Brantley Construction Services, LLC

CourtArmed Services Board of Contract Appeals
DecidedJanuary 28, 2021
DocketASBCA No. 61118
StatusPublished

This text of Brantley Construction Services, LLC (Brantley Construction Services, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brantley Construction Services, LLC, (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Brantley Construction Services, LLC ) ASBCA No. 61118 ) Under Contract No. W912HN-10-D-0056 )

APPEARANCE FOR THE APPELLANT: William A. Scott, Esq. Pedersen & Scott, P.C. Charleston, SC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Laura J. Arnett, Esq. Allie E. Vandivier, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Savannah

OPINION BY ADMINISTRATIVE JUDGE PAGE

Brantley Construction Services, LLC (BCS or appellant) entered into a contract with the United States Army Corps of Engineers, Savannah District (government or COE) to construct and replace Taxiway Juliet at Mackall Auxiliary Airfield (Mackall AAF) and Taxiway Mike at Pope Army Airfield (Pope AAF). Appellant alleges that the specifications relating to Taxiway Juliet were defective, making it impossible to perform in conformance with the contract. Appellant also alleges that it was delayed in its completion of Taxiway Mike due to issues caused by the government with Taxiway Juliet and that the government constructively changed the contract by failing to provide access to a specific batch plant site during the time of performance. The government denies the allegations, and instead asserts all issues arose due to appellant’s inabilities, lack of experience, and business choices. We deny the appeal.

FINDINGS OF FACT (FOF)

The Request for Proposal

1. The government issued a Request for Proposal (RFP) for Task Order No. W912HN-09-C-5944, for the repair and replacement of Taxiway Juliet at Mackall AAF and Taxiway Mike at Pope AAF, to the members of the Multiple Award Task Order Contract (MATOC) pool in August 2013 (Joint Stipulation of Facts (JSF) ¶¶ 1-3; R4, tab 3 at 56-57 1). BCS was a member of the MATOC pool, and submitted a bid for the work (JSF ¶¶ 2, 4).

2. The scope of work for the Task Order called for the replacement of both failed taxiways. This included demolishing the existing taxiways and replacing them to meet the current Unified Facilities Criteria (UFC) airfield requirements. The new taxiways work included “plain Portland cement concrete (PCC) airfield pavement, asphalt paved shoulders, replacement of appropriate airfield directional signage, runway/taxiway illumination, taxiway markings, and appropriate erosion and sediment control devices during construction.” Taxiway Juliet was also to include permanent storm water controls. (R4, tab 3 at 57) As explained in greater detail below, the contract allowed the contractor to determine whether it would use the slipform method or the fixed-form method of paving 2 at each of these airfields (JSF ¶ 16).

1 The Board will use the Bates-labeling to identify page numbers for any Rule 4 documents, unless otherwise noted. References to transcripts specify the volume and page number affixed by the court reporter, unless these are evidentiary depositions that have been admitted as part of the Rule 4 file. 2 We distinguish between “ready mix” or “ready mixed” concrete, “Ready Mix

Company,” and “Ready Mix Concrete.” “Ready Mixed Concrete Company” (sometimes called “Ready Mix Company”) is the brand name of a commercial enterprise that furnishes ready-mixed concrete. Lower case references to “ready mix” or “ready-mixed” are to a type of concrete which, under the terms of this contract and as explained by testimony, is mixed en route and transported to the placement site in an agitating truck (see, e.g., R4, tab 3 at 826; tr. 1/54-55, 57, 2/15). However, the distinction between the product and the company was not always strictly followed and the proprietary term is sometimes used in the vernacular. For example, T.C.P. Concrete Construction’s (TCP) representative clarified that the “Ready Mix” concrete in that company’s post-award bid to BCS was actually “ready mixed concrete” that it would have obtained from Concrete Services (see, e.g., R4, tab 45 at 225). Sometimes, the agitating trucks that carried the concrete in rotating drums were referred to as “ready mix trucks” even though it was not clear these belonged to the Ready Mixed Concrete Company (see, e.g., R4, tab 11 at 1204 and tab 30 at 3057-58). In similar fashion and as can be seen throughout the findings and decision, the paving method “slipform” is sometimes called “slip form” and the fixed-form paving method is also called “fixed form,” and “haul time” is “Haultime.”

2 3. The Taxiway Juliet contract required replacement of the entire taxiway, approximately 480 feet (tr. 1/46 3). The contract defined the site by a red line surrounding the specific area where the work was to be performed (R4, tab 4 at 949; tr. 1/45). There are no gates or fences restricting access to Mackall AAF (tr. 1/42-43, 2/177, 4/82; R4, tab 44 at 93).

4. The Taxiway Mike contract required the replacement of the current taxiway, as well as the installation of a 60-inch storm drain under the taxiway (tr. 1/49-50). There is a gate restricting access to Pope AAF and a pass is required for those who enter the facility (tr. 1/47-48).

5. Prior to the issuance of the solicitation, the government completed a biddability, constructability, operability, and environmental review certification, which found that the “project is ready for advertisement and award” (R4, tab 93 at 907-08, ex. 54).

6. Numbered paragraph 4 of the RFP states that “[i]f an Offeror believes the requirements in this RFP contain an error, omission, or are otherwise unsound; the Offeror shall immediately notify the Contracting Officer in writing, to include supporting rationale” (R4, tab 3 at 57). BCS did not contact the contracting officer (CO) regarding any potential errors, omissions, or issues with the RFP requirements prior to submitting its bid (tr. 4/197; see generally tr. 2/205-19).

Requirements in the RFP and Contract for the Slipform Paving Method and the Fixed-Form Paving Method

7. The RFP includes contract specification § 32 13 11, which states the requirements for concrete pavement for airfields and other heavy-duty pavements (JSF ¶ 8 citing R4, tab 3 at 377-437, 795-855). This specification lays out stringent requirements for the concrete to be used in paving Taxiway Juliet and Taxiway Mike, and professional qualifications for the concrete specialists used by the contractor (R4, tab 3 at 795-855). For example, the contractor would be paid only for concrete that met certain tolerances, and was made and placed in accordance with technical publications as referenced (see, e.g., id. at 795- 814, § 32 13 11, ¶¶ 1.1-1.6, including requirements for surface smoothness, edge slump and joint face deformation, plan grade, flexural strength, thickness, and diamond grinding of PCC surfaces). The contractor was held to quality control (QC) standards at § 32 13 11, ¶ 1.5 Quality Assurance (QA) (id. at 810-14), which included at ¶ 1.5.1 verifying to the CO that its QC staff, including the “petrographer, surveyor, concrete batch plant operator, and profilograph operator” were

3 Although the transcript refers to Taxiway Mike, when the testimony is placed in context this was erroneous, and the testimony about approximate length was for Taxiway Juliet.

3 “American Concrete Institute (ACI) Certified” at specific levels; at ¶1.5.2 that its “other staff” were suitably trained; and at ¶1.5.3 that the laboratory and testing facilities used by the contractor were accredited (id. at 810-11).

8.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
International Data Products Corp. v. United States
492 F.3d 1317 (Federal Circuit, 2007)
Al Johnson Construction Company v. The United States
854 F.2d 467 (Federal Circuit, 1988)
Froeschle Sons, Inc. v. The United States
891 F.2d 270 (Federal Circuit, 1989)
Fruin-Colnon Corporation v. The United States
912 F.2d 1426 (Federal Circuit, 1990)
Blake Construction Company, Inc. v. The United States
987 F.2d 743 (Federal Circuit, 1993)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Brantley Construction Services, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brantley-construction-services-llc-asbca-2021.