Fruin-Colnon Corporation v. The United States

912 F.2d 1426, 36 Cont. Cas. Fed. 75,923, 1990 U.S. App. LEXIS 13673, 1990 WL 114331
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 10, 1990
Docket90-1059
StatusPublished
Cited by56 cases

This text of 912 F.2d 1426 (Fruin-Colnon Corporation v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fruin-Colnon Corporation v. The United States, 912 F.2d 1426, 36 Cont. Cas. Fed. 75,923, 1990 U.S. App. LEXIS 13673, 1990 WL 114331 (Fed. Cir. 1990).

Opinion

PLAGER, Circuit Judge.

Fruin-Colnon Corporation (“Fruin”) entered into a contract with the U.S. Army Corps of Engineers (“Government”) to construct an addition to an existing Government building in St. Louis. Part way through performance of the contract, the parties fell into disagreement over how the electrical subcontract should be performed, a dispute based on a difference in interpretation of the contract terms. The dispute was resolved only by the Government ordering Fruin to do it the Government’s way, and Fruin doing it. This involved redoing some of the work already completed, and doing the balance of the work in a manner more costly to the contractor. Fruin now wants compensation for the extra cost.

The Armed Services Board of Contract Appeals (“Board”) held that the contract provision in issue is ambiguous and that while Fruin’s interpretation of the contract is reasonable, Fruin failed to show that it relied upon that interpretation in preparing its bid. Fruin-Colnon Corp., ASBCA No. 30702, 1989 WL 74397 (May 15, 1989) (Contract No. DACA41-83-C-0039). Fruin claims that that is not what the law of contract reliance requires. We conclude that the Board is correct, and we affirm.

I. BACKGROUND

In early 1983, Fruin submitted a bid to construct a 150,000 square foot basement addition to an existing building at the St. Louis Air Force Station. On April 18, 1983, Fruin was awarded the contract, in the amount of $14,179,051. The contract provided in pertinent part:

2. GENERAL:
2.1 Rules: The installation shall conform to the requirements of the National Electric Code, except where requirements in excess thereof are specified herein.
* * 5(5 # * *
8. WIRING METHODS:
* * 5}! * * *
8.2 Conduit (and tubing) systems shall be installed as indicated_ Aluminum conduit may be used only where installed exposed in dry locations.... Raceways shall be concealed where possible within finished walls, ceilings, and floors other than slabs-on-grade_
* * * * * £
8.2.3 Exposed raceways shall be installed parallel or perpendicular to walls, structural members, or intersections of vertical planes and ceilings.

The National Electric Code (“Code”) defines the terms “exposed” and “concealed”:

Exposed: (As applied to wiring methods.) On or attached to the surface or behind panels designed to allow access. [See “Accessible — (As applied to wiring methods).”]
Concealed: Rendered inaccessible by the structure or finish, of the building. Wires in concealed raceways are considered concealed, even though they may become accessible by withdrawing them. [See “Accessible — (As applied to wiring methods).”]
The Code further defines “accessible”: Accessible: (As applied to wiring methods.) Capable of being removed or exposed without damaging the building structure or finish, or not permanently closed in by the structure or finish of the building. (See “Concealed” and “Exposed.”)

Fruin hired a subcontractor, Sachs Electrical Co. (“Sachs”), to install the electrical *1428 work. On April 3, 1984, Fruin submitted a working drawing, prepared by the subcontractor, to the Government that indicated that both aluminum and non-aluminum conduit above (i.e., concealed by) a suspended ceiling was to be installed in a diagonal manner — that is, not parallel or perpendicular to walls and other structural members. Fruin’s subcontractor began installation of the conduit on April 9, 1984, in accordance with the drawings.

On April 12, 1984, the Government orally informed Fruin that the diagonal manner of installation was not acceptable, and on April 17, 1984, the Government formally notified Fruin in writing of its disapproval. Fruin took the position that the Government’s disapproval was unwarranted, and its subcontractor, despite the disapproval, continued for almost another month to install the conduit in a diagonal manner.

