J. L. Simmons Company, Inc., a Corporation v. The United States

304 F.2d 886, 158 Ct. Cl. 393, 1962 U.S. Ct. Cl. LEXIS 187
CourtUnited States Court of Claims
DecidedJuly 18, 1962
Docket186-59
StatusPublished
Cited by58 cases

This text of 304 F.2d 886 (J. L. Simmons Company, Inc., a Corporation v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. L. Simmons Company, Inc., a Corporation v. The United States, 304 F.2d 886, 158 Ct. Cl. 393, 1962 U.S. Ct. Cl. LEXIS 187 (cc 1962).

Opinion

JONES, Chief Judge.

This suit is brought by the J. L. Simmons Co., Inc., in its own behalf as prime contractor and for the benefit of 12 of its subcontractors to recover additional costs and damages allegedly incurred as a result of defendant’s breach of a construction contract. Defendant has filed a motion for partial summary judgment aimed at dismissing plaintiff’s petition insofar as it represents claims in behalf *887 of nine 1 of these subcontractors for failure to state a claim upon which relief can be granted.

The factual background giving rise to this suit may be briefly summarized for the purpose of resolving the legal issue raised by defendant’s motion. On October 5, 1949, plaintiff entered into a contract with defendant, acting through the Veterans Administration, whereby plaintiff agreed to furnish the labor, materials, and equipment, and perform all work necessary, for the complete construction of the West Side Veterans Hospital, Chicago, Illinois, and supporting facilities. Much of the work required to accomplish this result was thereafter subcontracted by plaintiff to other firms, twelve of whom are involved in this suit.

The claims here asserted relate to certain difficulties encountered by plaintiff and one of its subcontractors in the installation of the pile foundation for the main hospital building. It is said that plaintiff and these twelve subcontractors incurred the additional costs or damages sued for as a direct result of these foundation difficulties and the delays flowing therefrom. It is further contended that these difficulties were caused, primarily, by defendant’s breach of contract in failing to provide a suitable and workable design for the construction and installation of this foundation.

Be that as it may, plaintiff finally completed its performance of the contract on April 30, 1953. On April 15, 1953, however, and at various times thereafter until December 18, 1956, plaintiff executed with each of the nine subcontractors encompassed by defendant’s motion certain documents denominated “Subcontractor’s Waiver of Lien and Release.” The language of all of these documents is identical and pro vides:

“for the consideration aforesaid, the undersigned hereby waives, releases and discharges any and all liens, claim or right of lien, which may be afforded the subcontractor by any state or federal law or otherwise, including but not limited to any lien against the above prescribed buildings and premises on which the same are located or against which any funds due or to become due J. L. simmons company, INC., and any other claim or demand against J. L. SIMMONS COMPANY, INC., or its sureties, with the exception of its claim for losses because of engineering errors in design committed by the Veterans Administration. In the prosecution of any claim which J. L. simmons company, inc. shall advance against the United States for losses resulting from such error of design on the part of the Veterans Administration, there shall be included the claim of the undersigned. General expenses incident to the preparation and prosecution of such claim of the undersigned shall be borne by J. L. simmons company, inc., except that, at its own expense, the undersigned will provide for the attendance of whatever witnesses and the preparation of whatever documents may be necessary for the presentation of said claim. The selection of attorneys for the presentation of all claims (with the exception of the claim of MacArthur Concrete Pile Corporation who shall be permitted to engage counsel to act in collaboration with counsel selected by J. l. simmons company, inc.) shall be controlled by j. L. simmons COMPANY, INC. The portion of the *888 contingent fee to be charged against the recovered amount allocable to said claim of the undersigned, in the event that recovery is made, shall be as heretofore agreed upon in writing. Although J. L. SIMMONS COMPANY, INC. will attempt to have the claim of the undersigned separately considered and the amount thereof separately determined, it is recognized that such efforts may not be successful and that the amount allowed on said claim may be included in a single lump sum finding of damages sustained. If such be the case, the amount of the undersigned’s allowed claim shall be arrived at by determining the proportion which its claim as computed by Department of Justice Audit bears to the total of all allowed claims as computed by Department of Justice Audit. Either the disállowance of the undersigned’s claim by the court or the payment to the undersigned by J. L. SIMMONS COMPANY, INC. of the amount, if any, that may be recovered on said claim (less the proportion of expenses and attorneys’ fees, hereinbefore referred to, and less 25% of the amount remaining after the deduction of such proportion of expenses and attorneys’ fees) shall completely extinguish all further obligation of J. L. simmons company, inc. to the undersigned under the subcontract of . hereinbefore referred to, and shall operate as a full and complete release of any and all liability of j. L. SIMMONS COMPANY, INC. to the undersigned arising out of the performance by the undersigned of its work under said subcontract.”

