Dominion Resources, Inc. v. United States

84 Fed. Cl. 259, 2008 U.S. Claims LEXIS 308
CourtUnited States Court of Federal Claims
DecidedOctober 15, 2008
DocketNos. 04-83C, 04-84C
StatusPublished
Cited by18 cases

This text of 84 Fed. Cl. 259 (Dominion Resources, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dominion Resources, Inc. v. United States, 84 Fed. Cl. 259, 2008 U.S. Claims LEXIS 308 (uscfc 2008).

Opinion

OPINION

BRUGGINK, Judge.

This is one of a number of eases before the court involving contracts for the disposal of commercially-generated spent nuclear fuel (“SNF”) by the United States. The Department of Energy (“DOE”) failed to collect and dispose of spent nuclear fuel beginning January 31, 1998, as directed by the terms of DOE’s Standard Contract. As a result of DOE’s failure, plaintiffs Dominion Resources, Inc.—Dominion Nuclear Connecticut, Inc. (“DNC”) and Dominion Resources, Inc.—Virginia Electric and Power Company (“VEPCO”) respectively claim damages of $52,001,303 and $121,915,726. We refer to the two corporations collectively here as “Dominion” or “plaintiffs.” The Tucker Act, 28 U.S.C. § 1491(a) (2006) provides jurisdiction over plaintiffs’ claim. See PSEG Nuclear, L.L.C. v. United States, 465 F.3d 1343 (Fed. Cir.2006).

Only damages are at issue here because defendant’s liability for partial breach of contract has been established in prior eases. See Maine Yankee Atomic Power Co. v. United States, 225 F.3d 1336, 1337-40 (Fed. Cir.2000) (“Maine Yankee”); N. States Power Co. v. United States, 224 F.3d 1361, 1367 (Fed.Cir.2000). In a prior opinion, Dominion Resources, Inc. v. United States, 77 Fed. Cl. 151 (2007), we granted plaintiffs’ motion to dismiss defendant’s counterclaim and defendant’s claim for an offset against damages.

DNC operates three nuclear reactors at one power plant in Connecticut. These are referred to as Millstone Units 1, 2, and 3. VEPCO operates three nuclear reactors at two power plants in Virginia. These reactors are referred to as North Anna and Surry Units 1 and 2.1

DNC is the current holder of the three Standard Contracts for Millstone Units 1, 2, and 3. Those contracts were originally executed by Northeast Utilities Service Company, an affiliate of the then-owner of the Millstone plants. The Standard Contracts were assigned to DNC in 2001 when Millstone was sold. VEPCO was the original signatory and remains the current holder of the single Standard Contract for North Anna and Sur-ry.

Plaintiffs claim that the government’s failure to begin picking up nuclear waste in January 1998 made it necessary to take interim measures to store this material on site. As of May 2008, when this case went to trial, the government still had not constructed a SNF repository. It remains uncertain when DOE will commence performance of the Standard Contract.

While nuclear utilities may recover mitigation damages caused by DOE’s partial breach, they may not recover forecasted future costs. Ind. Mich. Power Co. v. United States, 422 F.3d 1369, 1375-77 (Fed.Cir. 2005). Accordingly, plaintiffs seek to recover mitigation costs incurred through June 30, 2006. Plaintiffs retain the right to bring subsequent claims for future damages incurred thereafter. See id. at 1378.

[262]*262At the North Anna facility in Virginia, plaintiffs constructed an Independent Spent Fuel Storage Installation (“ISFSI”) with the capacity for three pads. The government does not challenge plaintiffs’ assertion that the installation of the second pad at the North Anna ISFSI was prompted by the breach, but it does assert that the ISFSI and the first pad would have been constructed even if the government had performed.

Plaintiffs also seek reimbursement of expenses associated with modifications to the loading facilities at North Anna. There was already an ISFSI at the Surry facility prior to the breach. Plaintiffs claim that the breach caused them to load additional casks on the second pad at the Surry ISFSI, and to build a third pad and install ten casks there. Defendant questions charges related to the second pad; it does not question costs for the third pad. At Millstone, plaintiffs seek reimbursement for construction of an ISFSI at Unit 2, for an inter-unit transfer study, for additional storage racks at Unit 3, and associated expenses.

