Jaxon Construction, Inc.

Armed Services Board of Contract Appeals·Decided June 24, 2026·No. 64432·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) Jaxon Construction, Inc. ) ASBCA No. 64432 ) Under Contract No. W519TC-25-C-A037 )

APPEARANCE FOR THE APPELLANT: Mr. Michael E. Jackson President

APPEARANCES FOR THE GOVERNMENT: Dana J. Chase, Esq. Army Chief Trial Attorney Carter Cassidy, Esq. LTC Anthony V. Lenze, JA MAJ Joseph A. Seaton, JA Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE WOODROW PURSUANT TO BOARD RULE 12.2

Appellant, Jaxon Construction, Inc., appearing pro se through its president, Michael Jackson, elected to proceed under the Board’s Rule 12.2, Small Claims (Expedited) procedure. Accordingly, this decision has no precedential value, and in the absence of fraud is final and conclusive and may not be appealed or set aside. 41 U.S.C. § 7106(b)(4)-(5).

Jaxon appeals the contracting officer’s December 22, 2025 decision terminating its roof-repair contract for default. Jaxon asks the Board to convert the termination for default into a termination for the convenience of the government. The Board held a one-day virtual hearing on May 28, 2026.

The government proved serious deficiencies in Jaxon’s contract administration: missed initial submittal deadlines, unacceptable foundational preconstruction documents by the extended cure deadline, and no physical roof work before termination. Those facts matter, but the issue is the government’s burden in a pre- completion default. Considering the full record—including winter-work constraints, the contracting officer’s reference to a possible winter hold, the uncommunicated safety deficiencies, and the absence of an unequivocal refusal to perform—the government did not prove that default termination was justified. The appeal is sustained. FINDINGS OF FACT

1. On August 22, 2025, the Army awarded Contract No. W519TC-25-C-A037 to Jaxon for $438,765 to remove and replace the low-slope EPDM roof on the Building 222 Annex at Rock Island Arsenal. The firm fixed-price contract required performance inside a secure military installation, including work near or within a munitions area, completion within 80 working days after the Notice to Proceed, and physical construction to begin within 30 workdays after the Notice to Proceed. (R4, tabs 2, 27, 120; tr. 23-24, 45, 77)

2. The Scope of Work required a practicable schedule and Quality Control Plan within 15 days after the Notice to Proceed, remaining technical, safety, and material submittals within 30 days, and use of ENG Form 4025-R for submittal processing (R4, tabs 2 at 49, tab 27 at 523, tab 29 at 583; tr. 27, 29-31, 79, 118).

3. Contractor personnel had to comply with installation access procedures, including NCIC-III screening and in-person operational-security or munitions-area training before unescorted work in the secured area (R4, tab 2 at 51-53, tab 28 at 558- 60; tr. 24-26, 43-46, 88-89).

4. The parties executed the Notice to Proceed on September 18, 2025, making Jaxon’s practicable schedule and Quality Control Plan due October 3 and the remaining preconstruction submittals due October 18 (R4, tab 44; tr. 27-28, 79).

5. On September 18, Mr. Jackson traveled to Rock Island Arsenal for the preconstruction conference but was denied access. The contracting officer’s representative (COR), Jason Rupe, sent Jaxon an access form on September 8, but Mr. Jackson did not return a completed form. Jaxon’s operations manager, Daniel McKibben, passed screening, accessed the installation, and attended the conference. (R4, tabs 43, 121, 130; tr. 24-26, 65, 159-64)

6. Mr. Jackson received written denial and appeal information with telephone, email, and mailing instructions. He did not submit the written appeal documentation or certified court records through that process, although he credibly testified that he called the installation contact four times and that Jaxon raised the issue through the COR and an RFI. (R4, tabs 121, 130; tr. 161-65)

7. We do not find that the government improperly locked Jaxon out, actively hindered performance, breached the duty of good faith and fair dealing, or caused an excusable delay by denying Mr. Jackson access. The denial principally resulted from Jaxon’s failure to complete prescreening and pursue the written appeal process (R4, tabs 43, 121, 130; tr. 25-26, 88-89, 159-65).

2 8. The access issue nonetheless is part of the startup context. Jaxon had to verify existing site conditions, including the roof assembly. On September 23, Jaxon asked for roof-deck and core-sample information, explaining that security requirements prevented the intended site evaluation. Mr. Jackson testified that Jaxon normally would not prepare the Accident Prevention Plan and other technical submittals without physical site information. (R4, tab 2 at 47; tab 51 at 952; tr. 176- 77, 193-97)

9. The federal government shutdown began on October 1, 2025. The contracting officer and COR were available to administer this fully funded contract, and the contracting officer told Jaxon on October 6 that the shutdown did not suspend administrative deadlines. The government’s first review of Jaxon’s initial submittals took 15 days, exceeding the contract’s targeted 10-day period. (R4, tab 51 at 946; tr. 28-29, 42, 80-81, 90, 105, 119-21)

10. The shutdown nevertheless complicated startup. The contracting officer acknowledged that her email had an out-of-office message, that she had not provided alternate contact information, that she checked email only every other day or as needed when called, and that non-excepted personnel could not work (tr. 119-21)

11. Jaxon did not submit its practicable schedule or Quality Control Plan by October 3. Mr. Jackson acknowledged the missed deadline and that missing submittal deadlines on an 80-working-day project made timely completion harder. (R4, tab 51 at 946-48; tr. 27-28, 42, 105, 165-66, 197)

12. On October 16, Jaxon submitted material submittals without an acceptable practicable schedule or Quality Control Plan. The COR rejected some submittals because they did not properly use ENG Form 4025-R or were locked or uneditable. (R4, tab 52; tr. 29-31, 49-52, 101)

13. Jaxon executed a subcontract with Economy Roofing on October 7, according to Mr. Jackson. By December 3, Jaxon had not provided a binding plumbing subcontract, submitting only an unexecuted proposal, and proposed an Alternate Site Safety and Health Officer who lacked the required five years of construction-safety experience. The contracting officer confirmed that the contract did not require a licensed plumber or electrician, contrary to the Notice of Termination’s wording, although the work itself remained required. (R4, tabs 119-20, 126, 131; tr. 34-37, 99-100, 111, 122-23, 137-38)

14. On November 19, the contracting officer issued a cure notice citing failure to make progress, maintain the schedule, submit required administrative documentation, and commence physical work. The notice gave Jaxon ten days to cure. (R4, tab 75; tr. 82)

3 15. On November 20, Jaxon submitted a Practicable Schedule Submission Package proposing spring 2026 roof work and April 2026 completion. The proposal sought a substantial extension, but also responded to the contracting officer’s direction to show the working days needed for physical completion. (R4, tab 84; tr. 84, 189)

16. Before termination, the parties discussed winter limitations and a possible winter hold. The COR testified that EPDM could not be installed below 40 degrees Fahrenheit and that completion by January was impossible as of December 3. The contracting officer testified that, if Jaxon’s December 3 submittals had been approved, the government would have considered a winter hold and a feasible schedule extending to about April 1 (R4, tabs 84, 86; tr.

Free access — add to your briefcase to read the full text and ask questions with AI

Jaxon Construction, Inc., (asbca 2026).

Jaxon Construction, Inc. (Jaxon Construction, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related