Johnson Lasky Kindelin Architects, Inc v. United States

CourtUnited States Court of Federal Claims
DecidedJanuary 29, 2021
Docket19-1520
StatusPublished

This text of Johnson Lasky Kindelin Architects, Inc v. United States (Johnson Lasky Kindelin Architects, Inc v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson Lasky Kindelin Architects, Inc v. United States, (uscfc 2021).

Opinion

In the United States Court of Federal Claims No. 19-1520C

(Filed: January 29, 2021)

) JOHNSON LASKY KINDELIN ) ARCHITECTS, INC., for the benefit of ) IMEG CORP., f/k/a KJWW ) ENGINEERING ) ) Plaintiff, ) ) ) v. ) ) THE UNITED STATES, ) ) Defendant. )

OPINION AND ORDER

The Court once again must decide whether it has jurisdiction – pursuant to the Tucker Act, 28 U.S.C. § 1491(a), and the Contract Disputes Act (“CDA”), 41 U.S.C. §§ 7101–7109 – to decide a case predicated upon a government claim contained in a contracting officer’s final decision finding that two, unrelated contractors are jointly liable for the same injury and sum certain arising from alleged breaches of their respective, independent contracts. For the reasons discussed below, and based upon the Court’s previous decision in Johnson Lasky Kindelin Architects, Inc. v. United States (“JLK I”), No. 19-1419C, -- Fed. Cl. --, 2020 WL 7649972 (Dec. 23, 2020), the Court dismisses this case for lack of jurisdiction.

I. Factual Background

Plaintiff Johnson Lasky Kindelin Architects, Inc. (“JLK”) filed two separate complaints against Defendant, the United States of America, acting by and through the General Services Administration (“GSA”). Both cases involve the same underlying contract. This Court dismissed the first matter in JLK I. This decision addresses JLK’s second case against the government.

In 2010, GSA retained JLK to provide professional design services as the architect-engineer supporting the relocation of existing National Labor Relations Board (“NLRB”) office space. JLK I, 2020 WL 7649972, at *1 (Dec. 23, 2020). GSA separately contracted with Master Design Build, LLC (“MDB”) to provide the necessary construction services for the relocation of the NLRB office space. Id.

In JLK I, the claim at issue involved a supplemental air conditioning unit, which JLK designed for the NLRB space and MDB installed. Id. Ultimately, a condenser fluid pipe in the newly installed cooling system malfunctioned and caused extensive damage to parts of the NLRB space, as well as portions of the United States Bankruptcy Court on the sixth and seventh floors of the building in which the NLRB space was located. Id. at *2. GSA retained Bailey Edward, an independent architecture and engineer consulting firm, to investigate the cause of the condenser fluid piping system failure. Id. Following that investigation, Bailey Edward issued a report, in which the firm concluded that “that the leak resulted due to the confluence of several factors,” including issues with JLK’s design and MDB’s installation failures. Id. Bailey Edward, however, “determined that it could not assign fault to JLK to the exclusion of MDB (or the government) . . . .” Id.

After reviewing Bailey Edward’s report, the cognizant contracting officer issued a single contracting officer’s final decision (“COFD”) to both JLK and MDB for $1,938,866.86, claiming that both companies were jointly and severally liable to GSA for that amount. Id. at *3. While the COFD acknowledged that the design and construction services were provided separately by JLK and MDB under different contracts, the contracting officer nevertheless concluded that JLK and MDB were jointly and severally liable for the resulting damages and, accordingly, instructed them to collectively reimburse GSA. Id. In essence, the contracting officer issued a COFD finding two, unrelated contractors – JLK and MDB – jointly and severally liable for the same sum certain arising from independent breaches of their respective contracts with GSA. Id. at *1. It is this COFD upon which JLK’s first claim and complaint were predicated and that this Court ultimately dismissed in JLK I.

