Kennedy v. United States

164 Ct. Cl. 507, 1964 U.S. Ct. Cl. LEXIS 55, 1964 WL 8588
CourtUnited States Court of Claims
DecidedFebruary 14, 1964
DocketNo. 425-55
StatusPublished
Cited by21 cases

This text of 164 Ct. Cl. 507 (Kennedy v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kennedy v. United States, 164 Ct. Cl. 507, 1964 U.S. Ct. Cl. LEXIS 55, 1964 WL 8588 (cc 1964).

Opinion

Dtjbeee, Judge,

delivered the opinion of the court:

This suit is for costs and termination damages which plaintiff alleges arose out of defendant’s termination of a contract. Defendant counterclaims for damages arising from the contractor’s wrongful default, and for the excessive use of Government supplied materials.

Plaintiff is trustee in bankruptcy for Greenstreet, Inc. In 1950, Greenstreet bid on a supply contract to provide field j ackets for the Army. Proposed quantities and delivery dates were set forth in the Invitation to Bid. Although Greenstreet had no prior experience in the production of field jackets, it nevertheless was awarded the contract on December 23, 1950. The contract was for 100,000 jackets, the first 15,000 to be delivered by January 21,1951. Green-street, expecting to receive the contract, had been preparing for performance. It had ordered 87 pieces of additional equipment, had arranged to increase its factory space, and had negotiated the hiring of a larger, experienced work force.

The award telegram was received on Friday, December 22, 1950, but Greenstreet was unable to contact the Government Procurement Agency which was to supply materials, and was therefore unable to provide shipping instructions until December 26. The carrier named by Greenstreet was unacceptable ; a new carrier was designated, and the first consignment of materials was received on January 2, 1951.

[510]*510Under the contract, a preproduction sample was required. The sample jacket was submitted on January 22, 1951, and was disapproved. Though six different defects were reportedly found in the garment, Greenstreet was advised to proceed with production while correcting the errors.

Production problems were immediately encountered. A discussion of the various problems is included in the findings. The most serious of these arose after Greenstreet had machine-sewed buttons into place as directed by Operation No. 26 of Military Specification MIL-J-843 (29 July 1949). Operation No. 33 required stitching along and approximately two inches from the front edge of the fly. The stitching could not be machine-performed after the buttons were in place. Other contractors, when faced with the same problem, had placed the stitches only 1% inches from the edge, and no objection had been forthcoming from the Quartermaster Corps. But this fact was not known to Green-street. Greenstreet requested permission to deviate, and when no reply was received within a reasonable time, Greenstreet reworked a number of jackets. The buttons were removed by hand, the stitching was put in, and the buttons were replaced by hand. As this process was too time-consuming and costly Greenstreet deviated from the specifications to allow machine performance of these operations on subsequent production. No objection to the deviation was made.

Correction of this and other production problems delayed any January delivery.1 The first lot of completed jackets was submitted on February 16, 1951. Forty garments were selected from the 1,540 submitted. Of these forty, twenty-six were found to have defects. The lot was rej ected. After reworking the lot, 1,400 jackets were re-submitted. Forty garments were again selected for inspection, and all forty garments were found to have defects. The lot was rejected.

Greenstreet was now in financial difficulty. Operations could only continue if delivery of the completed jackets were effectuated and payment was received. An appeal to Green-street’s work force was made, and volunteers continued their [511]*511attempts to correct defects of the rejected lot. While the volunteers were thus engaged, the following communications were exchanged.

On February 20, 1951 the contracting officer sent the following telegram to Greenstreet:

EEUE CONTRACT DA-30-280-51-QM-8638, JACKET, FIELD, WITHOUT LINER, INFORMATION FURNISHED INDICATES THAT PRODUCTION ON THIS CONTRACT HAS STOPPED. INFORM THIS OFFICE BY WIRE AT ONCE AS TO WHEN PRODUCTION WILL RESUME, OR WHAT YOUR INTENTIONS REGARDING COMPLETION OF THIS CONTRACT.

