Cascade Pacific International v. The United States

773 F.2d 287, 33 Cont. Cas. Fed. 73,958, 1985 U.S. App. LEXIS 15270
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 16, 1985
DocketAppeal 85-618
StatusPublished
Cited by49 cases

This text of 773 F.2d 287 (Cascade Pacific International v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cascade Pacific International v. The United States, 773 F.2d 287, 33 Cont. Cas. Fed. 73,958, 1985 U.S. App. LEXIS 15270 (Fed. Cir. 1985).

Opinion

JACK R. MILLER, Senior Circuit Judge.

This is an appeal by Cascade Pacific International (“CPI”), from a decision of the General Services Administration Board of Contract Appeals under the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1982) (“CDA”), upholding the Contracting Officer’s decisions to default terminate the subject contract and to grant in part the *289 Government’s claim for breach of contract damages. We affirm.

The issues on appeal are (1) whether the board’s denial of CPI’s claim that the General Services Administration wrongfully terminated its contract for default is supported by substantial evidence, (2) whether the board properly concluded that the Government was entitled to damages for CPI’s breach of the contract, and (3) whether the board’s assessment of damages incurred as a result of CPI’s breach denied CPI its due process right to adequate notice of the assessment imposed upon it.

BACKGROUND 1

CPI entered into a one-year fixed-price supply requirements contract with the General Services Administration (“GSA”) for builders’ hardware (GS-04S-23598) (“ ’598”), including full surface and half surface spring hinges, on July 1, 1980. The contract prices per pair of full surface spring hinges ranged from $2,125 to $2,585, and those for half surface spring hinges ranged from $2,485 to $2,545. The specification indicated that the spring hinges were required to conform to Federal Specification FF-H-116E, which mandated, inter alia, that the spring hinges be plated and have a US10 finish, 2 that the thickness of the metal be 0.082 +/-0.005 inches, and that the spring hinges have button tips.

The contract also contained the standard Inspection and Default clauses, Standard Form 32, April 1975 Revision. Under the contract, the spring hinges were to be submitted for inspection and testing within forty-five days after receipt of an order, before delivery, but the contract language regarding finish or performance testing by the Government was the following:

4. QUALITY ASSURANCE PROVISIONS
4.2 Visual And Dimensional Examination. Hinges furnished under this specification shall be examined for the defects____ The inspection level shall be level II ... with an acceptable quality level____
4.3 Finish and performance. When specified ... samples of hinges from each lot shall be selected in accordance with [regulations]. Samples shall be tested in accordance with 4.4 and 4.5____
4.4 Finish testing. Finishes of hinges shall be tested in accordance with the procedure detailed in ANSI [American National Standards Institute] A156.1.
4.5 Performance testing. Hinges ... shall be tested in accordance with the applicable sections of ANSI A156.1____
6.5 Finishes.
6.5.4 Comparison of standard finishes. Owing to differences in the processes of producing hardware finishes and the variety of metals to which they are applied, it is commercially impracticable to attain an exact match. Therefore, it is understood that hardware delivered in a standard finish from two or more sources will compare reasonably when the items are viewed at arm’s length and approximately two feet apart____

Federal Specification (“FF-H-116E”).

ANSI A156.1, paragraphs 4.1-4.6, describe wear tests for certain types of hinges (but not, explicitly, spring hinges), including a finish test (“Salt Spray” test) that consists of exposing a finished hinge to a salt fog over a period of time followed by visual inspection for signs of corrosion. The test requires that the commercial equivalent of a US10 finish show no “red rust” corrosion to the unaided eye at eighteen hours of salt fog. Builders’ Hardware *290 Manufacturers Association 101, paragraph 5.2, rev. Sept. 1976.

Prior to initiation of the ‘598 contract, GSA had procured full surface and half surface spring hinges from Mallin Lock Manufacturing Co. (“Mallin”), a competitor of CPI. Although Mallin obtained some of its hardware from Lawrence Brothers, Inc. (“Lawrence”), another of CPI’s competitors, Mallin did not obtain from Lawrence full surface or half surface spring hinges.

