Johnson Lasky Kindelin Architects, Inc v. United States

CourtUnited States Court of Federal Claims
DecidedDecember 23, 2020
Docket19-1419
StatusPublished

This text of Johnson Lasky Kindelin Architects, Inc v. United States (Johnson Lasky Kindelin Architects, Inc v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson Lasky Kindelin Architects, Inc v. United States, (uscfc 2020).

Opinion

In the United States Court of Federal Claims No. 19-1419C

(Filed: December 23, 2020)

) JOHNSON LASKY KINDELIN ) ARCHITECTS, INC., ) ) Contract Disputes Act; contract damages; Plaintiff, ) tort damages; sounding in tort; joint and ) several liability; jurisdiction; RCFC v. ) 12(h)(3); government claim; government ) counterclaim; contracting officer’s final ) decision; RCFC 14; RCFC 19 THE UNITED STATES, ) ) Defendant. )

Lucas T. Hanback, Rogers Joseph O’Donnell, P.C., Washington, DC, for plaintiff. With him on the briefs were Stephen L. Bacon and Matthew Ligda.

P. Davis Oliver, United States Department of Justice, Civil Division, Washington, DC, for defendant. With him on the briefs were Joseph H. Hunt, Assistant Attorney General, Civil Division, Robert E. Kirschman, Jr., Director, and Elizabeth M. Hosford, Assistant Director, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC.

ORDER AND OPINION

I. Introduction

This case presents what appears to be a jurisdictional issue of first impression: whether this Court has jurisdiction – pursuant to the Tucker Act, 28 U.S.C. § 1491(a), and the Contract Disputes Act (“CDA”), 41 U.S.C. §§ 7101–7109 – to decide a case predicated upon a government claim contained in a contracting officer’s final decision finding that two, unrelated contractors are jointly and severally liable for the same injury and sum certain arising from independent breaches of their respective contracts.

The Court answers that question in the negative and, accordingly, dismisses this case for lack of jurisdiction. II. FACTUAL BACKGROUND 1

A. The Parties and The Contracts At Issue

Plaintiff and Counterclaim-Defendant, Johnson Lasky Kindelin Architects, Inc. (“JLK”), is an Illinois corporation that provides architectural and engineering services. ECF No. 1 (“Compl.”) ¶ 1. Defendant and Counterclaim-Plaintiff is the United States of America, acting by and through the General Services Administration (“GSA”). ECF No. 12 (“Answer” or “Counterclaim”) ¶ 2. On or about December 23, 2010, GSA awarded JLK a contract to provide architectural and engineering services. Compl. ¶ 4; see ECF No. 1-1 (“Ex. 1”); Answer ¶ 4.

Pursuant to that contract, GSA issued Task Order GS-P-05-14-FB-0103 (“the JLK Task Order”) to JLK to provide professional design services as the architect-engineer supporting the relocation of existing National Labor Relations Board (“NLRB”) office space in the Dirksen building in Chicago, Illinois (“the Courthouse”). Counterclaim ¶ 4. GSA separately contracted with Master Design Build, Inc. (“MDB”) – via Delivery Order GS-P-05-14-FB-0059 (“the MDB Delivery Order”) – to provide the necessary construction services for the relocation of the NLRB office space. Id. ¶ 5.

Among other items, JLK’s proposed “work include[d] locating and specifying infrastructure (conduit and back boxes) for the telecommunications and security systems” as well as “[t]he design of a supplemental air conditioning unit[.]” Ex. 1 at 133, 135. Prior to the construction, “the 8th floor of the Dirksen building had an existing glycol water system used to provide coolant to the elevators and to supplemental cooling units that are typically utilized in tenant server rooms.” Compl. ¶ 15. As part of the NLRB build out, a new computer room air conditioning unit (“CRU”) had to be added for a new server room. Id. at ¶ 16. That, in turn, required “[n]ew supply lines . . . to provide glycol water to the CRU.” Id. at ¶ 17. To ensure “adequate flow of coolant to the CRU[,] a small inline pump was added to the supply line prior to the CRU.” Id. at ¶ 18. JLK was responsible for designing the new air conditioning unit, while MDB was tasked with the installation of the new cooling system. Id. at ¶ 8.

