C.H. Guernsey & Co. v. United States

65 Fed. Cl. 582, 2005 U.S. Claims LEXIS 125, 2005 WL 1023510
CourtUnited States Court of Federal Claims
DecidedApril 29, 2005
DocketNo. 99-294 C
StatusPublished
Cited by4 cases

This text of 65 Fed. Cl. 582 (C.H. Guernsey & Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C.H. Guernsey & Co. v. United States, 65 Fed. Cl. 582, 2005 U.S. Claims LEXIS 125, 2005 WL 1023510 (uscfc 2005).

Opinion

MEMORANDUM OPINION AND ORDER

BRADEN, Judge.

A subcontractor bid on an important Army training facility without reviewing the underlying Design Plans and Specifications. That act caused a substantial delay in the construction of the project that already was behind schedule because of inclement weather conditions. Rather than explaining the situation to the Army Generals waiting for the facility to be completed and face their displeasure, the United States Army Corps of Engineers decided to complete the project on time, without regard to cost, and then look for a scapegoat.

FACTUAL BACKGROUND1

A. Design Of The Close Combat Tactical Training Facility, Fort Knox, Kentucky.

On June 6, 1994, the United States Army Corps of Engineers (“Army Corps”) awarded C.H. Guernsey & Co. (“Guernsey”), an architectural and engineering firm with its principal place of business in Oklahoma City, Oklahoma, Contract No. DACA27-94-C-0060 (“Contract”) for the design of a Close Combat Tactical Training Facility (“CCTTF”), to [584]*584be located in Fort Knox, Kentucky. See Jt. Stip. f l.2 Under the terms of Contract No. DACA27-94-C-0060, Guernsey was to provide the Army Corps design services, plans, and specifications in two phases: Con-cepVPreliminary Design, for a base amount of $115,366.00; and a Final Design Phase Option for $184,118.00. See, e.g., JX 1 at B-1; see also TR at 127-28. Contract No. DACA27-94-C-0060 also provided that Guernsey would “design and detail a complete and usable facility[.]” See JX 1 It C.l. at 3. Section 52.0236-23 therein sets forth the following specific responsibilities of the architect-engineer contractor:

(a) [Guernsey] shall be responsible for the professional quality, technical accuracy, and the coordination of all designs, drawings, specifications, and other services furnished by [Guernsey] under this contract. [Guernsey] shall, without additional compensation, correct or revise any errors or deficiencies in its designs, drawings, specifications, and other services.
(b) Neither the Government’s review, approval or acceptance of, nor payment for, the services required under this contract shall be construed to operate as a waiver of any rights under this contract or of any cause of action arising out of the performance of this contract, and [Guernsey] shall be and remain liable to the Government in accordance with applicable law for all damages to the Government caused by [Guemsey]’s negligent performance of any of the services furnished under this contract.

JX 1 at F-52 (“Architect-Engineer clause”). On June 6, 1994, Guernsey received a Notice to Proceed. See JX 24.

On October 10, 1994, Guernsey entered into a Consulting Services Contract with Fink, Roberts, and Petrie, Inc. (“Fink”) to prepare studies and/or architectural and engineering design services, as required by Guernsey. See JX 50. On April 17, 1995, Guernsey submitted a 30% Design Submittal to the Army Corps. See JX 2; JX 51; see also TR at 363-65, 378. In July 1995, Guernsey submitted a 60% Design Submittal, but did not address in the Design Analysis Section specific lateral deflection values. See JX 3 at D.2 (“The supplier will also be directed to limit the lateral deflections to values compatible with the exterior cladding system for both wind and seismic loads. The specific values have not yet been determined.”). The Calculations Section of the 60% Design Sub-mittal addressed Deformation Compatibility as follows:

DEFORMATION CAPABILITY BRICK/BLOCK & MOMENT FRAMES 3Rw/8 x A OF FRAMES

[[Image here]]

See JX 3 at C-9.

On July 6,1995, Guernsey provided a Construction Schedule to the Army Corps that estimated 256 days to construct the CCTTF from Notice to Proceed through Project Completion, based on a normal 8 hours a day work week. See JX 57 at 7.

On August 18, 1995, Guernsey’s Project Manager sent a Confirmation Notice No. 5 including Guernsey’s responses to Army Corps’ comments on the 60% Design Submit-tal. See JX 4. Confirmation Notice No. 5 also responded to an August 2,1995 directive from Mr. Russell Boyd, a member of the Army Corps Technical Services Branch, [585]*585Quality Assurance that directed Guernsey as follows:

Lateral deflection of the Pre-engineered structure shall be limited to L/600 unless the masonry is isolated from the structure. Deflection is governed by the limits of the masonry.

See JX 4 It 6 at 2 (emphasis added); see also TR at 62-63, 91.

Boyd testified that in making this directive he relied on a July 2, 1992 Army Corps Engineer Technical Letter 1110-3-439 for Engineering and Design, Masonry Veneer/Steel Stud Walls (Nonbearing Construction) lifting a moratorium that the Army Corps had imposed on the use of masonry veneer and steel stud systems on military construction projects, because of a continuing problem with brick veneer cracking resulting in rust damage to fasteners on the connections and the failure of those connections. See PX 53 It 1; see also TR at 105-06. The purpose of the Engineer Technical Letter was to specify what the Army Corps required to solve that problem, i.e., “the limitation of the deflection for the brick.” See TR at 120. The Technical Letter provided:

Information contained in this letter lifts the moratorium on the nonbearing wall systems.
******
a. Wall construction. A well defined industry standard is not available for the design of masonry veneer and steel stud systems!.]
b. Allowable deflection. Industry standards for an allowable service deflection criteria varies widely from L/1403 for tall slender reinforced walls, L/360 for steel studs as recommended by the Metal Lath/Steel Framing Association and L/600 or L/720 for steel studs as recommended by the Brick Institute of America, “L” being the height of the wall in inches.

PX 53 H1f 1, 3a-b, see also TR at 103-04.4

In addition, Boyd relied on February 1987 Technical Notes of the Brick Institute of America (“Brick Institute”) that recommended:

Stiffness Considerations____ Many design tables are based on a stud deflection of L/360. Using this stiffness of backup represented by an L/360 deflection may permit more deflection than the veneer is able to tolerate without cracking.

******

Stiffness Requirements. Based on observations, experience and judgment, the Brick Institute of America suggests that in order to obtain the stiffness necessary for performance, the maximum deflection that should be permitted for the steel stud backup, when considered alone at full lateral design load, be L/600 to L/720.

PX 54 at 3-4; see also TR at 109-10, 119-20.

Guernsey’s Plans and Specifications, however, did not include steel stud walls. See TR at 119. Nevertheless, Guernsey’s “action in response” to Boyd’s directive was “[w]ill comply.” See JX 4 at Conf. No. 5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BPLW Architects & Engineers, Inc. v. United States
106 Fed. Cl. 521 (Federal Claims, 2012)
Pacific Gas & Electric Co. v. United States
73 Fed. Cl. 333 (Federal Claims, 2006)
Ulysses, Inc. v. United States
66 Fed. Cl. 161 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
65 Fed. Cl. 582, 2005 U.S. Claims LEXIS 125, 2005 WL 1023510, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ch-guernsey-co-v-united-states-uscfc-2005.