D. Joseph Devito, Receiver for Seaview Electric Company v. The United States

413 F.2d 1147, 188 Ct. Cl. 979, 1969 U.S. Ct. Cl. LEXIS 52
CourtUnited States Court of Claims
DecidedJuly 16, 1969
Docket432-65
StatusPublished
Cited by96 cases

This text of 413 F.2d 1147 (D. Joseph Devito, Receiver for Seaview Electric Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D. Joseph Devito, Receiver for Seaview Electric Company v. The United States, 413 F.2d 1147, 188 Ct. Cl. 979, 1969 U.S. Ct. Cl. LEXIS 52 (cc 1969).

Opinion

PER CURIAM:

This case was referred to Trial Commissioner C. Murray Bernhardt with directions to make recommendation for conclusions of law on plaintiff’s motion for summary judgment and defendant’s cross-motion for partial summary judgment under the order of reference and Rule 99(c). The commissioner has done so in an opinion and report filed on November 7, 1968. Defendant filed a request for review by the court of the commissioner’s opinion and the case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court is in agreement with the opinion and recommendation of the commissioner, with modifications, it hereby adopts the same, as modified, as the basis for its judgment in this case, as hereinafter set forth. Therefore, plaintiff is entitled to recover and its motion for summary judgment is granted and defendant’s cross-motion is denied. The case is returned to the ASBCA for determination of recoverable costs under the applicable formula as set forth in the opinion, and proceedings here are suspended for 90 days. Plaintiff shall comply with Rule 100 and the General Order of April 1,1968.

Commissioner Bernhardt’s opinion, as modified by the court, is as follows:

Plaintiff 1 seeks recovery of $150,000 resulting from the default termination of a fixed-price supply contract awarded to Seaview Electric Company by the U. S. Army Signal Corps, for Seaview’s alleged failure to timely deliver certain wire-splicing kits. The Armed Services Board of Contract Appeals (hereinafter, *1149 “ASBCA” or “the Board”) upheld the action of the contracting officer in terminating Seaview’s contract for default. 2 Plaintiff contends that the adverse ASBCA decision is not supported by substantial evidence, is arbitrary and grossly erroneous. Also, that at the time of termination Seaview was not in default because (a) termination occurred prior to the expiration of a reasonable time for performance which should have been granted after Seaview encountered excusable causes of delay, or (b) the termination action was premature because it occurred prior to the passage of a reasonable time for performance after the Government had waived the established delivery schedule. The Board erred as will be shown.

The contract was awarded to Seaview on April 30, 1959, for 11,160 wire-splicing kits at a total contract price of $213,156. Within a month, however, the contract quantity and consideration were approximately doubled, to 22,319 items for $426,292.90, by Modification No. 1 to the contract, dated May 28, 1959. The delivery schedule required submission of preproduction samples by November 2, 1959, and production quantities commencing March 29, 1960. Subsequent to submission of bids, but prior to contract award, Seaview was advised by Government personnel that there were some errors and defects in the contract drawings and specifications. Upon request, Seaview advised that it would correct the deficiencies at no cost to the Government which was done. In all, over 200 changes to the drawings and specifications Seaview found to be necessary were approved by the Government. Pre-production samples were timely submitted on October 29, 1959, and approved by the Government on November 2, 1959. Formal Government acceptance of the samples was issued November 23, 1959.

Thereafter, and prior to the termination, Seaview encountered five alleged causes of delay. These were: (1) the impact of a nationwide steel strike upon the prime contractor and its suppliers and subcontractors; (2) production tolerance difficulties attributed by plaintiff to the extensive changes to the contract drawings and specifications previously mentioned; (3) Seaview’s inability to finalize production plans and tolerances claimed to be due to Government indecision between early March and mid-July of 1960 regarding the finish specified for the wire splicers, after the Government’s discovery that the specified finish was unsuitable for field use; (4) a fire on August 30, 1960, which destroyed most of Seaview’s production space; and (5) the closing of a key subcontractor’s shop at a very critical point in production, on November 4,1960.

