James A. Boyajian, Assignee of Triumph Manufacturing Company, Bankrupt v. The United States

423 F.2d 1231, 191 Ct. Cl. 233, 1970 U.S. Ct. Cl. LEXIS 27
CourtUnited States Court of Claims
DecidedMarch 20, 1970
Docket261-60
StatusPublished
Cited by104 cases

This text of 423 F.2d 1231 (James A. Boyajian, Assignee of Triumph Manufacturing Company, Bankrupt v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James A. Boyajian, Assignee of Triumph Manufacturing Company, Bankrupt v. The United States, 423 F.2d 1231, 191 Ct. Cl. 233, 1970 U.S. Ct. Cl. LEXIS 27 (cc 1970).

Opinion

OPINION

PER CURIAM.

This case was referred to Trial Commissioner Saul Richard Gamer with directions to make findings of fact and recommendation for conclusions of law under the order of reference and Rule 57(a) [since September 1, 1969, Rule 134 (h)]. The commissioner has done so in an opinion and report filed on April 30, 1969. Exceptions to the commissioner’s opinion, findings and recommended conclusion of law were taken by plaintiff, defendant urged their adoption, and the case has been submitted to the court on oral argument of counsel and the briefs of the parties. The commissioner’s discussion of, and refusal to apply, the “total cost” theory of damages is wholly consistent with our recent decision in H. John Homan Co., Inc. v. United States, 418 F.2d 522, 189 Ct.Cl. 500 (1969). In Homan there were factors — pointed out in the opinion in that case — calling for use of that theory which are absent here. Since the court agrees with the opinion, findings and recommended conclusion of law of the trial commissioner, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Therefore, plaintiff is not entitled to recover and the petition is dismissed.

OPINION OF COMMISSIONER

GAMER, Commissioner.

The petition herein sets forth, in six causes of action, various claims arising out of production contracts which the Triumph Manufacturing Company, an Illinois corporation, entered into with the Air Force in 1955 and 1956. Triumph was adjudged a bankrupt in 1958, and in 1960, as authorized by an order of the bankruptcy court, all of its right, title, and interest in the claims herein were assigned to plaintiff, who was Triumph’s president and principal stockholder. For convenience, however, Triumph will sometimes be referred to as the plaintiff.

On defendant’s motion for summary judgment, the court, by order of October 30, 1964, dismissed the fifth cause of action. Thereafter, trial proceedings were conducted with respect to the remaining five causes.

The causes of action left for consideration are grounded upon contracts for the manufacture of “Modulators,” 1 as well as a contract for the manufacture of “Interval and Dwell Testers.” 2 There *1233 were three Modulator contracts dated October 24, 1955, May 2, 1956, and July 20, 1956, respectively, but they were generally administered as one. (Essentially, the second and third contracts constituted additions to the original quantity.) 3 Accordingly, they will sometimes be referred to collectively as the Modulator contract. The Interval and Dwell Tester contract was dated February 10, 1955.

