Bender GmbH v. Brownlee

106 F. App'x 728
CourtCourt of Appeals for the Federal Circuit
DecidedJuly 30, 2004
DocketNo. 04-1056
StatusPublished

This text of 106 F. App'x 728 (Bender GmbH v. Brownlee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bender GmbH v. Brownlee, 106 F. App'x 728 (Fed. Cir. 2004).

Opinion

PER CURIAM.

Appellant Bender GmbH (“Bender”) appeals a decision by the Armed Services Board of Contract Appeals (“the Board”), upholding the default termination of Bender’s contract with the Department of Army. Bender GmbH, 2003 WL 21489700 (A.S.B.C.A. Jun.24, 2003). For the reasons that follow, we affirm the Board’s decision.

BACKGROUND

This appeal arises from a dispute between Bender and the Army concerning a contract that the Army awarded to Bender to replace and repair portions of an existing retaining wall on the Nahe River at a water supply facility near Baumholder, Germany. In the course of performance, the parties executed four modifications to the contract. Only Modifications Nos. 2 and 4 are pertinent here. In Modification No. 2, Bender sought and obtained additional money to perform drilling in class 6 and 7 soil and to extend the completion date to January 30, 1998. Bender was unable, however, to complete performance under the contract by that date. Accordingly, Bender submitted another request for equitable adjustment to account for drilling into class 7 soil on January 26, 1998. The parties eventually executed another modification (Modification No. 4) on June 25, 1998, in which the Army agreed to end a pending termination for default proceeding, give Bender a second chance to perform under the contract, and extend the contract deadline to October 9, 1998. In addition, the modification provided that the revised structural analysis (“statical”) proposed by Bender would be accepted by the Army in exchange for Bender’s waiver of “any and all claims or requests for equitable adjustment arising from, or connected to, alleged differing site conditions, stop work orders, and delays occurring after the effective date of the contract.”

Following the execution of Modification No. 4, the Army issued two cure notices. In the first cure notice, the Army brought to Bender’s attention its failure to perform certain services called for in Modification Nos. 2 and 4, including demolition of the entire toe cut-off wall. In the second cure notice, the Army warned Bender that its failure to make adequate progress to ensure completion of the project by the contract deadline may result in termination of the contract.

On October 2, 1998, the Army instructed Bender to suspend work on the foundation because it had not received any structural analysis to accomplish the foundation work specified in the specifications. The Army observed that it did not appear that the construction taking place would replace the foundation as required under the contract. Moreover, the construction undertaken by Bender would appear to narrow the width of the river, which was not approved by the German Water Authorities. Pursuant to the second cure notice, the Army terminated the contract for default on November 24, 1998. Bender timely appealed to the Board, which upheld the Army’s termination decision. Bender now appeals the Board’s decision. We have jurisdiction of this appeal pursuant to 28 U.S.C. § 1295(a)(10) and the Contract Disputes Act of 1978 (“CDA”) under 21 U.S.C. § 607(g)(1)(A).

STANDARD OF REVIEW

Under the CDA, we review the Board’s conclusions of law de novo. 41 U.S.C. § 609(b) (1987). Although the Board’s in[730]*730terpretations are not final and conclusive, “we give careful consideration and great respect to a board’s interpretation [of contracts] because legal interpretations by tribunals having expertise are helpful even if not compelling,” Fruin-Colnon Corp. v. United States, 912 F.2d 1426, 1429 (Fed. Cir.1990). Whether or not a default by a contractor is excusable is a question of fact. Copeland v. Veneman, 350 F.3d 1230, 1233 (Fed.Cir.2003). Determination of facts found by the Board are “final and conclusive” unless it was arbitrary, capricious, based upon less than substantial evidence or rendered in bad faith. 41 U.S.C. § 609(b); Wickham Contracting Co. v. Fischer, 12 F.3d 1574, 1577 (Fed.Cir.1994).

DISCUSSION

1. Justified Default Termination

The government bears the burden of proof on the initial question of whether it was justified in terminating Bender for default. Lisbon Contractors, Inc. v. United States, 828 F.2d 759, 764 (Fed.Cir.1987). Only after the justified default issue is resolved do we turn to the other claims, such as whether Bender’s delay was excusable. Id. In this case, the contract incorporates by reference Federal Acquisitions Regulation (“FAR”) clause 52.249-10, the standard language for default in a fixed-price construction. 48 C.F.R. 52.249-10. In default cases involving a contractor’s alleged failure to make sufficient progress, termination may be justified if the contracting officer is “justifiably insecure about the contract’s timely completion,” Discount Co. v. United States, 213 Ct.Cl. 567, 554 F.2d 435, 441 (1977), based upon the “events, actions, and communications leading to the default decision.” McDonnell Douglas Corp. v. United States, 323 F.3d 1006, 1017 (Fed.Cir.2003). The default language only requires “a reasonable belief on the part of the contracting officer that there was ‘no reasonable likelihood that the [contractor] could perform the entire contract effort within the time remaining for contract performance.’ ” Id. at 1016 (quoting Lisbon, 828 F.2d at 765).

The contracting officers testified that because of Bender’s repeated delays extending over 2 years, inability or unwillingness to protect the work site from flooding damage,1 and unwillingness to continue work on other areas of the project after the Army issued the partial suspension, they felt justifiably insecure whether Bender would complete the project by the contract deadline of October 9, 1998, or for that matter, December 31, 1998, the date to which Bender sought an extension. Bender proffers no record evidence to show it could have completed the project by the contract deadline. Indeed, in response to the Army’s September 16, 1998 cure notice, which warned Bender that it may terminate the contract because Bender did not appear able to complete the project in time, Bender “rejected” the cure notice and claimed that, because of the class 7 soil in the riverbed, it “require[d]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
106 F. App'x 728, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bender-gmbh-v-brownlee-cafc-2004.