Carolina Power & Light Co. v. United States

573 F.3d 1271, 2009 U.S. App. LEXIS 16060
CourtCourt of Appeals for the Federal Circuit
DecidedJuly 21, 2009
Docket2008-5108
StatusPublished
Cited by52 cases

This text of 573 F.3d 1271 (Carolina Power & Light Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carolina Power & Light Co. v. United States, 573 F.3d 1271, 2009 U.S. App. LEXIS 16060 (Fed. Cir. 2009).

Opinion

RADER, Circuit Judge.

The United States Court of Federal Claims entered judgment in the amount of $82,789,289 against the United States for the Department of Energy’s (DOE’s) partial breach of its contract with certain nuclear utilities. Carolina Power & Light Co. v. United States, 82 Fed.Cl. 23 (2008) (CP&L I). Because the trial court based its award on a damages model expressly rejected by this court in Pacific Gas & Electric Co. v. United States, 536 F.3d 1282 (Fed.Cir.2008), this court affirms in part and vacates and remands in part.

I.

In this case as in others, the record shows that the United States partially breached its contracts with domestic nuclear utilities to store high-level nuclear waste (HLW) and spent nuclear fuel (SNF). A detailed factual background appears in several other opinions of this court. See, e.g., Yankee Atomic Elec. Co. v. United States, 536 F.3d 1268 (Fed.Cir.2008); Me. Yankee Atomic Power Co. v. United States, 225 F.3d 1336 (Fed.Cir.2000).

The plaintiffs in this case are Carolina Power & Light Company (CP & L) and Florida Power Corporation (FPC) (collectively, following the convention of the trial court, Progress Energy). Progress Energy operates five nuclear reactors at four power stations in North Carolina, South Carolina, and Florida. The power plants are known as Harris, Brunswick, Robinson, and Crystal River.

Under the Nuclear Waste Policy Act of 1982 (NWPA), Pub.L. No. 97-425, 96 Stat. 2201 (codified at 42 U.S.C. §§ 10101-10270), Progress Energy entered into a “Standard Contract” with DOE. Under that contract, DOE obligated itself to take title to and dispose of Progress Energy’s SNF and HLW, starting no later than January 31, 1998. As consideration for this performance, the contract required Progress Energy to pay one-time and recurring quarterly fees. Through December 31, 2005, Progress Energy has paid some $661 million in fees to DOE under the Standard Contract.

DOE partially breached its contractual obligations by failing to perform waste acceptance in accordance with the Standard Contract. See Ind. Mich. Power Co. v. United States, 422 F.3d 1369, 1376-77 (Fed.Cir.2005); Me. Yankee, 225 F.3d at 1343. The parties in this litigation do not dispute this conclusion. Instead, they dispute the amount of mitigation damages owed to Progress Energy for that breach. Progress Energy has incurred substantial mitigation costs in storing SNF that otherwise would have been stored by DOE under the contract.

The Standard Contract did not articulate a firm rate at which DOE would accept and dispose of SNF and HLW. Instead, the Standard Contract required DOE to issue annual capacity reports (ACRs), beginning no later than July 1, 1987, setting forth projected yearly receiving capacity for government nuclear waste storage facilities. Additionally, the Standard Contract required DOE to issue annual acceptance priority rankings (APRs) to identify the order in which SNF and HLW would be collected from various parties, based on a first-in, first-out queue model. In response to these APRs, the utilities submitted a delivery commitment schedule (DCS) to identify the spent fuel ready for delivery beginning sixty-three months after the DCS submission. This court has referred to this iterative process as the acceptance capacity schedule or ACS process. See Pac. Gas, 536 F.3d at 1286.