The contracting officer never recognized the impact upon plaintiff caused by the second and third of these causes of delay. Due to the steel strike, however, the contract delivery schedule was extended by bilateral agreement in Modification No. 5 to the contract, dated April 7, 1960. This revised schedule required Seaview to deliver 1,000 units by July 29, 1960; 1,835 units each month thereafter through October 28, 1960; and 2,000 units on the 28th of November and each month thereafter until completion on June 28, 1961. This was the official contract delivery requirement at the time of termination on January 16, 1961. There was agreement by the parties to extend to November 29, 1960, the time for the initial delivery installment as a result of the fire at Seaview’s plant, but this agreement was never consummated by formal contractual agreement. The fifth-cited cause of delay remains an issue in this litigation but mooted, as we shall see.

Seaview did not meet the July 29, 1960 first incremental delivery date established by Modification No. 5. It expected to make the first delivery that month. On August 22 the contracting officer ad *1150 vised the company by letter that default action would be withheld until August 31. As a result of the fire which occurred on August 30, the contracting officer indicated by letter dated November 1, 1960, that he would allow a three-months’ delay in delivery, and subsequently forwarded a proposed supplemental agreement incorporating a new delivery schedule proposed by Seaview. This schedule called for 1,000 units to be delivered on November 29, 1960, and 2,000 units per month thereafter, until completion of deliveries on October 29, 1961. The proposed agreement was executed for Seaview and returned to the contracting officer on December 19, 1960, but was not executed by him, and consequently never became a formal part of the contract. The Board tacitly acknowledged this extension, and so do we.

Due to the previously mentioned abrupt shutdown of a key subcontractor, J. & P. Equipment Co., Inc. (hereinafter “J & P”) on November 4, 1960, Seaview did not meet the proposed delivery schedule, but thereafter made deliveries of 420 wire-splicing kits, as follows:

130 units on 11-30-60 to Brooklyn, N. Y.
34 units on 12-8-60 to Fort Benning, Ga.
156 units on 12-20-60 to Fort Gordon, Ga.
100 units on 12-30-60 to:
Fort Devens, Mass. (17 units)
Fort Sill, Okla. (30 units)
Fort Leonard Wood, Mo. (53 units)

On November 25, 1960, the contracting officer requested authority to terminate, 3 and on January 16, 1961, the contracting officer received authority to, and did, terminate, pursuant to the “Default” article of the contract, Seaview’s right to deliver the balance of the contract units, citing as cause therefor Seaview’s failure to timely deliver on the incremental delivery dates.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paragon Defense Solutions, Inc.
Armed Services Board of Contract Appeals, 2025
Consorzio Stabile GMG S.c.ar.1.
Armed Services Board of Contract Appeals, 2023
GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2020
DCX-CHOL Enterprises, Inc.
Armed Services Board of Contract Appeals, 2019
Watts Constructors, LLC
Armed Services Board of Contract Appeals, 2019
State Corps v. United States
Federal Claims, 2019
Delfasco LLC
Armed Services Board of Contract Appeals, 2017
Third Coast Fresh Distribution, L.L.C.
Armed Services Board of Contract Appeals, 2016
Precision Standard, Inc.
Armed Services Board of Contract Appeals, 2015
ASFA International Construction Industry and Trade, Inc.
Armed Services Board of Contract Appeals, 2014
DayDanyon Corporation
Armed Services Board of Contract Appeals, 2014
Spodek v. United States Postal Service
58 F. Supp. 3d 728 (N.D. Texas, 2012)
5860 Chicago Ridge, LLC v. United States
104 Fed. Cl. 740 (Federal Claims, 2012)
Martin Construction, Inc. v. United States
102 Fed. Cl. 562 (Federal Claims, 2011)
United Partition Systems, Inc. v. United States
90 Fed. Cl. 74 (Federal Claims, 2009)
Takota Corp. v. United States
90 Fed. Cl. 11 (Federal Claims, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
413 F.2d 1147, 188 Ct. Cl. 979, 1969 U.S. Ct. Cl. LEXIS 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-joseph-devito-receiver-for-seaview-electric-company-v-the-united-cc-1969.