The above-captioned case raises a similar issue. As part of JLK’s prime contract with GSA, JLK hired a subcontractor, IMEG Corp. (“IMEG”), to provide design services for the installation of a fire alarm system. ECF No. 1 (“Compl.”) ¶ 9. After GSA determined that certain conduit connections for the fire alarm system were not furnished and installed per project specifications, MDB charged GSA $48,795.54 to complete the additional work. Id. at ¶¶ 15, 16. On October 2, 2018, the same contracting officer who had issued the COFD in JLK I issued another COFD, this time finding that JLK and MDB were jointly liable for the $48,795.54 MDB charged to GSA for the conduit work.1 Id. at ¶¶ 17, 18. The COFD at issue here uses identical language

1JLK, as a prime contractor, is responsible for the actions of its subcontractors. See Todd Const., L.P. v. United States, 656 F.3d 1306, 1316 (Fed. Cir. 2011) (“[A] contractor is responsible for the

-2- as the COFD in JLK I, with the agency claiming a sum certain from the same parties and under the same contracts at issue in JLK I, once again invoking a tort theory of joint liability.2

II. Procedural History

On October 1, 2019, JLK, for the benefit of IMEG, filed suit in this Court, alleging that the COFD for $48,795.54 was unreasonable and erroneous, or in the alternative, incomplete. Compl. at 7. JLK also filed a notice of directly related case, informing the Court that the instant case involved the same contracts as those at issue in JLK I, which had been filed several weeks prior. ECF No. 2. On January 9, 2020, GSA filed an answer and counterclaim, requesting that the Court enter judgment in GSA’s favor in the amount of $48,795.54 and dismiss JLK’s claim. ECF No. 14. JLK filed an answer to GSA’s counterclaim on January 30, 2020. ECF No. 15. The case was reassigned to the undersigned Judge on February 5, 2020. ECF Nos. 16, 17.

On March 19, 2020, the parties filed a joint preliminary status report requesting that further proceedings be stayed “in light of enforcement proceedings that the General Service Administration (GSA) will bring against Master Design Build, LLC (MDB) for the exact same debt – $48,795.54 – that is at issue in this litigation.” See ECF

unexcused performance failures of its subcontractors.”). This claim, brought by JLK on behalf of IMEG, is a sponsored (or “pass-through”) claim. See Montano Elec. Contractor v. United States, 114 Fed. Cl. 675, 680 (2014) (“Even absent privity of contract, a subcontractor's claims may be brought against the government if the prime contractor brings the suit on behalf of the subcontractor—as a pass-through or sponsored claim.”), aff'd, 610 F. App'x 987 (Fed. Cir. 2015); see also Compl. ¶ 10 (“In August of 2019 . . . JLK transferred its appellate rights against the GSA to IMEG, effectively, sponsoring any de facto claims which could be incurred by IMEG in relating to this matter.”). 2 In particular, the contracting officer determined as follows: JLK & MDB [a]re jointly liable because: 1) MDB/their sub did not provide the submittal initially that clarified what conduit/connection components were for the fire alarm system and what were for the remainder of the electrical systems installation; 2) JLK/their MEP sub did not clarify this further in their review of the submittals, to assure that the installation of the fire alarm system followed the specifications. Compl. at ¶ 18. Moreover, according to the second COFD, because “both JLK and MDB have both provided design and construction services, respectively, on numerous projects for GSA, they both were totally familiar with the all of the GSA requirements of a fire alarm system installation; simply put, this oversight on both of their parts should not have occurred in the first place.” Id.

-3- No. 18 at 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Todd Construction, L.P. v. United States
656 F.3d 1306 (Federal Circuit, 2011)
Montano Electrical Contractor v. United States
114 Fed. Cl. 675 (Federal Claims, 2014)
Montano Electrical Contractor v. United States
610 F. App'x 987 (Federal Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Johnson Lasky Kindelin Architects, Inc v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-lasky-kindelin-architects-inc-v-united-states-uscfc-2021.