On February 23, 1951, Greenstreet replied as follows by telegram to the contracting officer’s telegram of February 20, 1951:

RETEL WORKING WITH SKELETON CREW TO PREPARE LOT FOR RESUBMISSION FULL SCALE OPERATIONS CANNOT BE REINSTATED UNTIL PROPER FINANCING IS FORTHCOMING

On February 24, 1951, the contracting officer sent the following letter to Greenstreet:

Reference is made to Contract DA-30-280-QM-8638 dated 22 December 1950 for the delivery of 100,000 Jackets, Field without liner, for deliveries commencing 22 January 1951.
In accordance with the provisions of the default article of the contract and by reason of your failure to make deliveries as required under the terms and conditions of the subject contract, your right to deliver the entire contract quantity of 100,000 Jackets, Field without liner, is hereby terminated.
This notice of termination is to be considered as a determination and finding of the contracting officer in accordance with the disputes article of the contract.

The termination notice was received by Greenstreet on February 26, and all work was immediately discontinued. As of that date, 2,500 field jackets had been completed (none had been accepted) and cuttings for an additional 19,860 had been made. No compensation for this work had been paid.

[512]*512Bankruptcy proceedings were instituted, and on March 14, 1951, the United States filed a reclamation petition as a result of which, defendant recovered the materials furnished Greenstreet, including the finished jackets and the cuttings.

A counterclaim based on the termination of the contract and filed by plaintiff was dismissed by the United States Court of Appeals for the Tth Circuit on jurisdictional grounds.

Meanwhile, defendant contracted for the repurchase of the needed field jackets at a cost increased by $37,034.28.

In August of 1955, four years after the above described events transpired, the trustee in bankruptcy requested the contracting officer to make findings of fact on whether Green-street’s default was excusable, and whether the contract prescribed firm delivery dates. The contracting officer found that the default was not excusable and that the dates were firm. The Armed Services Board of Contract Appeals upheld the contracting officer’s action of terminating the contract on the grounds of Greenstreet’s default. Suit was then filed here.

The question here to be decided is whether Greenstreet or the United States caused the termination of the contract. If we hold that defendant caused the termination, we must then decide the nature of the termination — whether it was breach or termination for convenience. If we hold that Greenstreet defaulted, we must determine whether the default was or was not excusable.

Both parties devote considerable time and energy to a discussion of whether defendant caused delay and whether the delivery dates were firm or merely desirable. But Green-street never requested any extension of time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Emiabata v. United States
Federal Circuit, 2019
State Corps v. United States
Federal Claims, 2019
Emiabata v. United States
Federal Claims, 2018
5860 Chicago Ridge, LLC v. United States
104 Fed. Cl. 740 (Federal Claims, 2012)
Keeter Trading Co. v. United States
79 Fed. Cl. 243 (Federal Claims, 2007)
McDonnell Douglas Corp. v. United States
76 Fed. Cl. 385 (Federal Claims, 2007)
Abcon Associates, Inc. v. United States
49 Fed. Cl. 678 (Federal Claims, 2001)
Eagle Aviation, Inc. v. United States
33 Cont. Cas. Fed. 74,055 (Court of Claims, 1985)
Cascade Pacific International v. The United States
773 F.2d 287 (Federal Circuit, 1985)
Thoen v. United States
32 Cont. Cas. Fed. 72,876 (Court of Claims, 1984)
Hutchens v. United States
5 Cl. Ct. 524 (Court of Claims, 1984)
Aiken v. United States
4 Cl. Ct. 685 (Court of Claims, 1984)
Southeastern Airways Corp. v. United States
673 F.2d 368 (Court of Claims, 1982)
National Eastern Corp. v. United States
477 F.2d 1347 (Court of Claims, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
164 Ct. Cl. 507, 1964 U.S. Ct. Cl. LEXIS 55, 1964 WL 8588, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kennedy-v-united-states-cc-1964.