By mid-October, 1980, CPI had received four orders for spring hinges. For three of the orders, CPI failed to meet the delivery due dates and, therefore, negotiated a price reduction for late delivery. In December, 1980, CPI tendered for inspection a lot of full surface spring hinges to the agency. GSA rejected the lot, explaining that upon inspection the spring hinges had not met the requirements for button tips, metal gauge, and finish type. The spring hinges supplied by CPI had a US10 finish. However, the finish was not plated and, rather, had been achieved by painting over the base metal followed by coating with a clear acrylic lacquer.

In response to the Contracting Officer’s (“CO”) order to CPI to “show cause” why the contract should not be terminated, CPI attempted to negotiate three changes or equitable adjustments to the contract specification in exchange for a price reduction. The agency agreed to make adjustments relating to the base metal thickness and tips, but did not agree to accept painted spring hinges in lieu of plated ones. In response to CPI’s assertion that the paint finish met the performance requirements of the specifications, GSA responded, in pertinent part, that “[t]he deviation from the US3,[ 3 ] brass plated finish required by the contract is not acceptable. The painted finish offered is not as corrosion resistant, nor is it acceptable in appearance.”

On May 7, 1981, CPI informed GSA that if it would not accept painted in lieu of plated spring hinges, “we will be unable to perform.” By May 21, 1981, CPI had missed delivery on all but two of fifteen orders for spring hinges. The last two deliveries were due on or before July 15. In June, GSA again issued an order for CPI to show cause within ten days why it should not be terminated for default. CPI’s contract administrator testified before the board that he attempted to locate alternate sources of the spring hinges. He declared that he. was told by Lawrence that it had supplied Mallin with spring hinges, but would not state whether it presently had the ability to manufacture plated spring hinges. He also testified that other suppliers had told him that plated hinges conforming to the specification “are not and have never been made by any manufacturer with a plated finish.” The CO stated that when she telephoned Mallin, it confirmed that it had manufactured and provided plated spring hinges conforming to FF-H-116E. Mallin provided the CO with samples of its spring hinges and an undated catalogue cut from Lawrence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

West Point Utilities, LLC
Armed Services Board of Contract Appeals, 2025
LKJ Crabbe Inc.
Armed Services Board of Contract Appeals, 2018
SYMVIONICS, Inc.
Armed Services Board of Contract Appeals, 2017
Military Aircraft Parts
Armed Services Board of Contract Appeals, 2017
Capy Machine Shop, Inc.
Armed Services Board of Contract Appeals, 2014
Trust Title Company v. United States
118 Fed. Cl. 99 (Federal Claims, 2014)
M.E.S., Inc. v. United States
104 Fed. Cl. 620 (Federal Claims, 2012)
5860 Chicago Ridge, LLC v. United States
104 Fed. Cl. 740 (Federal Claims, 2012)
Ceradyne, Inc. v. United States
103 Fed. Cl. 1 (Federal Claims, 2012)
Outdoor Venture Corp. v. United States
100 Fed. Cl. 146 (Federal Claims, 2011)
Armour of America v. United States
96 Fed. Cl. 726 (Federal Claims, 2011)
M. Maropakis Carpentry, Inc. v. United States
84 Fed. Cl. 182 (Federal Claims, 2008)
Cumberland Casualty & Surety Co. v. United States
82 Fed. Cl. 500 (Federal Claims, 2008)
Universal Construction, Inc. v. United States
71 Fed. Cl. 179 (Federal Claims, 2006)
Indiana Michigan Power Company v. United States
422 F.3d 1369 (Federal Circuit, 2005)
Southern Comfort Builders, Inc. v. United States
67 Fed. Cl. 124 (Federal Claims, 2005)
Frazier v. United States
67 Fed. Cl. 56 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
773 F.2d 287, 33 Cont. Cas. Fed. 73,958, 1985 U.S. App. LEXIS 15270, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cascade-pacific-international-v-the-united-states-cafc-1985.