Southern Nuclear Operating Co. v. United States

77 Fed. Cl. 396, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20190, 65 ERC (BNA) 1713, 2007 U.S. Claims LEXIS 220, 2007 WL 2005164
CourtUnited States Court of Federal Claims
DecidedJuly 9, 2007
DocketNo. 98-614C
StatusPublished
Cited by42 cases

This text of 77 Fed. Cl. 396 (Southern Nuclear Operating Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Nuclear Operating Co. v. United States, 77 Fed. Cl. 396, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20190, 65 ERC (BNA) 1713, 2007 U.S. Claims LEXIS 220, 2007 WL 2005164 (uscfc 2007).

Opinion

OPINION

MEROW, Senior Judge.

Two nuclear utilities seek damages for the failure of the United States Department of Energy (“DOE”) to commence performance of its contract to accept, transport and dispose of their spent nuclear fuel (“SNF”).1 Because of DOE’s delay in commencement of performance, these utilities have incurred enormous expenses to construct additional storage for their SNF, passed on to their customers along with the some $825 million in fees plaintiffs have paid under the contract as of 2004. (Tr. 251 (Cocherell).)

The court has jurisdiction over plaintiffs’ claims. PSEG Nuclear, L.L.C. v. United States, 465 F.3d 1343 (Fed.Cir.2006) (holding that the Nuclear Waste Policy Act (“NWPA”) did not strip the court of its Tucker Act jurisdiction over claims arising out of the Standard Contract). Partial breach has been established. Indiana Michigan Power Co. v. United States, 422 F.3d 1369, 1372-73 (Fed.Cir.2005) (finding DOE liable for breach of contract); Maine Yankee Power Co. v. United States, 225 F.3d 1336, 1342 (Fed.Cir.2000), aff'g Yankee Atomic Elec. Co. v. United States, 42 Fed.Cl. 223 (1998) (DOE’s failure to begin performance by January 31, 1998 was a partial breach and “[t]he breach involved all the utilities that had signed the contract—the entire nuclear electric industry.”). Accordingly, the court granted plaintiffs’ motion for partial summary judgment on liability for partial breach of contract. “There is no dispute concerning the fact that the United States, operating through the DOE, failed to meet the contractual requirement to begin disposition of the nuclear waste covered by the Standard Contracts by no later than January 31, 1998.” (Order, Apr. 7, 2004, Dkt. 234, 5.)

The Federal Circuit held in Indiana Michigan, that while nuclear utilities could not recover their forecasted future costs of storing SNF that DOE contracted to remove, appropriately established and incurred mitigation expenses were recoverable. On September 15, 2005, the parties agreed that trial in this matter would be limited to costs incurred through December 31, 2004. On September 16, 2005, the court ordered that “[t]he scope of the trial proceedings in this matter will comprise damage evidence up to and including December 31, 2004.” (Order, Sept. 16, 2005, Dkt. 304, 2.) Plaintiffs’ Amended and Supplemental Complaint for damages through December 31, 2004 was deemed filed as of October 11, 2005. (Order, Oct. 26, 2005, Dkt. 315.) After a lengthy trial, the parties submitted post-trial briefs.2 [399]*399Oral argument and supplemental briefing followed.

Introduction

Following the enactment of the NWPA, Pub.L. No. 97-425, 96 Stat. 2201 (Jan. 7, 1988) (codified at 42 U.S.C. §§ 10101-10270), plaintiffs, along with all domestic nuclear electrical utilities, signed Standard Contracts with DOE wherein, in return for the utilities’ payment of substantial fees, DOE would accept title to designated SNF at the reactor sites, and transport and dispose of the utilities’ SNF, starting on or before January 31, 1998. DOE did not commence performance by January 31, 1998 as required by the NWPA and the Standard Contracts. While DOE insists there will be performance, the forecasted inauguration continues to recede from 2003, to 2010, to 2017, and to 2018, the latest prognosis.

Standard Contracts were signed by plaintiffs Georgia Power Company (“GPC”) and Alabama Power Company (“APC”). APC owns Plant Farley. GPC holds a majority interest in Plants Hatch and Vogtle.3 Each of the these electrical plants have two nuclear reactors. (Tr. 134 (Long).) Hatch Unit 1 began operation in 1974; Unit 2 in 1978. Farley Units 1 and 2 started in 1977 and 1981, and Vogtle in 1987 and 1989. Plaintiff Southern Nuclear Operating Company (“SNC”) operates the plants and is agent for APC and GPC on matters relating to the Standard Contracts. (Tr. 126-27 (Long).) SNC, APC and GPC are subsidiaries of the Southern Company, a holding company. (Tr. 126 (Long).)

