Snyder-Lynch Motors, Inc. v. United States

154 Ct. Cl. 476
CourtUnited States Court of Claims
DecidedJuly 19, 1961
DocketNo. 233-57
StatusPublished

This text of 154 Ct. Cl. 476 (Snyder-Lynch Motors, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Snyder-Lynch Motors, Inc. v. United States, 154 Ct. Cl. 476 (cc 1961).

Opinion

Laramore, Judge,

delivered the opinion of the court:

This is an action for damages arising out of two contracts. Under a facilities contract, Ord-244, the Government agreed to furnish plaintiff certain facilities needed to perform a supply contract. The second contract, DA-04-495-OE.D-242, in the amount of $1,054,207.50, was for the rebuilding of 750 tank engines.

Plaintiff claims for recovery in four counts against the United States, the sum of $782,167.23 for alleged misrepresentation and breach of the two contracts above referred to. Under count one, claim is made for $101,739.16 of additional costs for extra work in the procurement of parts for the rebuilding of 750 GAA engines for M4A3 tanks, by reason of misrepresentation of the replacement parts required and procured on behalf of defendant.

Under count two, claim is made for $92,544.18 of increased costs by reason of the refusal and neglect of defendant’s authorized agents to comply with the contract provisions, and their interference with plaintiff’s efficient performance.

Under count three, claim is made for damages of $582,-883.89 against the defendant for withholding of reimbursement payments due plaintiff under its contract that required, [478]*478in part, the procurement of engine parts on behalf of the defendant.

Under count four, claim is made for $5,000 of increased costs to plaintiff by reason of the failure of the defendant to inspect facilities within a reasonable time, which had been procured and installed on behalf of the defendant, under a facilities contract, for use in rebuilding the 750 GAA engines, thereby delaying the reimbursement to plaintiff for its costs in acquiring and installing said facilities.1

The facts are voluminous and will be referred to here only to the extent necessary to each count of plaintiff’s claim. Each count will be dealt with separately. The facts respecting each contract are fully found by the commissioner and adopted by the court.

Under count one of plaintiff’s claim the charge is made that defendant misrepresented the amount of replacement parts required.

The facts show that the defendant, after considerable experience under a like contract with the firm of Bowen and McLaughlin, on October-31, 1951, sent Mr. Wesley M. San-didge, Chief of the Tank Automotive Branch, and Mr. Thomas E. Carpenter, a contract negotiator with the Los Angeles Ordnance District (LAOD), to plaintiff’s plant with the view of interesting plaintiff in rebuilding tank engines.

After certain negotiations plaintiff decided to bid on the rebuilding process. Prior to submitting its bid, the plaintiff requested a specimen engine that could be torn down and rebuilt for a practical test of the time and labor involved. The plaintiff was unable to obtain such an engine through LAOD, but did acquire one from another source for this purpose.

Following its study, plaintiff submitted a bid of $911.32 per engine. However, plaintiff’s representatives were advised [479]*479that this sum was too high, and plaintiff agreed to refigure it. Finally, a revised estimate was submitted which, after certain adjustment, was in the amount of $605.61 per engine. However, at no time did the plaintiff submit a bid estimate of $800 for parts in rebuilding the engine. Plaintiff was advised by Mr. Sandidge, Chief of the Tank Automotive Division, and Mr. Henry C. Genthe, a contract negotiator, that the cost would be about $800 for each engine, and the plaintiff relied on this estimate in figuring its fixed price bid for rebuilding. The award was then diverted from Bowen and McLaughlin to plaintiff, Snyder-Lynch Motors, Inc.

The facts further show that when the first contract was awarded to Bowen and McLaughlin for the same rebuilding early in 1951, there was very little information available for a determination of the cost or requirements of replacement parts. The estimate of $800 per engine proposed by the contract negotiator was merely for the purpose of an allotment of funds.

When the procurement order was received for the 750 engines, the defendant was in possession of information resulting from the experience of Bowen and McLaughlin that the cost of parts would substantially exceed the original estimate of $800. As a matter of fact, the cost of parts was approximately 145.5 percent over and above the estimated requirements. However, plaintiff was not advised of these facts and actually had no information regarding the required replacement parts, or the cost of the same at. the time its contract was negotiated.

Based on these and other facts, of record, the commissioner has found that:..' • . ' .

It is reasonable to conclude that the contracting of ficer, the contract negotiator and LAOD knew that $800 per engine was inadequate for the cost of replacement of parts prior to negotiating the plaintiff’s contract, but that the estimate of $800 per engine was used in plaintiff’s contract for the firm commitment of funds in the fiscal period, as had been done in the Bowen & McLaughlin contract in early 1951.

We think the Government was remiss in not making the information regarding the Bowen and McLaughlin experience available to plaintiff. Based on this conclusion, the [480]*480withholding of this information constituted a breach of the contract, and the plaintiff is entitled to recover the damages flowing therefrom. Ragonese, et al. v. United States, 128 Ct. Cl. 156; Bateson-Stolte, Inc. v. United States, 145 Ct. Cl. 387. Plaintiff’s unrecovered indirect costs of procuring the tank engine parts was $87,587.06. Plaintiff is entitled to damages in that amount on count one of its claim for the breach of the contract.

In count two plaintiff contends that defendant’s inspectors and agents interfered with plaintiff’s usual and customary operations and imposed certain requirements in violation of the contract provisions and specifications for the rebuilding of tank engines under contract Ord-242.

Plaintiff’s theory of this claim is that the defendant’s inspector, Jones, was responsible for all excess costs to June 30,1952. This is not sustained by the evidence. Conceding, however, that defendant did interfere with plaintiff’s operations, the record discloses and the commissioner has found that there is no proof of any excess costs that may be attributed to any improper action or failure on the part of defendant’s inspectors or officials. Under these circumstances, plaintiff cannot recover on this item of the claim for failure to prove damages, and count two will be dismissed.

Count three is for damages resulting from defendant’s alleged withholding of reimbursement payments due plaintiff under the contract. Plaintiff contends that the action of the defendant in withholding, from payments for reimbursable items, amounts to cover checks issued for reimbursement for direct charges, which checks had not cleared the bank within 30 days from the date of the checks, amounts to arbitrary and capricious action. Plaintiff then says that because of such action it was unable to continue its financing arrangements and that by reason thereof plaintiff was forced to and did sell its automobile agency together with equipment and inventory and that it thereby suffered a loss.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bateson-Stolte, Inc. v. United States
172 F. Supp. 454 (Court of Claims, 1959)
Ragonese & Scaravelli v. United States
120 F. Supp. 768 (Court of Claims, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
154 Ct. Cl. 476, Counsel Stack Legal Research, https://law.counselstack.com/opinion/snyder-lynch-motors-inc-v-united-states-cc-1961.