Plaintiffs assert the following claims: 1) $71,629,207 to design and construct an ISFSI and procure and load spent fuel dry storage casks onto the ISFSI at North Anna; 2) $50,286,519 to construct a third spent fuel storage pad at the Surry ISFSI and procure and load spent fuel dry storage casks at Surry, from the second cask loaded in 2000 and onward; 3) $1,138,620 to conduct studies for potential inter-unit transfer of spent fuel at Millstone; 4) $12,803,274 to add additional racks to the Millstone Unit 3 spent fuel pool; and 5) $38,059,409 to design and construct an ISFSI and procure and load spent fuel dry storage casks onto the ISFSI at Millstone. The total claim amounts to $174,605,091.

The court conducted a ten-day trial in Washington, D.C., in May 2008. The witnesses in order of appearance were: Tom Alan Brookmire, Supervisor of Nuclear Engineering in Dominion’s Nuclear Spent Fuel Group; Marvin Lee Smith, Project Director in Dominion’s New Plant Licensing Project group; Brian Harold Wakeman, Engineer III in Dominion’s Nuclear Spent Fuel Group; Michael J. Rutkoske, former consultant engineer for Dominion; Carl Whitaker, Senior Nuclear Engineer at Dominion; Wesley Allen Jenkins, Senior Control Specialist in Dominion’s New Plant Licensing Project group; Kerry L. Baseshore, Director of Nuclear Analysis and Fuel at Dominion; Robert L. Morgan, former Director of DOE’s Office of Civilian Radioactive Waste Management (“OCRWM”); David K. Zabransky, nuclear utility specialist in OCRWM’s Office of Waste Management; John D. Dakers, Project Manager at Dominion; Luis L. Nunez, Jr., Project Manager in Nuclear Licensing and Operation Support at Dominion; Lee D. Katz, Controller for Dominion Generation; Thomas Pollog, a DOE engineer in the Office of Waste Management within OCRWM; Michael J. Lawrence, DOE’s former Director of OCRWM; Lee O. Hill, Nuclear Fuel Procurement engineer at Dominion; Dr. Johnathan Neuberger, Ph.D., defendant’s expert in finance and risk management; Loring E. Mills, former executive with Edison Electric Institute (“EEI”); Joseph M. Grillo, defendant’s expert in nuclear power management and operations, reactor operations, and nuclear fuel handling and oversight; R. Larry Johnson, defendant’s expert in financial analysis, cost accounting, auditing, and analysis of economic damages; and Christopher Kouts, DOE’s Director of Office of System Analysis and Strategy Development in OCRWM. Excerpts from the trial testimony of these witnesses is referred to herein as “t£j. »

The court also accepted the parties’ designations of deposition and trial testimony2 from eight witnesses: Lake H. Barrett, DOE’s former Deputy Director of the OCRWM; Alan Brownstein, DOE’s former [263]*263Director of the OCRWM Regulatory Coordination Division; Christopher Kouts; Ronald A. Milner, former Chief Operating Officer of the OCRWM; Robert M. Rosselli, former Director of DOE’s Resource Management Division; Nancy H. Slater, former team leader in the OCRWM Regulatory Coordination Division; Victor W. Trebules, former Director of the Office of Project Control at OCRWM; and Robert L. Morgan.

Subsequent to the trial, the Federal Circuit resolved issues common to SNF cases in Sacramento Municipal Utility District v. United States, 2008 WL 3539880, — Fed. Appx.-(Fed.Cir.2008),

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Energy Northwest v. United States
115 Fed. Cl. 69 (Federal Claims, 2014)
Portland General Electric Co. v. United States
107 Fed. Cl. 633 (Federal Claims, 2012)
Carolina Power & Light Co. v. United States
98 Fed. Cl. 785 (Federal Claims, 2011)
Dominion Resources, Inc. v. United States
641 F.3d 1359 (Federal Circuit, 2011)
Kansas Gas & Electric Co. v. United States
95 Fed. Cl. 257 (Federal Claims, 2010)
Entergy Nuclear Vermont Yankee, LLC v. United States
95 Fed. Cl. 160 (Federal Claims, 2010)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
Arizona Public Service Co. v. United States
93 Fed. Cl. 384 (Federal Claims, 2010)
Southern California Edison Co. v. United States
93 Fed. Cl. 337 (Federal Claims, 2010)
Boston Edison Co. v. United States
93 Fed. Cl. 105 (Federal Claims, 2010)
Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
84 Fed. Cl. 259, 2008 U.S. Claims LEXIS 308, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dominion-resources-inc-v-united-states-uscfc-2008.