BPLW Architects & Engineers, Inc. v. United States

106 Fed. Cl. 521, 2012 U.S. Claims LEXIS 1071, 2012 WL 3877616
CourtUnited States Court of Federal Claims
DecidedSeptember 7, 2012
DocketNo. 09-672C
StatusPublished
Cited by7 cases

This text of 106 Fed. Cl. 521 (BPLW Architects & Engineers, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BPLW Architects & Engineers, Inc. v. United States, 106 Fed. Cl. 521, 2012 U.S. Claims LEXIS 1071, 2012 WL 3877616 (uscfc 2012).

Opinion

OPINION AND ORDER

WHEELER, Judge.

The Government contracted with BPLW Architects & Engineers, Inc. to provide architectural and engineering services for the construction of two student dormitory buildings at Lackland Air Force Base in San Antonio, Texas. Shortly after the general contractor, CF Jordan, finished construction of the dorms, below grade piping problems occurred, resulting in the flooding of several dorm units. The Government contracted with CF Jordan to repair some of the broken pipes and with another contractor, Tepa EC, LLC to replace the entire subsurface piping system and to remedy the inadequate grading around the dorms.

The Government claims that BPLW provided a negligent underfloor piping design, as the design failed to accommodate the “highly expansive” soils in the San Antonio area. In addition, the Government claims that BPLW provided a negligent civil site grading design, as it did not provide for the requisite five percent slope away from the dorms. The Government contends that these negligent designs caused the piping problems at the dorms and led it to incur substantial expense to repair broken pipes, replace the underfloor piping system, and remedy the site grading. For its damages, the Government claims a total of $6,755,826.72 from BPLW.

The Court has jurisdiction of this matter under the Contract Disputes Act, 41 U.S.C. § 7104(b) (2006) (“CDA”), on appeal from the contracting officer’s November 25, 2008 final decision wherein the Government claimed more than $7.6 million in damages from BPLW for negligent design. BPLW timely filed its petition in this Court on October 7, 2009. The Court conducted trial in Fort Worth, Texas from February 27 through March 7, 2012, and heard the testimony of eighteen witnesses, eight of whom were experts. The Government presented its ease first because it had the burden of proof to substantiate its claim. Following trial, the parties submitted post-trial briefs on May 17, 2012, and post-trial response briefs on June [525]*52518, 2012. The Court heard closing arguments on July 16, 2012 in Washington, DC.

As set forth below, the Court finds that BPLW did indeed provide negligent underfloor piping and civil site grading designs, as both failed to comply with the contract requirements and the applicable standard of care. The Court also finds, however, that the Government failed to establish that these negligent designs caused either the initial pipe breakage ultimately repaired by CF Jordan or the inadequate site grading remedied by Tepa. In addition, the Court finds that irrespective of causation, the Government failed to prove the reasonableness of the costs it paid to Tepa to replace the underfloor piping system. The Court therefore concludes that BPLW is liable to the Government for $197,596.47 in costs the Government incurred to implement certain modifications to BPLW’s designs, but that the Government is not entitled to the other damages it claims.

Factual Background1

I. The Contract — December 2002/January 2003

The United States Air Force hired the United States Army Corps of Engineers, Fort Worth District (“the Corps”) as the contracting agency to procure the design and construction of student dormitories on Lack-land Air Foree Base (“AFB”) in San Antonio, Texas. Stip. ¶ l.2 Plaintiff, BPLW Architects & Engineers, Inc. (“BPLW”) is an architectural and engineering firm headquartered in Albuquerque, New Mexico. Id. ¶ 2; Compl. ¶ 2. On or about December 17, 2001, BPLW and the Corps entered into an “Architect-Engineer Contract,” No. DACA 63-02-C-001 (“the Contract”), under which BPLW agreed to design student dormitory “FY03” at Laek-land AFB. Stip. ¶ 3; DX 3. On or about January 14, 2003, BPLW entered into a modification of the Contract to design student dormitory “FY04,” which is adjacent to the FY03 dormitory at Lackland AFB. Stip. ¶ 4. After modifications, the Contract amounted to $1,869,252.80. Id.

BPLW provided structural engineering and mechanical, electrical, and plumbing (“MEP”) engineering services as part of its Contract with the Corps. Stip. ¶ 7. The Contract’s Statement of Work specified that the Government would supply BPLW with “a report to define soil conditions at the site and paving and foundation requirements as may be applicable.” Id. ¶ 6; DX 12 at 12. In line with this provision, the Corps provided the geotechnical engineering services for the project and prepared the foundation and pavement design analyses (“the soils reports”), dated May 2002 and July 2003, for the FY03 and FY04 dorms, respectively. Stip. ¶ 8; see PX 5; PX 6. The two soils reports are the same in all substantive respects. Compl. ¶ 13; see PX 5; PX 6. BPLW was obligated under the Contract to follow the soils reports in preparing the structural and MEP designs 3 for the dorms. Stip. ¶¶ 11,14.

A The Soils Reports

Mark Black, a geotechnical engineer and assistant chief of engineering in the Corps’ Fort Worth District, authored the FY03 soils report, Tr. 56, 59, 61 (Black), and Ken McCleskey, acting chief of the Corps’ geo-technical section, authored the FY04 soils report, Tr. 583-84, 589 (McCleskey). Mr. Black and Mr. McCleskey prepared the soils reports based upon their respective subsurface investigations and subsequent laborato[526]*526ry testing of samples obtained from the dorm sites. See Tr. 69-72 (Black), 593 (MeCles-key). The principal finding of both Mr. Black and Mr. McCleskey was that the soil at the site of the dorms had a very high “shrink swell potential,” see Stip. ¶ 17; Tr. 74 (Black), 594-95 (McCleskey), or in the words of Mr. Black, that the soil was “extremely highly expansive,” Tr. 74. The soils reports reflect this finding, noting that “[o]nce built upon these soils can experience significant volumetric changes when their in situ moisture environment is altered.” PX 5 at 8; PX 6 at 9. Specifically, both soils reports state that “the expansive soils have a heave potential” of more than nine inches. PX 5 at 8; PX 6 at 8.

In light of the expansive soil, the soils reports direct that “the presence of a highly active subgrade must be accounted for in the design of the Dormitory foundation and floor slab systems to prevent both functional and aesthetic problems within the completed facility.” PX 5 at 9; PX 6 at 9. To account for the highly active subgrade, the soils reports specifically recommend a foundation system consisting of a drilled and underreamed pier foundation with a 12-inch void space under the floor slab. PX 5 at 9-10; PX 6 at 9-10. The drilled and underreamed pier foundation prevents the building from moving, regardless of soil heave. See Tr. 574 (Focht). As the Government’s expert, John Focht III,4 explained:

All of the structural loads come down to a series of drilled concrete piers that are embedded at about 35 feet, and so the load carries down through the portion of the soil that’s shrinking and swelling, and it is resting down in some materials that don’t move. As a result the structure is not moving, so as the soil goes up and down the building is largely staying in place.

Id. The 12-inch void space under the floor slab prevents the soil from coming into contact with, and pushing up on, the building floor whenever the soil expands.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
106 Fed. Cl. 521, 2012 U.S. Claims LEXIS 1071, 2012 WL 3877616, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bplw-architects-engineers-inc-v-united-states-uscfc-2012.