1 This section does not constitute factual findings by the Court. Rather, this Court assumes, as it must, that the factual allegations contained in the government’s Counterclaim are true for the purposes of resolving the Plaintiff’s pending motion to dismiss. See Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (“[F]or the purposes of a motion to dismiss we must take all of the factual allegations in the complaint as true.” (citing Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555 (2007))). The Court also has referenced facts from the Plaintiff’s Complaint for context and clarity, and has considered “matters incorporated by reference or integral to the claim, items subject to judicial notice, [and] matters of public record.” Dimare Fresh, Inc. v. United States, 808 F.3d 1301, 1306 (Fed. Cir. 2015) (quoting 5B Charles Alan Wright & Arthur R. Miller, Federal Practice and Procedure § 1357 (3d ed. 2004)); see also RCFC 9(k); ECF No. 13 (“Pl. Mot.”) at 3 n.1.

-2- B. Damage To The Government’s Courthouse

On March 3, 2016, MDB attempted to investigate what sounded like a “hammering noise” emanating from the cooling system that had been installed in the Courthouse. Counterclaim ¶ 17. MDB sent a technician from the CRU’s manufacturer to the Courthouse to investigate the noise. See id.; Compl. ¶ 24. GSA, however, did not permit the service technician to access the site, because the technician allegedly did not possess the contractually required security clearance. Counterclaim ¶ 17.

On March 15, 2016, a condenser fluid pipe in the newly installed cooling system malfunctioned and caused extensive damage to parts of the Courthouse, including parts of the NLRB space, as well as portions of the United States Bankruptcy Court on the sixth and seventh floors. Counterclaim ¶¶ 6–7.

Following the leak, GSA retained Bailey Edward, an independent architecture and engineering consulting firm, to conduct a forensic investigation to ascertain the cause of the condenser fluid piping system failure and to issue a report. See ECF No. 1-3 (“Bailey Edward Study”); see also Compl. ¶14. The Bailey Edward Study concluded, among other things, that

[t]he design called for a centrifugal wet rotor pump without any provision to turn the pump off when flow was not needed . . . When the motorized control valve is closed and the pump remains energized, the pump is operating under a no flow condition which results in premature pump failure. . . . Operating the pump in a no flow condition also causes the water within the impeller housing to heat up and could have resulted in failure of the downstream gasket. In this particular instance the no flow condition from the closed control valve resulted in vibration that was transmitted to the connected piping and additionally created objectionable noise.

Bailey Edward Study at 6; see Counterclaim ¶ 12. The Bailey Edward Study also found that JLK’s design documents identified spring isolation hangers that MDB had not installed. Bailey Edward Study at 6; Counterclaim ¶ 16. Specifically, Bailey Edward concluded that

[a]lthough the design identified that spring hangers were to be installed at the pump, none were provided. Per the GSA P100 document all pumps should be provided with flexible connections on the inlet and discharge. However, the installation of such appurtenances was not identified in the contract documents, and flexible connections were not provided by the contractor. The installation of these devices

-3- would have reduced the vibration transmitted from the pump to the piping and increased the time to failure.

Bailey Edward Study at 6; Counterclaim ¶ 16.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ex Parte McCardle
74 U.S. 506 (Supreme Court, 1869)
First National Bank in St. Louis v. Missouri
263 U.S. 640 (Supreme Court, 1924)
KVOS, Inc. v. Associated Press
299 U.S. 269 (Supreme Court, 1936)
Edmonds v. Compagnie Generale Transatlantique
443 U.S. 256 (Supreme Court, 1979)
McDermott, Inc. v. AmClyde
511 U.S. 202 (Supreme Court, 1994)
Kokkonen v. Guardian Life Insurance Co. of America
511 U.S. 375 (Supreme Court, 1994)
Rumsfeld v. Padilla
542 U.S. 426 (Supreme Court, 2004)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
United States v. Hayes
555 U.S. 415 (Supreme Court, 2009)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
United States v. Vargas, Michael
415 F.3d 23 (D.C. Circuit, 2004)
Tilcon Capaldi, Inc. v. Feldman
249 F.3d 54 (First Circuit, 2001)
Henderson v. Shinseki
131 S. Ct. 1197 (Supreme Court, 2011)
Hartford Fire Insurance v. United States
544 F.3d 1289 (Federal Circuit, 2008)
Rick's Mishroom Service, Inc. v. United States
521 F.3d 1338 (Federal Circuit, 2008)
Renda Marine, Inc. v. United States
509 F.3d 1372 (Federal Circuit, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Johnson Lasky Kindelin Architects, Inc v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-lasky-kindelin-architects-inc-v-united-states-uscfc-2020.