Carolina Power & Light Co. v. United States

98 Fed. Cl. 785, 2011 U.S. Claims LEXIS 1097, 2011 WL 2349780
CourtUnited States Court of Federal Claims
DecidedJune 14, 2011
DocketNo. 04-037C
StatusPublished
Cited by8 cases

This text of 98 Fed. Cl. 785 (Carolina Power & Light Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carolina Power & Light Co. v. United States, 98 Fed. Cl. 785, 2011 U.S. Claims LEXIS 1097, 2011 WL 2349780 (uscfc 2011).

Opinion

OPINION AND ORDER

WHEELER, Judge.

This case is before the Court on remand from the United States Court of Appeals for the Federal Circuit. See Carolina Power & Light Co. v. United States, 573 F.3d 1271 (Fed.Cir.2009). Plaintiffs Carolina Power & Light Company and Florida Power Corporation (collectively “Progress Energy”) own five nuclear reactors at four power plants in North Carolina, South Carolina, and Florida. The power plants are known as Harris, Brunswick, Robinson, and Crystal River. Progress Energy incurred substantial costs at these plants because the Department of Energy (DOE) failed to collect and dispose of spent nuclear fuel beginning January 31, 1998 as required under DOE’s Standard Contract. Following a November 2007 trial, this Court awarded Progress Energy $82,782,289 for the costs of mitigating DOE’s partial breach. Carolina Power & Light Co. v. United States, 82 Fed.Cl. 23 (2008), [787]*787amended by 82 Fed.Cl. 317 (2008). Defendant appealed this ruling, contending that the Court had not used the correct spent fuel acceptance rate in calculating Progress Energy’s recovery. Although Defendant partially prevailed in having the Federal Circuit clarify the proper acceptance rate to be employed, the result now is that Progress Energy is entitled to a greater recovery than if Defendant had not appealed.

The Standard Contract, executed in 1983, did not contain an express acceptance rate for DOE’s expected collection of spent fuel fifteen years later in 1998. See Carolina Power, 82 Fed.Cl. at 37. At trial, Progress Energy used a 2004 DOE Annual Capacity Report (ACR) to calculate damages. Id. at 43. However, the Federal Circuit held that DOE’s 1987 ACR should be used instead for this purpose. Carolina Power, 573 F.3d at 1277. The 1987 and 2004 ACRs are quite similar in ultimately reaching an industry acceptance rate of 3,000 metric tons of uranium (MTUs) per year, but the 1987 ACR has a more rapid ramp-up rate in the first two years than the 2004 ACR. Thereafter, the 1987 ACR does not reach 3,000 MTUs per year- until the eleventh year of the program, while the 2004 ACR reaches 3,000 MTUs per year in the fifth year.

On remand, Progress Energy has revised its damages model to conform to the 1987 ACR as the Federal Circuit mandated. Essentially, the 1987 ACR ramp-up rate in the early years of DOE’s performance yields a higher claim recovery because DOE would have collected more of Progress Energy’s spent fuel sooner, and thus more of the costs are DOE’s responsibility. Progress Energy also assumed in its revised model that spent fuel could be shared among its plants as authorized by the Standard Contract, and that in using DOE allocations, it would prioritize Robinson spent fuel stored at Harris over Robinson spent fuel stored at Brunswick. Based upon these adjustments, Progress Energy has added $9,168,312 to its claim, bringing the total to $91,957,601. The additional $9,168,312 consists of: (a) $8,038,737 for 27 additional spent fuel shipments between plants that could have been avoided under the 1987 ACR rate; and (b) $1,129,575 associated with the re-rack of the Harris Plant B spent fuel pool that would not have been necessary under the 1987 ACR rate. Of this amount, Defendant concedes liability for $4,168,234, but contests the remainder.

