West Point Utilities, LLC

CourtArmed Services Board of Contract Appeals
DecidedSeptember 4, 2025
Docket63006
StatusPublished

This text of West Point Utilities, LLC (West Point Utilities, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West Point Utilities, LLC, (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) West Point Utilities, LLC ) ASBCA No. 63006 ) Under Contract No. N62473-19-D-1206 ) Task Order No. N62473-20-F-4216 )

APPEARANCES FOR THE APPELLANT: Kirk E. Niemi, Esq. David B. Wonderlick, Esq. Varela, Lee, Metz & Guarino, LLP Tysons Corner, VA

APPEARANCES FOR THE GOVERNMENT: Allison M. McDade, Esq. Navy Chief Trial Attorney Sharon G. Hutchins, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE WOODROW ON THE GOVERNMENT’S MOTIONS TO STRIKE AND FOR SUMMARY JUDGMENT

This appeal arises from a default termination under an Indefinite Delivery Indefinite Quantity (IDIQ) Multiple Award Construction Contract (MACC) for wet utilities construction projects. In November 2018, the Naval Facilities Engineering Command Southwest (NAVFAC or Navy) awarded West Point Utilities, LLC (West Point) a $249 million MACC covering construction, renovation, and repair projects across six western states. The dispute centers on Task Order No. N62473-20-F-4216 for water treatment plant repairs at Naval Air Facility El Centro, California, with an original completion date of September 22, 2021, later extended to May 12, 2022. Following performance delays and West Point’s responses to cure and show cause notices, the contracting officer terminated West Point for default. West Point challenges this termination and seeks conversion to a termination for convenience, while also alleging additional damages and a breach of its fair opportunity to compete for future task orders.

This matter comes before us on the Navy’s motion seeking dismissal of Counts I and II of West Point’s complaint for lack of jurisdiction and for summary judgment upholding the default termination. We hold that: (1) the Board lacks jurisdiction over West Point’s claims for monetary damages and breach of fair opportunity to compete absent certified claims to the contracting officer; and (2) genuine issues of material fact preclude summary judgment upholding the default termination. Accordingly, we grant the government’s motion to dismiss for lack of jurisdiction to entertain the allegations set forth in paragraphs 84, 85, and Count II (paragraphs 88-91) of West Point’s complaint and, therefore, strike those allegations. 1

Finally, we deny the government’s motion for summary judgment and lift the stay entered pursuant to our November 29, 2021 Order. The government shall file an answer to appellant’s complaint no later than 40 days from the date of this decision.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On November 14, 2018, NAVFAC awarded to West Point - Granite JV, LLC (West Point) Contract No. N62473-19-D-1206, an Indefinite Delivery Indefinite Quantity (IDIQ), Small Business Multiple Award Construction Contact (MACC), for new construction, renovation, and repair of wet utilities construction projects at various Government installations located in California, Arizona, Nevada, Utah, Colorado, and New Mexico. The maximum dollar amount for all the contracts combined was $249,000,000, with an estimated task order range of $300,000 to $20,000,000, and a minimum guarantee of $5,000. (R4, tab 1 at 1)

2. The MACC contract incorporated by reference Federal Acquisition Regulation (FAR) 52.249-10, DEFAULT (FIXED PRICE CONSTRUCTION) (APR 1984) (R4, tab 1 at 25). This provision states, in relevant part:

If the Contractor refuses or fails to prosecute the work or any separable part, with the diligence that will insure its completion within the time specified in this contract including any extension, or fails to complete the work within this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work (or the separable part of the work) that has been delayed

FAR 52.249-10(a)

3. The MACC contract established task order (TO) terms as follows: Section 00801(6)(a) provided a base year of 12 months, which the Contracting Officer (CO) could shorten if the maximum contract amount was ordered earlier. Section 801(6)(b) allowed up to four 12-month option periods for a maximum duration of 60 months or until the estimated maximum dollar value was reached, whichever

1 In a footnote, appellant represents that it will submit a claim requesting an extension of time for completion of the project (app. opp’n at 2 n.1). However, the record contains no indication of this, nor is there any indication that appellant has filed a separate appeal relating to the contract at issue here. 2 occurred first. The Government could exercise these options by providing written notice during the performance period, with preliminary notice required at least 60 days before contract expiration. (R4, tab 1 at 72-73) Paragraph 2 of Section 00803 of the MACC contract also expressly established an opportunity to compete for task orders, stating in relevant part: “[a]ll awardees will be given a fair opportunity to be considered for each Task Order unless the Contracting Officer applies one of the exceptions noted below.” (R4, tab 1 at 80 (emphasis added))

4. The MACC contract established a minimum guarantee of $5,000 to each awardee, as follows:

The Government makes no representation as to the number of Task Orders or actual amount of work to be ordered, however, during the term of the contract, a minimum of $5,000 is guaranteed to each awardee. Contractors are not guaranteed work in excess of the minimum guarantee specified herein.

(Id. at 73)

5. On November 12, 2019, NAVFAC issued Modification No. P0001 to the contract exercising option period one and extending the term of the MACC contract for one year, from November 14, 2019, through November 13, 2020 (R4, tab 2 at 38- 39).

6. On March 16, 2020, NAVFAC awarded to West Point – Granite JV, LLC Task Order No. N62473-20-F-4216, a $14,990,280, firm fixed-price, design-bid-build project for water treatment plant repairs to Basins 343-348 and 352-353 at Naval Air Facility El Centro, El Centro, California. The task order specified a completion date of September 22, 2021. (R4, tab 8 at 54, 56-57).

7. Effective October 6, 2020, NAVFAC and West Point entered into a Change- of-Name Agreement to recognize the contractor’s change of name from West Point - Granite JV, LLC to West Point Utilities, LLC pursuant to the July 27, 2020 amendment to West Point – Granite JV, LLC’s certificate of incorporation (R3, tab 5 at 45-46). Later, on October 27, 2020, NAVFAC issued a modification to the MACC contract, which noted the organizational change and stated that, pursuant to the Change-of-Name Agreement, NAVFAC would issue all subsequent task orders and modifications to West Point Utilities (R4, tab 4 at 43-44 (Modification No. P00003)).

8. In a bilateral modification to the task order, on October 29, 2020, NAVFAC formally changed the contractor’s name to West Point Utilities, LLC, granted a no-cost time extension of 232 days (with a new completion date of May 12, 2022) due to

3 excusable pandemic-related delays impacting financial reporting and bonding, and added a clause prohibiting contracting for certain telecommunications and surveillance equipment. (R4, tab 11 at 716-21 (Modification No. P00002))

9. On November 12, 2020, NAVFAC issued unilateral Modification No. P00005 to the MACC contract exercising option period two for the period of performance from November 14, 2020, through November 13, 2021 (R4, tab 7 at 52- 53).

Cure Notice

10. On March 9, 2021, CO Jessica Garrett issued a Cure Notice citing numerous overdue submittals. The notice warned that failure to address these deficiencies within ten days risked termination for default. At that time, the government estimated West Point was 99 days behind schedule. (R4, tab 15 at 731)

11. On March 19, 2021, West Point responded to the cure notice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Cascade Pacific International v. The United States
773 F.2d 287 (Federal Circuit, 1985)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Dcx, Inc. v. William J. Perry, Secretary of Defense
79 F.3d 132 (Federal Circuit, 1996)
Varilease Technology Group, Inc. v. United States
289 F.3d 795 (Federal Circuit, 2002)
Securiforce International America, LLC v. United States
879 F.3d 1354 (Federal Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
West Point Utilities, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-point-utilities-llc-asbca-2025.