cas. Fed. 75,950 (Court of Claims, 1990)
Fruin-Colnon Corporation v. The United States
912 F.2d 1426 (Federal Circuit, 1990)
Craft Machine Works, Inc. v. United States
36 Cont. Cas. Fed. 75,861 (Court of Claims, 1990)
Froeschle Sons, Inc. v. The United States
891 F.2d 270 (Federal Circuit, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
867 F.2d 600, 35 Cont. Cas. Fed. 75,622, 1989 U.S. App. LEXIS 1183, 1989 WL 8725, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lear-siegler-management-services-corporation-v-the-united-states-cafc-1989.