Plaintiffs seek reimbursement of their actual costs spent mitigating DOE’s delays. Rather than allow their spent fuel pools to completely fill with SNF, which would result in shutting down their reactors, replacing that source of electricity at a much higher cost, plaintiffs decided to incur the relatively lesser expense of additional on-site storage. Substantial costs (the amounts of which are mostly not disputed) were incurred to design, engineer, license, construct, install, load, operate and maintain this additional storage. As described in more detail hereinafter, at Plant Hatch, an Independent Spent Fuel Storage Installation (“ISFSI”), consisting of four highly-engineered concrete pads, each with a capacity to hold twelve dry SNF storage casks, was built. By December 31, 2004, twenty-two casks were purchased, loaded with SNF and placed on the pads. Construction of Plant Farley’s ISFSI began in 2000, and as of December 31, 2004, three dry SNF storage casks were purchased but had not been loaded. From 1998 to 2000, Plant Vogtle procured and installed racks to increase the capacity of its spent fuel pool. The actual costs of these mitigation measures are sought in this action.

Upon careful consideration of testimony, argument, documents and exhibits, the court concludes that plaintiffs incurred substantial costs in mitigating DOE’s acknowledged, continuing and substantial delay in commencement of performance—a partial breach of contract, which was a substantial causal factor in these mitigating storage decisions and of the reasonable costs thereof, and that but for the delay, these expenditures would not have been incurred. The court finds that, in the main, those mitigation decisions and costs were foreseeable and reasonable.

• A brief discussion of the generation of nuclear power provides background for the court’s findings and conclusions. Uranium oxide pellets (little finger-sized) are placed into 12-14 foot metal rods and bundled into assemblies, approximately nine inches square. Assemblies are placed in the reactor core, where fission produces heat, which is converted to steam, which drives turbines and generates electricity. (Tr. 142 (Long).) Nuclear-generated power constitutes 16 percent of the total electricity used by plaintiffs’ some four million customers4 and is their [400]*400most cost efficient and emission-free form of electrical generation. (Tr. 136 (Long).) Louis Long, SNC Vice President, with 35 years of nuclear power generation experience, testified about the importance of these nuclear plants and set the stage for the mitigating decisions discussed herein:5

A. [T]he Southern system has a system that’s about 40,000 megawatts total. In that system, power is generated from basically four different sources. One is our coal plant. That’s our largest ... about 69 percent of the power that’s generated by the Southern Company comes from the coal plants. [Sixteen] percent, the second largest generator of electricity in the Southern system is out of our nuclear plants. And then we also have about 12 percent comes from gas and then about 3 percent comes from hydro. So nuclear is the second largest generator of electricity on the Southern system. The importance, though, is really relative to the cost of electricity out of those four sources.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Georgia Power Company v. United States
132 Fed. Cl. 412 (Federal Claims, 2017)
Alabama Power Company v. United States
119 Fed. Cl. 615 (Federal Claims, 2014)
Energy Northwest v. United States
115 Fed. Cl. 69 (Federal Claims, 2014)
Portland General Electric Co. v. United States
107 Fed. Cl. 633 (Federal Claims, 2012)
Southern Nuclear Operating Co. v. United States
637 F.3d 1297 (Federal Circuit, 2011)
Kansas Gas & Electric Co. v. United States
95 Fed. Cl. 257 (Federal Claims, 2010)
Entergy Nuclear Vermont Yankee, LLC v. United States
95 Fed. Cl. 160 (Federal Claims, 2010)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
Entergy Nuclear Fitzpatrick, LLC v. United States
93 Fed. Cl. 739 (Federal Claims, 2010)
Arizona Public Service Co. v. United States
93 Fed. Cl. 384 (Federal Claims, 2010)
Southern California Edison Co. v. United States
93 Fed. Cl. 337 (Federal Claims, 2010)
System Fuels, Inc. v. United States
92 Fed. Cl. 101 (Federal Claims, 2010)
Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)
Dominion Resources, Inc. v. United States
84 Fed. Cl. 259 (Federal Claims, 2008)
Sacramento Municipal Utility District v. United States
293 F. App'x 766 (Federal Circuit, 2008)
Carolina Power & Light Co. v. United States
82 Fed. Cl. 23 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
77 Fed. Cl. 396, 37 Envtl. L. Rep. (Envtl. Law Inst.) 20190, 65 ERC (BNA) 1713, 2007 U.S. Claims LEXIS 220, 2007 WL 2005164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-nuclear-operating-co-v-united-states-uscfc-2007.