Thereafter, the parties attempted to resolve their dispute. It was Fruin’s contention, and the Board later so found, that the Code applies to contract terms only when they involve safety considerations. Fruin argued that the term “exposed” means “visible,” and that the Code definition of “exposed,” which includes “panels designed to allow access,” and which thus includes conduit out of sight above suspended ceilings, only applies when there is a safety consideration involved. It was Fruin’s position that the “parallel or perpendicular” requirement of section 8.2.3 is an aesthetic-based provision, and thus, that the term “exposed” in that section therefore means “visible,” and that it would not include conduit concealed by a suspended ceiling.

The Government held fast to its belief that the term “exposed” applied to the conduit in dispute, and required Fruin to remove the diagonally installed conduit and replace it with parallel and perpendicular conduit runs. Fruin complied and then filed a claim with the contracting officer (“CO”) for an equitable adjustment of $186,349.21 to cover the costs of the reins-tallation.

On October 30, 1984, the CO denied Fruin’s claim for an equitable adjustment of the contract. Fruin appealed the CO’s decision to the Board, pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-13.

On May 15, 1989, the Board issued its opinion finding that “the Corps of Engineers intended the electrical conduit or raceways required under [the] contract to be installed above the suspended ceilings in a parallel and perpendicular fashion and that this is the way the specification had been interpreted and wiring installed for a number of years.” However, the Board also found the testimony of Fruin’s expert concerning the meaning of the contract term “exposed” to be persuasive, and concluded that Fruin was correct that the Code definition of “exposed” does not control when that term is used in non-safety related provisions of the contract. The Board determined that both parties’ interpretations of the contract were reasonable and that the contract was thus ambiguous.

The Board ultimately denied Fruin’s claim, however, because Fruin did not submit any evidence showing that it relied upon its interpretation of the contract at the time the contract was first bid, Fruin thereafter appealed to this court challenging that requirement.

II. DISCUSSION

The standard of review in cases under the Contract Disputes Act is governed by 41 U.S.C. § 609(b) (1988), which states in pertinent part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Corinthian-WBCM, a Joint Venture
Armed Services Board of Contract Appeals, 2021
Brantley Construction Services, LLC
Armed Services Board of Contract Appeals, 2021
Optimization Consulting, Inc.
Armed Services Board of Contract Appeals, 2019
Rustler Construction, Inc. v. District of Columbia
211 A.3d 187 (District of Columbia Court of Appeals, 2019)
KiewitPhelps
Armed Services Board of Contract Appeals, 2019
K-Con, Inc. v. Secretary of the Army
908 F.3d 719 (Federal Circuit, 2018)
North American Landscaping, Construction and Dredge, Co., Inc.
Armed Services Board of Contract Appeals, 2018
Systems Development Corp. v. McHugh
658 F.3d 1341 (Federal Circuit, 2011)
Red River Holdings, LLC v. United States
802 F. Supp. 2d 648 (D. Maryland, 2011)
Donley v. Lockheed Martin Corp.
608 F.3d 1348 (Federal Circuit, 2010)
Total Procurement Service, Inc. v. Sec. Of Defense
337 F. App'x 906 (Federal Circuit, 2009)
Grumman Aerospace Corporation v. Wynne
497 F.3d 1350 (Federal Circuit, 2007)
Medlin Construction Group, Ltd. v. Harvey
449 F.3d 1195 (Federal Circuit, 2006)
Coy/Superior Team v. BNFL, Inc.
174 F. App'x 901 (Sixth Circuit, 2006)
Bender GmbH v. Brownlee
106 F. App'x 728 (Federal Circuit, 2004)
Bechtel National, Inc. v. Roche
65 F. App'x 277 (Federal Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
912 F.2d 1426, 36 Cont. Cas. Fed. 75,923, 1990 U.S. App. LEXIS 13673, 1990 WL 114331, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fruin-colnon-corporation-v-the-united-states-cafc-1990.