San Carlos Irrigation and Drainage District v. The United States

877 F.2d 957, 1989 WL 59813
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 24, 1989
Docket89-1007
StatusPublished
Cited by239 cases

This text of 877 F.2d 957 (San Carlos Irrigation and Drainage District v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
San Carlos Irrigation and Drainage District v. The United States, 877 F.2d 957, 1989 WL 59813 (Fed. Cir. 1989).

Opinion

BISSELL, Circuit Judge.

The San Carlos Irrigation and Drainage District (District) appeals the United States Claims Court’s judgment granting the government’s summary judgment motion and dismissing the complaint. See San Carlos Irrigation & Drainage Dist. v. United States, 15 Cl.Ct. 197 (1988). We reverse and remand.

BACKGROUND

In 1924, Congress authorized construction of the Coolidge Dam across the Gila River as part of the San Carlos Irrigation Project (Project). Act of June 7, 1924, ch. 288, 43 Stat. 475. The stated purposes of the Act were to “provid[e] water for the irrigation of lands allotted to Pima Indians on the Gila River Reservation, Arizona,” and to “irrigat[e] such other lands in public or private ownership, as in the opinion of the [Secretary of the Interior] can be served ... without diminishing the supply necessary for said Indian lands.” Id. at 475. The total cost of the Project was to be distributed equally per acre among the Indian lands and the public or private lands served by the Project. Id. The Act authorized the Secretary to enter into a construction repayment contract with a district embracing the publicly-owned or privately-owned lands. Id. at 476. Four years later, Congress supplemented the Act to authorize the Secretary of the Interior (Secretary) to develop electrical power at the Coolidge Dam, to recoup power plant construction costs under a repayment contract, to sell the dam’s surplus power, and to apply the net revenues to reimburse the government for power plant construction, irrigation project construction, and operation and maintenance of the irrigation project, in that order. Act of March 7, 1928, ch. 137, 45 Stat. 200, 210-11.

The non-Indian landowners organized the District to represent them in dealings with the Secretary. On June 8, 1931, the District entered into a repayment contract with the government (Repayment Contract). The Repayment Contract defined the Project Works as including, inter alia, the Coolidge Dam, the San Carlos Reservoir, and everything pertaining thereto, including the power plant and electrical transmission lines. The government agreed to continue to maintain all of the Project Works, and the District agreed to pay annually five percent of the Project’s construction costs and all operating and maintenance costs. The Repayment Contract was subsequently supplemented to set the amount of annual repayment on a sliding scale according to the amount of water in the reservoir. After the dam’s completion in 1931, the government through the Bureau of Indian Affairs assumed exclusive control and management of the Project Works’ operation and maintenance.

Subsequently, the Secretary executed a Joint Works Order defining the Joint Works to include the Coolidge Dam, San Carlos Reservoir and electrical power generating, transmission and distribution system, and continuing the government’s responsibility of operating and maintaining those structures. The Order gave the District responsibility for operating and maintaining the segments of the Project Works serving the District lands exclusively.

On October 1,1983, a storm caused large inflows of water into the San Carlos Reservoir. The reservoir began to spill over the spillway crest two days later. The electrical switchyard located between the dam and the powerhouse began to settle, causing the soil to cave in and result in damage to the switchyard’s electrical equipment. The dam was shut down and evacuated, *959 leaving no way to generate electrical power or store water.

The District filed suit for breach of its contracts and agreements with the government. The District sought, inter alia, specific damages for one-half of the irrigation water lost and one-half of the electrical energy lost as a result of the dam’s inoper-ability. The government moved for summary judgment arguing, inter alia, that the Repayment Contract does not give rise to a contractual duty to operate and maintain the spillway gates in order to benefit the District. The Claims Court found that the government “expressly agreed ... to operate and maintain the project,” San Carlos, 15 Cl.Ct. at 203, but characterized the District’s complaint as only alleging the breach of two contractual duties — (1) to maintain the dam’s designed storage capacity by properly operating and maintaining the spillway gates and (2) to generate and sell electrical power by properly operating and maintaining the electrical generation system. Id. at 202. In granting the government’s summary judgment motion, the Claims Court concluded that the duties alleged by the District were not created by the Repayment Contract and, therefore, the District had failed to state a claim for which relief could be granted. Id. at 203-04.

ISSUES *

1. Whether the Claims Court erred in granting summary judgment.

2. Whether the District’s claim sounds in tort, thus precluding the Claims Court from exercising jurisdiction.

OPINION

I

To recover for breach of contract, a party must allege and establish: (1) a valid contract between the parties, (2) an obligation or duty arising out of the contract, (3) a breach of that duty, and (4) damages caused by the breach. See Giroir v. MBank Dallas, N.A., 676 F.Supp. 915, 918-19 (E.D.Ark.1987); see also Pennsylvania, Dept. of Transp. v. United States, 643 F.2d 758, 762 (Ct.Cl.) (noting “the well-established rule ... that a ‘government contractor bears the burden of establishing the fundamental facts of liability, causation and resultant injury’ ” (citations omitted)), cert. denied, 454 U.S. 826, 102 S.Ct. 117, 70 L.Ed.2d 101 (1981). The District’s complaint was incorrectly recast by the Claims Court as asserting only the specific duties of maintaining the spillways and maintaining the electrical generation facilities. The Claims Court failed to recognize that the District also expressly alleged a contractual duty requiring the government to operate and maintain the entire Joint Works. Complaint at 7, 8, San Carlos Irrigation & Drainage District v. United States, 15 Cl.Ct. 197 (1988).

The Claims Court concluded that the Repayment Contract could not be interpreted to show that the damages for lost water and lost electricity sought by the District were within the parties’ contemplation. San Carlos, 15 Cl.Ct. at 202. Reliance upon that conclusion to hold that the District had failed to allege a duty which, if breached, would allow recovery of damages is inappropriate. Such an analysis is relevant to determining whether the District can prove that it has suffered any consequential damages. Cf. Prudential Ins. Co. of Am. v. United States, 801 F.2d 1295, 1300 (Fed.Cir.1986) (holding that consequential or special damages, in order to be recoverable, must be foreseeable at the time the contract is executed), cert. denied, 479 U.S. 1086, 107 S.Ct. 1289, 94 L.Ed.2d 146 (1987).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
877 F.2d 957, 1989 WL 59813, Counsel Stack Legal Research, https://law.counselstack.com/opinion/san-carlos-irrigation-and-drainage-district-v-the-united-states-cafc-1989.