Southern Comfort Builders, Inc. v. United States

67 Fed. Cl. 124, 2005 U.S. Claims LEXIS 225, 2005 WL 1804325
CourtUnited States Court of Federal Claims
DecidedJuly 29, 2005
DocketNo. 00-542C
StatusPublished
Cited by9 cases

This text of 67 Fed. Cl. 124 (Southern Comfort Builders, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Comfort Builders, Inc. v. United States, 67 Fed. Cl. 124, 2005 U.S. Claims LEXIS 225, 2005 WL 1804325 (uscfc 2005).

Opinion

OPINION

HORN, Judge.

This case arises from a contract between the plaintiff, Southern Comfort Builders, Inc., (SCBI) and the National Aeronautics and Space Administration (NASA) to install heating, ventilation, and air conditioning (HVAC) equipment, along with the associated ductwork, wiring and piping in Mobile Launch Platforms (MLPs) for the NASA space shuttles at Kennedy Space Center, Florida. SCBI seeks damages alleging that, during the course of its performance, it encountered defective contract specifications, not obvious before actual performance, and a Type I differing site condition, in that the surfaces, ducts, and pipes of the MLPs were contaminated with lead-based paint, which was not indicated in the bid documents. The lead paint required abatement before SCBI could proceed with the contract. SCBI further claims that NASA improperly administered the contract. According to the plaintiff, the government’s actions, including the defective specifications, differing site conditions and failure to properly administer the contract, all caused delays and loss of productivity, which resulted in added costs, for which plaintiff should be compensated. The plaintiff also alleges that the defendant failed to pay SCBI for its work in accordance with the terms and conditions of the contract, in violation of the Prompt Payment Act, 31 U.S.C. §§ 3901, et seq. (2000). Finally, the plaintiff alleges that the defendant failed to negotiate contract modifications in good faith, which, according to the plaintiff, “constitutes a constructive change to the Contract.” Plaintiffs complaint initially requested damages in the amount of $374,946.00.1

The defendant filed a counterclaim, initially in the amount of $84,657.00. The defendant alleges that the plaintiff failed to provide coordination drawings as required by the contract and, therefore, that the plaintiff saved approximately $30,000.00, the estimated cost of generating the required drawings. In the joint stipulation of facts, however, the defendant reduced this amount and the parties state: “The Government further seeks $6,484.00, which is the Government’s calculation of the total costs of preparing coordination drawings for MLP-1.” The defendant also includes in its counterclaim the cost incurred to replace or correct rejected work, including fan drive mechanisms and belt guards and/or access door interlocks. The contracting officer issued a final decision finding that plaintiff owed the defendant [127]*127$54,475.00 for the cost of the government’s reprocurement, although the defendant admits that $3,500.00 of that amount was not related to work performed by the plaintiff. In the joint stipulation of facts, the defendant seeks $50,975.00 for the reprocurement. The total value of the defendant’s counterclaim is $57,459.00. The defendant is currently holding retainage of $15,975.00.

FINDINGS OF FACT

On March 25, 1998, NASA awarded SCBI contract no. NAS 10-98024 for replacement of HVAC equipment, along with the associated ductwork, wiring and piping in MLPs for the NASA space shuttles at Kennedy Space Center, Florida. The contract was awarded to SCBI based upon a sealed bid totaling $818,056.00. On March 18, 1998, before NASA awarded the contract to SCBI, NASA sent a letter to SCBI requesting confirmation of their bid price. In the letter, NASA stated that SCBI actually was not the lowest bidder, but that the lowest bidder had requested to withdraw its bid because of a mistake in bid. NASA requested SCBI to confirm its bid stating that: “The disparity between [SCBI’s] bid and the other bids and the Government Estimate is of such a magnitude as to indicate the possibility of a mistake in bid.” The record does not indicate how SCBI verified its bid to NASA; however, SCBI was awarded the MLP contract.