Defendant’s objections to the revised claim can be summarized in two categories. First, Defendant asserts that $5,000,078 of Progress Energy’s costs are not attributable to the 1987 ACR acceptance rate differences, but to other unrelated changes to Progress Energy’s causation model. Second, Defendant states that the new model is flawed because it does not account for Progress Energy’s management practice of maintaining “prudent operating reserve” for the storage of spent fuel.

The Court conducted a one-day remand trial on February 16, 2011, and received post-trial briefs from the parties on March 18, 2011 and reply briefs on April 1, 2011. Based upon the new evidence presented, the Court concludes that Progress Energy is entitled to additional damages of $9,168,312. Defendant’s objections to Progress Energy’s additional damages, discussed below, are without merit. Progress Energy’s total recovery therefore is $91,957,601.

Background

The following information from the Court’s first decision and subsequent history is relevant to the damages issues presented on remand. A more complete analysis of the entire case is available by referring directly to that decision. Carolina Power, 82 Fed.Cl. 23.

A. The Standard Contract

DOE’s Standard Contract resulted from Congress’s passage of the Nuclear Waste Policy Act of 1982 (NWPA), Pub.L. No. 97-425, 96 Stat. 2201 (codified at 42 U.S.C. §§ 10101-10270). Carolina Power, 82 Fed.Cl. at 28-29. In the NWPA, Congress directed the Secretary of DOE to “enter into contracts with any person who generates or holds title to high-level radioactive waste, or spent nuclear fuel, of domestic origin for the acceptance of title, subsequent transportation, and disposal of such waste or spent nuclear fuel.” § 10222(a)(1); Carolina Power, [788]*78882 Fed.Cl. at 28-29. DOE published the proposed Standard Contract in the Federal Register on February 4, 1983. Id. at 29. Nuclear plant owners and operators had no choice but to enter into the Standard Contract with DOE. Id.

The Standard Contract required DOE to accept title to all spent nuclear fuel beginning January 31, 1998. Id. The Standard Contract also required DOE to issue an ACR, beginning not later than July 1, 1987. Id. The ACR would project DOE’s annual spent fuel receiving capacity for the ten years “following the projected commencement of operation of the initial DOE facility.” Id. DOE was required to issue an annual priority ranking (APR) beginning April 1, 1991, to identify the order in which spent fuel and high level waste would be collected, with the older fuel or waste being collected first. Id. The utilities were then required to prepare a delivery commitment schedule which identified the spent nuclear fuel that the utility would deliver to DOE 63 months thereafter. Id.

By 1987, DOE knew that it would not have a functioning permanent repository to begin accepting spent fuel on January 31, 1998. Id. at 32. DOE submitted a proposal to Congress to build a Federal Interim Storage or Monitored Retrievable Storage (MRS) facility. Id. Congress amended the NWPA to allow the new storage facility, but limited the MRS capacity to 10,000 MTUs and stated that MRS construction could not begin until a license was issued for construction of a permanent facility. Id. at 32-33; 42 U.S.C. §§ 10162(b), 10168(d)(1), (3). In June 1987, DOE published its first statutorily required ACR. Carolina Power, 82 Fed.Cl. at 33. The 1987 ACR adopted the following industry-wide acceptance schedule: 1,200 MTUs for 1998-2002, 2,000 MTUs in 2003, 2,650 MTUs for 2004-2007, and 3,000 MTUs annually thereafter. Id. In 1991, DOE published its first official APR setting the order of fuel acceptance at individual nuclear plants with an objective of collecting the oldest fuel first. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carolina Power & Light Co. v. United States
115 Fed. Cl. 57 (Federal Claims, 2014)
Frank Gaylord v. United States
112 Fed. Cl. 539 (Federal Claims, 2013)
St. John v. Peterson
2013 SD 67 (South Dakota Supreme Court, 2013)
Otay Mesa Property, L.P. v. United States
110 Fed. Cl. 732 (Federal Claims, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
98 Fed. Cl. 785, 2011 U.S. Claims LEXIS 1097, 2011 WL 2349780, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carolina-power-light-co-v-united-states-uscfc-2011.