*1274 During a nine-day trial, the parties in this case presented evidence regarding DOE’s fuel acceptance rate obligations under the Standard Contract and the actual expenses borne by Progress Energy as a result of the government’s breach. The trial court, while recognizing that the Standard Contract lacked a firm rate of fuel acceptance, interpreted the Standard Contract as including obligations “that would achieve the goals of the NWPA.” CP&L I, 82 Fed.Cl. at 37. Focusing on the purported motivation behind Congress’s enactment of the NWPA, the court stated:

It is apparent to the Court that the NWPA’s purpose was to establish one or more central repositories for the storage of spent nuclear fuel so that nuclear utilities would not need to provide for additional spent fuel storage at their reactors....
The NWPA mandated that DOE’s mission plan contain an estimate of “the total repository capacity required to safely accommodate the disposal of all high-level radioactive waste and spent nuclear fuel expected to be generated through December 30, 2020 .... ” § 10221(a)(9). All of DOE’s early mission plans, and related statements and actions, reflect an intent to achieve this objective....

Id. at 37.

Based on this standard, the trial court adopted plaintiffs’ argument that a rate of 3000 metric tons of uranium (MTUs) was a reasonable measure of DOE’s performance absent the breach. The trial court credited a model prepared by Progress Energy based on waste allocations under a 3000 MTU rate to determine what steps the utilities would have taken to store SNF had DOE begun accepting fuel in 1998. The trial court derived this model from the rates set forth in the 2004 version of DOE’s ACR, which contemplated spent fuel acceptance at a permanent repository beginning in 2010. The trial court rejected the government’s damages analysis, which was based upon a lower acceptance rate of 900 MTUs dictated by the 1991 ACS. Under the United States’s theory of damages, the 1991 ACS would have entitled Progress Energy to recover $47,755,006. The trial court also rejected the government’s arguments that certain overhead costs in the amount of $4,231,710 were not recoverable because they were fixed costs not incremental to the breach.

The government now appeals from the trial court’s judgment dated June 19, 2008, awarding plaintiffs the amount of $82,789,289. Notably, on August 7, 2008, this court issued a decision in Pacific Gas identifying the appropriate SNF acceptance rate as that identified in the June 1987 ACS — a rate advocated by neither party in the instant case. This court has jurisdiction under 28 U.S.C. § 1295(a)(3).

II.

This court must vacate the trial court’s judgment because it is premised upon a damages model this court expressly rejected in Pacific Gas. In Pacific Gas, this court identified the 1987 ACS as “the most reasonable measure of the contractual acceptance rate.” 536 F.3d at 1292.

In Pacific Gas, this court reviewed the Court of Federal Claims’s selection of the 1991 ACS as the proper acceptance rate for measuring damages. This court noted with approval the trial court’s decision to rely on the ACS process, rather than an implied specific acceptance rate of 3000 MTU per year. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Entergy Gulf States, Inc. v. United States
125 Fed. Cl. 678 (Federal Claims, 2016)
System Fuels, Inc. v. United States
818 F.3d 1302 (Federal Circuit, 2016)
Dms Imaging, Inc. v. United States
123 Fed. Cl. 645 (Federal Claims, 2015)
Dairyland Power Cooperative v. United States
123 Fed. Cl. 220 (Federal Claims, 2015)
System Fuels, Inc. v. United States
120 Fed. Cl. 635 (Federal Claims, 2015)
Sacramento Municipal Utility District v. United States
120 Fed. Cl. 270 (Federal Claims, 2015)
Alabama Power Company v. United States
119 Fed. Cl. 615 (Federal Claims, 2014)
Chevron U.S.A., Inc. v. United States
116 Fed. Cl. 202 (Federal Claims, 2014)
Energy Northwest v. United States
115 Fed. Cl. 69 (Federal Claims, 2014)
Yankee Atomic Electric Company v. United States
113 Fed. Cl. 323 (Federal Claims, 2013)
SUFI Network Services, Inc. v. United States
108 Fed. Cl. 287 (Federal Claims, 2012)
BPLW Architects & Engineers, Inc. v. United States
106 Fed. Cl. 521 (Federal Claims, 2012)
Kansas Gas and Electric Co. v. United States
685 F.3d 1361 (Federal Circuit, 2012)
Yankee Atomic Electric Co. v. United States
679 F.3d 1354 (Federal Circuit, 2012)
Boston Edison Co. v. United States
658 F.3d 1361 (Federal Circuit, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
573 F.3d 1271, 2009 U.S. App. LEXIS 16060, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carolina-power-light-co-v-united-states-cafc-2009.