THE MODULATOR CONTRACT CLAIMS

First Cause of Action

The contract provided that preproduction models, referred to as “First Articles,” be submitted to defendant for testing and approval prior to the commencement of full-scale production. Plaintiff contends that it manufactured the three required models and, prior to their submission to defendant, it proceeded, as provided by the contract, to test them to make certain they were properly calibrated; that such tests were performed in accordance with a method authorized by the contract, i. e., the “interference pattern method”; that, in applying such test method, plaintiff complied in all respects with the specified procedures; that defendant, however, knew from past experience on previous contracts, but wrongfully failed to disclose to plaintiff, that such procedures were defective and that it would, therefore, be difficult to attain proper calibration with their use; that, upon plaintiff’s submission of the models in October 1956, defendant tested them by using a different method, i. e., by employing certain test equipment called a “Zifor”; 4 that the Zifor was a relatively new item, manufactured by the Collins Radio Company, which quickly gave accurate calibration results; that defendant’s Zifor tests showed that the three submitted First Articles were not properly calibrated, resulting in their rejection; that defendant then wrongfully insisted that the First Articles, as well as all 529 Modulators to be produced, be thereafter tested and calibrated only in accordance with the Zifor; that, although defendant lent a Zifor to plaintiff for the limited purpose of properly calibrating the First Articles, which were thereafter accepted on January 31, 1957, plaintiff was required to purchase a Zifor from the Collins Radio Company for use in its contract production operations and that plaintiff could not, therefore, commence such operations until it had obtained a Zifor; and that defendant’s insistence upon plaintiff’s use of a Zifor caused a six-month delay in the performance of the contract in that plaintiff was not able to obtain one until April 1957 and could, therefore, make no substantial or effective production progress until such time. Plaintiff says that the furnish-, ing by defendant of inaccurate and defective interference pattern method calibration procedures, as well as its knowledge, but failure to make disclosure, of such defective procedures and the resultant difficulties of obtaining accurate results from the use thereof, constituted breaches of the contract. It argues that, had it known in October 1955, when the contract was awarded, that the interference pattern method would be useless, and that defendant would insist on the Zifor procedure instead, it could have then promptly ordered a Zifor and would have had ample time to obtain it prior to the submission of the First Articles a *1234 year later in October 1956, 5 so that production could have then immediately commenced. Thus, says plaintiff, the six-month delay in production to April 1957, during which period plaintiff’s overhead and other expenses continued, would have been avoided. This cause of action is based upon such delay damages.

Second Cause of Action

Plaintiff contends that the aforesaid six-month delay in production to April 1957 depleted its capital to such an extent that it was unable to continue with performance; that, to enable plaintiff to continue, plaintiff and the Air Force, under date of April 10, 1957, entered into an “Advance Payment Pool Agreement” under which defendant agreed to advance to plaintiff amounts not to exceed $250,000; that defendant, on April 10, 1957, and July 18, 1957, advanced the sums of $160,000 and $20,000, respectively, but despite plaintiff’s need for the balance of $70,000 to obtain the smooth production flow incident to large-scale production, defendant arbitrarily and capriciously refused to advance any additional sums; and that defendant’s refusal was, under the circumstances, a breach of contract, resulting in inefficient, costly, and delayed contract performance. 6

Third Cause of Action

This cause is grounded upon the same facts as the first cause of action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anthony and Gordon Construction Co.
Armed Services Board of Contract Appeals, 2021
East Coast Repair & Fabrication, LLC v. United States
199 F. Supp. 3d 1006 (E.D. Virginia, 2016)
BAE Systems San Francisco Ship Repair
Armed Services Board of Contract Appeals, 2016
E & E Enterprises Global, Inc. v. United States
120 Fed. Cl. 165 (Federal Claims, 2015)
Eden Isle Marina, Inc. v. the United States 0
113 Fed. Cl. 372 (Federal Claims, 2013)
Wayne Knorr, Inc. v. Department of Transportation
973 A.2d 1061 (Commonwealth Court of Pennsylvania, 2009)
System Fuels, Inc. v. United States
79 Fed. Cl. 37 (Federal Claims, 2007)
Caddell Construction Co. v. United States
78 Fed. Cl. 406 (Federal Claims, 2007)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)
North Star Alaska Housing Corp. v. United States
76 Fed. Cl. 158 (Federal Claims, 2007)
A. G. Cullen Construction, Inc. v. State System of Higher Education
898 A.2d 1145 (Commonwealth Court of Pennsylvania, 2006)
Tennessee Valley Authority v. United States
69 Fed. Cl. 515 (Federal Claims, 2006)
Orlosky Inc. v. United States
68 Fed. Cl. 296 (Federal Claims, 2005)
Southern Comfort Builders, Inc. v. United States
67 Fed. Cl. 124 (Federal Claims, 2005)
City of Westminster v. Centric-Jones Constructors
100 P.3d 472 (Colorado Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
423 F.2d 1231, 191 Ct. Cl. 233, 1970 U.S. Ct. Cl. LEXIS 27, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-a-boyajian-assignee-of-triumph-manufacturing-company-bankrupt-v-cc-1970.