The MLP contract was a fixed-price contract with two tasks and one option. Task one required SCBI to replace HVAC equipment in MLP-1. Task two required SCBI to replace HVAC equipment in MLP-2. The contract also included a fixed-price option for MLP-3. Before NASA awarded the MLP contract, a pre-bid site visit was held on February 24, 1998. During the site visit, potential bidders were invited to walk the facility, survey the MLPs and ask the contracting officer questions. Because the solicitation, specifications and diagrams were released before the pre-bid site visit, all potential bidders had an opportunity to review the drawings and specifications included in the solicitation before attending the pre-bid site visit, and to compare the contract specifications to the actual structural measurements in the MLPs. Although SCBI bid on and won the MLP contract, it did not attend the pre-bid site visit. After SCBI won the contract, however, it requested permission from NASA to survey the MLPs to conduct measurements. On April 2, 1998, the defendant informed SCBI that it could inspect MLP-1 on April 6, 7, and 8,1998, and MLP-3 on April 6, 7, 8, 9, and 10, 1998. On April 9, 1998, SCBI visited MLP-1. Curtis Reed, SCBI’s project superintendent, stated at the trial that the purpose of the inspection was only to measure the MLP doors to determine how SCBI would fit its equipment into the MLPs and that the defendant did not permit SCBI access to the MLP to compare the contract specifications to the actual measurements of the equipment within the MLPs. A daily construction log entry drafted by the defendant on April 9, 1998, shows that SCBI visited MLP-1 “to take door opening measurements.” Another construction log entry drafted by the defendant indicates that SCBI visited the MLPs on the evening of May 6, 1998, “to take measurements and plan lifting procedure.”

The government issued SCBI a notice to proceed on April 3, 1998. Pursuant to the notice, SCBI was required to complete all contract performance, including punch list items, by December 28, 1999. In the notice, the government also stated that SCBI should “[k]eep in mind that access to the construction site will be governed by the Work Area Access Constraints’ clause.” The constraints clause of the contract is found at Article 18 of the contract, which discusses the particular time and access restrictions within which SCBI was to complete the contract. Specifically, the contract was restrictive in that it set forth the precise sequence in which SCBI was to complete the MLP work and required all work packages to be completed in three modification periods or work windows, each six weeks long. The contract included thirteen work packages for each MLP, which were required to be performed during the NASA specified work windows.

The MLP contract specified SCBI’s work sequence by requiring that: “All tasks within a modification period shall be performed in the sequence shown for those tasks in that [128]*128modification period.” The contract, however, also stated that “the sequence in which the modification periods (work windows) containing these tasks will be performed will be based upon MLP availability and will be determined by the Government.” By a letter dated June 22, 1998, NASA informed SCBI that MLP-1 would be available from June 10 — July 21, 1998 for the first work window. Although the letter was sent after the work window commenced, the letter stated that it confirmed “previous informal discussions, provided at status meetings prior to the work window, which the parties agreed would suffice for notification of this work window.”

SCBI commenced work on the MLP contract in June, 1998.2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baker DC, LLC v. Baggette Constr., Inc.
378 F. Supp. 3d 399 (D. Maryland, 2019)
Flatiron-Lane v. Case Atlantic Co.
121 F. Supp. 3d 515 (M.D. North Carolina, 2015)
PCL Construction Services, Inc. v. United States
84 Fed. Cl. 601 (Federal Claims, 2008)
Caddell Construction Co. v. United States
78 Fed. Cl. 406 (Federal Claims, 2007)
Laurelwood Homes LLC v. United States
78 Fed. Cl. 290 (Federal Claims, 2007)
Sarang Corp. v. United States
76 Fed. Cl. 560 (Federal Claims, 2007)
Inversa, S.A. v. United States
73 Fed. Cl. 245 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
67 Fed. Cl. 124, 2005 U.S. Claims LEXIS 225, 2005 WL 1804325, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-comfort-builders-inc-v-united-states-uscfc-2005.