Montano Electrical Contractor v. United States

114 Fed. Cl. 675, 2014 U.S. Claims LEXIS 105, 2014 WL 643469
United States Court of Federal Claims·Decided February 20, 2014·No. 13-435C·Published·Cited by 13 cases

Opinion

OPINION AND ORDER

LETTOW, Judge.

In this contract dispute, plaintiff Jose Montano, doing business as Montano Electrical Contractor (“Montano Electrical”), seeks payment from the United States (“the government”) for money allegedly owed for electrical work he performed as a subcontractor to a government contractor. Pending before the court is the government’s motion to dismiss for lack of subject matter jurisdiction pursuant to Rule 12(b)(1) of the Rules of the Court of Federal Claims (“RCFC”) or, alternatively, for failure to state a claim upon which relief can be granted pursuant to RCFC 12(b)(6). 1

BACKGROUND 2

On April 30,1999, the United States Army Corps of Engineers (“the Corps”), Mobile District, awarded American Renovation and Construction (“ARC”) a contract for the design and construction of family housing at Redstone Arsenal in Huntsville, Alabama. See Def.’s Mot. at 3. Following the award, ARC entered into a subcontract with Mr. Montano to complete electrical work on the project. Id. In January 2002, ARC defaulted on its contract with the government, and its surety, St. Paul Mercury Insurance Company (“St. Paul”), took over and completed the contract using Soltek Pacific (“Soltek”) as the completion contractor. See Compl. Ex. 3, ¶ 4 (A Montano Electrical Contractor, ASBCA No. 56951, 10-2 BCA ¶ 34587, 2010 WL 4418630 (Oct. 27, 2010) (“ASBCA Op.”)). 3 Mr. Montano and St. Paul executed two agreements, assigning Mr. Montano’s electrical subcontract to Soltek and releasing St. Paul from any claims Mr. Montano had against it. Compl. at 7. The complaint alleges that Mr. Montano signed the agreements under economic compulsion. Id. During the construction process, the original subcontract had been subject to a number of change orders. Compl. at 8-9. The complaint alleges that although Mr. Montano completed the electrical work for ARC, and later Soltek, as required, he was not fully compensated for a number of the change orders. Compl. at 9-10.

On April 14, 2003, St. Paul filed a claim with the government for an equitable adjustment attributable to the additional work and time needed to complete the Redstone Arsenal family-housing project. Compl. Ex. 29, at 2. On September 11, 2003, St. Paul submitted an amendment to its claim, indicating under the heading “Additional Subcontractor *678 Costs” that it was negotiating a settlement with Mr. Montano. Id. at 7. On December 23, 2003, Mr. Montano sent a claim to St. Paul seeking additional payments of $520,303.43 under the subcontract, Compl. at 4, also providing a copy of the claim to Gene Curtis, the Corps’ contracting officer, see Def.’s Mot. at 4. 4 The complaint alleges that Mr. Montano made telephone calls to Mr. Curtis during this time, seeking assistance regarding his claim against St. Paul. Compl. at 5. According to the complaint, during these conversations, Mr. Curtis stated that he could not help or provide advice because Mr. Montano was a subcontractor. Id. On April 30, 2004, however, Mr. Curtis wrote to Mr. Montano to remind him of his possible remedies against St. Paul under the Miller Act, 40 U.S.C. § 3133, and to inform him that Mr. Curtis had no authority to help him recover from St. Paul. Compl. Ex. 31 (Letter from Curtis to Montano (Apr. 30, 2004)). In this letter, Mr. Curtis mentioned that St. Paul had filed a claim with the government on the prime contract. Id. Over the next months, Mr. Montano and the Corps met twice to discuss the disputes between Mr. Montano and St. Paul. See Compl. Ex. 32, at 1 (Letter from Curtis to Montano (Sept. 8, 2004)). Among other things, Mr. Montano claimed that St. Paul was violating the Federal Acquisition Regulations (“FAR”), but Mr. Curtis informed him that the government had found no FAR violations by St. Paul and reiterated to Mr. Montano that the Miller Act was the appropriate remedy for nonpayment by the prime contractor. Id. Mr. Curtis also reminded Mr. Montano that the dispute did not involve the United States as a party and concluded that he found “no basis to pursue this [matter] further.” Id.

On November 24, 2004, Mr. Montano submitted a Freedom of Information Act (“FOIA”) request for documentation concerning the inspection and acceptance reports for the family-housing project at Redstone Arsenal, the takeover agreement between ARC and St. Paul, and St. Paul’s claim against the government regarding the Redstone Arsenal contract. Compl. Ex. 37, at 2 (Letter from Joseph Gonzales to Montano (Feb. 15, 2005)). The government denied this request because the relevant documents contained confidential business data. Id. Mi’. Montano filed an appeal of the denial. See Compl. Ex. 29, at 9 (Letter from Donna Black to Montano (Nov. 17, 2006)) (responding to the appeal). The Corps’ counsel advised that the appeal was under consideration at the Corps’s headquarters, and that St. Paul’s claim against the government “included costs for settlement with A. Montano Electrical in the amount of $156,200.00.” Id. Mr. Montano sought additional information regarding this settlement from the government, and on March 14, 2007, he received a letter, through counsel, from the Corps stating that a tentative settlement had been reached between St. Paul and the government but that “details [were] still being worked out.” See Compl. Ex. 30, at 2 (Letter from David Brasfield, Jr. to Robert Presto (Mar. 14,2007)). The Corps indicated that by June 30, 2007, it hoped to have the necessary funds available to implement the settlement. Id. On June 15, 2007, Mr. Montano’s counsel then contacted St. Paul in an attempt to secure a portion of the funds for Mr. Montano. Id. at 3 (Letter from Presto to Montano (June 15, 2007)). Mi*. Montano contends that he did not receive any portion of the settlement funds from St. Paul. Pl.’s Resp. at 19. Subsequently, the Corps informed Mr. Montano that the government had paid St. Paul the amount due under the settlement in June 2007 and considered the claim closed. See Compl. Ex. 28 (Letter from Black to Montano (Mar. 20, 2009)).

On September 13, 2009, Mr. Montano filed a request with the Armed Services Board of Contract Appeals (“ASBCA”) for “help” on his case. ASBCA Op. at 4. The ASBCA treated the request as an appeal under the Contracts Dispute Act (“CDA”), 41 U.S.C. §§ 7104(a), 7105(e)(1)(A). Ultimately, the ASBCA determined that it lacked jurisdiction over the appeal because Mr. Montano *679 was not a contractor as required by the CDA but rather was a subcontractor. ASBCA Op. at 5.

Free access — add to your briefcase to read the full text and ask questions with AI

Montano Electrical Contractor v. United States, 114 Fed. Cl. 675, 2014 U.S. Claims LEXIS 105, 2014 WL 643469 (uscfc 2014).

114 Fed. Cl. 675 (Montano Electrical Contractor v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Dunbar-Brown v. United States
Federal Claims, 2026
Embrey v. United States
Federal Claims, 2020
Montano Electrical Contractor v. United States
610 F. App'x 987 (Federal Circuit, 2015)
Montiel v. United States
118 Fed. Cl. 283 (Federal Claims, 2014)
Allen v. United States
Federal Claims, 2014
Taylor-Tillotson v. United States
115 Fed. Cl. 800 (Federal Claims, 2014)