Discount Co. v. United States

554 F.2d 435, 23 Cont. Cas. Fed. 81,250, 213 Ct. Cl. 567, 1977 U.S. Ct. Cl. LEXIS 30
CourtUnited States Court of Claims
DecidedApril 20, 1977
DocketNo. 178-75
StatusPublished
Cited by32 cases

This text of 554 F.2d 435 (Discount Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Discount Co. v. United States, 554 F.2d 435, 23 Cont. Cas. Fed. 81,250, 213 Ct. Cl. 567, 1977 U.S. Ct. Cl. LEXIS 30 (cc 1977).

Opinions

Davis, Judge,

delivered the opinion of the court:

This contract case is before us under the Wunderlich Act, 41 U.S.C. §§ 321-22 (1970), for scrutiny of a decision by the Department of Agriculture Board of Contract Appeals (Board). Plaintiff, Discount Company, Inc., appealed its termination for default to the Board, requesting that the termination be considered for the convenience of the Government.1 The Board decided that the default termination was appropriate and Discount subsequently requested a rehearing, which was denied with an opinion. Plaintiff then brought suit here to review the Board’s decision, and Trial Judge Browne has recommended that the administrative determination in favor of the Government be reversed. We conclude, however, that the Board’s upholding of the default termination should stand.

In May, 1968, the Forest Service awarded plaintiff a contract to construct the Mona Campground and Lookout Boating Site in the Willamette National Forest, Oregon. For a contract price of $104,399.99, Discount was to complete a boat launching ramp, parking lot and campgrounds within 180 days of the notice to proceed, which was issued on June 24, 1968.

[570]*570From the beginning, plaintiff encountered difficulties on the job.2 Discount was nonetheless on schedule at the time work was suspended (due to adverse weather conditions) in December, 1968. In October, 1968, the contracting officer had decided that plaintiffs work on the parking area and boat ramp was not in accordance with specifications and directed the contractor to remove the structures during the next construction season.3 In addition, the contracting officer reminded plaintiff that during the next construction season the boat ramp area would be partially covered by the rising water level in the Lake Mona Reservoir. In fact, the water level limited Discount’s access to the boat ramp and parking lot for most of the 1969 building season.

Prior to the resumption of work for the 1969 season, Discount and the Government’s representatives had two conferences to decide on the best way to proceed with the removal of the nonconforming structures and to plan the remaining work under the contract. The contractor agreed to wait until September 1969 (when the boat ramp would no longer be under water) to work on the allegedly nonconforming structures but to begin its campground construction on June 2, 1969.4

On June 2, the contracting officer submitted to Discount a change order which designated an alternative borrow site and also gave plaintiff a partial work resumption order for the campground construction agreed to at the second preseason conference. Plaintiff returned the order unsigned and alleged that it could not proceed because of problems [571]*571with the Government’s restaking of the area and certain clearing and grubbing difficulties. When the restaking was completed, the work order was reissued and signed on June 24, 1969, effective the next day. No work, however, was begun on the campground.

On July 14, 1969, the Forest Service ordered a full resumption of work, effective July 15. This full work resumption order took into account the Government’s anticipated "as is” acceptance of the boat ramp (see footnote 3, supra) and required work to resume on all other phases of the project (particularly the campground). Despite this order (and the previous partial resumption order of June 24), which required work on the campground area (unaffected by the high water level), the Government alleges that no substantial amount of work was performed on the job site during the summer of 1969. Because of this alleged lack of progress, the Government, on July 23, 1969, sent Discount a 10-day cure notice demanding that work be resumed so as to ensure the project’s completion before the expiration of the total contractual time remaining. It also requested a schedule for the work not yet begun or completed. When Discount neither resumed work nor provided a schedule, the contract was terminated for default on August 12th.

It should be inserted here that an additional point of contention between the parties arose during the summer of 1969. In June of that year, the Government submitted to plaintiff Pay Invoice No. 6, representing an estimated progress payment for work done in the previous year. Plaintiff disputed the estimated percentage of work completed and refused to sign; when the parties finally agreed, on August 4, 1969, to the amount due, the Government decided that Discount was in default of the 10-day cure notice, and was likely to be terminated; payment was therefore withheld to protect the sureties. This dispute over Pay Invoice No. 6 has resurfaced as an important point in the Trial Judge’s decision and in the Government’s objections to it.

Unlike the Trial Judge, we consider that the Board’s factual findings were neither arbitrary, capricious, so erroneous as to imply bad faith, or unsupported by [572]*572substantial evidence in the record as a whole — and that the Board’s ultimate determination was permissible. The fundamental issue before the administrative tribunal, and now before the court, is whether Discount made so little progress on its contract in the summer of 1969 that a default termination was justified. The Government’s notice of termination stated that at the time it defaulted Discount the extent of plaintiffs work was inadequate indication of the diligent performance required to assure completion of the project within the contractual time. The Board found that plaintiff failed to perform sufficient work during the summer of 1969 and that its failure was unexcused, and then concluded that based on Discount’s entire performance the termination was warranted. We hold these determinations to be adequately supported under the Wunderlich Act.

First, the record demonstrates that the Board could allowably find that, despite two resumption-of-work orders and plaintiffs assurances that work would soon resume, no substantial progress was actually made on campground construction during the 1969 work season. As of August 4, 1969 — weeks after the order to resume work had issued and a day after the 10-day cure notice had expired— plaintiff had neither begun more-than-piddling construction activities at the campground, nor assured the Government that it could meet the completion deadline. Nor was any substantial work thereafter undertaken. The significant job left to do was the preparation and completion of the campground, and there was sufficient affirmative proof that Discount did practically nothing toward that goal.5 [573]*573Plaintiff impliedly admits as much when it repeatedly says in its brief that it could not grade the campground without borrow, but that it had no proper place from which to obtain borrow (a cardinal point we discuss later). Discount did do some minor work on other aspects (e.g. on a waterline and some plumbing) but there is very little doubt that it performed little or nothing on the central component — the clearing and grading of the campground.6

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.S. Aeroteam, Inc.
Armed Services Board of Contract Appeals, 2025
Transportation v. Eagle Peak Rock & Paving, Inc.
69 F.4th 1367 (Federal Circuit, 2023)
MOQA-AQYOL JV, LTD.
Armed Services Board of Contract Appeals, 2017
Nelson, Inc.
Armed Services Board of Contract Appeals, 2015
Trust Title Company v. United States
118 Fed. Cl. 99 (Federal Claims, 2014)
Cumberland Casualty & Surety Co. v. United States
82 Fed. Cl. 500 (Federal Claims, 2008)
McDonnell Douglas Corp. v. United States
76 Fed. Cl. 385 (Federal Claims, 2007)
Aptus Co. v. United States
61 Fed. Cl. 638 (Federal Claims, 2004)
Bender GmbH v. Brownlee
106 F. App'x 728 (Federal Circuit, 2004)
Morganti National, Inc. v. United States
49 Fed. Cl. 110 (Federal Claims, 2001)
St. Paul Fire & Marine Insurance v. City of Green River
93 F. Supp. 2d 1170 (D. Wyoming, 2000)
Professional Services Supplier, Inc. v. United States
45 Fed. Cl. 808 (Federal Claims, 2000)
Earth Burners, Inc. v. United States
43 Cont. Cas. Fed. 77,455 (Federal Claims, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
554 F.2d 435, 23 Cont. Cas. Fed. 81,250, 213 Ct. Cl. 567, 1977 U.S. Ct. Cl. LEXIS 30, Counsel Stack Legal Research, https://law.counselstack.com/opinion/discount-co-v-united-states-cc-1977.