Defendant’s motion is premised on the proposition that these documents preclude plaintiff from asserting against the Government the claims of these nine subcontractors because of the so-called “Severin doctrine.” Severin v. United States, 99 Ct.Cl. 435 (1943), cert. denied 322 U.S. 733, 64 S.Ct. 1045, 88 L.Ed. 1567 (1944). That is, these claims cannot now constitute a part of the damages sustained by this plaintiff, because of defendant’s alleged breach of contract, since plaintiff has not reimbursed these subcontractors for their damages and has no independent liability to do so in the future, having effectively insulated itself from such liability by virtue of these releases. Defendant argues that the releases, although purporting to exempt these subcontractor claims, actually have the effect of relieving plaintiff of all possible liability for them. According to defendant, the documents simply provide for the happening of one of two possible events — if this court allows the claims of these subcontractors, plaintiff will pay over to them an unspecified amount of the recovery; if this court disallows their claims, all further obligation of plaintiff to the subcontractors will be extinguished. This, defendant concludes, is no liability on the part of plaintiff at all.

Since our decision in the Severin case, supra, this court has repeatedly delineated the only grounds upon which a prime contractor may sue the Government for damages incurred by one of its subcontractors through the fault of the Government. The decided cases make abundantly clear that a suit of this nature may be maintained only when the prime contractor has reimbursed its subcontractor for the latter’s damages or remains liable for such reimbursement in the future. These are the only ways in which the damages of the subcontractor can become, in turn, the damages of the prime contractor, for which recovery may be had against the Government. Continental Illinois National Bank & Trust Co. v. United States, 81 F.Supp. 596, 112 Ct.Cl. 563 (1949); Warren Brothers Roads Co. v. United States, 105 F.Supp. 826, 123 Ct.Cl. 48 (1952); F. H. McGraw & Co. v. United States, 131 Ct.Cl. 501, 130 F.Supp. 394 (1955); J. W. Bateson Co., Inc. v. United States, 143 Ct.Cl. 228, 163 F.Supp. 871 (1958).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2020
Montano Electrical Contractor v. United States
114 Fed. Cl. 675 (Federal Claims, 2014)
Northrop Grumman Computing Systems, Inc. v. United States
99 Fed. Cl. 651 (Federal Claims, 2011)
ACE Constructors, Inc. v. United States
70 Fed. Cl. 253 (Federal Claims, 2006)
Gentex Corp. v. United States
61 Fed. Cl. 49 (Federal Claims, 2004)
Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
Alamo Community College District v. Browning Construction Co.
131 S.W.3d 146 (Court of Appeals of Texas, 2004)
Inter Contr Corp v. City of Dallas Texas
407 F.3d 708 (Fifth Circuit, 2003)
Interstate Contracting Corp. v. City of Dallas
320 F.3d 539 (Fifth Circuit, 2003)
Roof-Techs International, Inc. v. State
57 P.3d 538 (Court of Appeals of Kansas, 2002)
Perry-McCall Construction, Inc. v. United States
46 Fed. Cl. 664 (Federal Claims, 2000)
Morrison Knudsen Corp. v. Fireman's Fund Insurance
175 F.3d 1221 (Tenth Circuit, 1999)
Ecology & Environment, Inc. v. United States
43 Cont. Cas. Fed. 77,456 (Federal Claims, 1999)
Kentucky Bridge & Dam, Inc. v. United States
42 Cont. Cas. Fed. 77,404 (Federal Claims, 1998)
James Reeves Contractor, Inc. v. United States
39 Cont. Cas. Fed. 76,694 (Federal Claims, 1994)
George Hyman Construction Co. v. United States
39 Cont. Cas. Fed. 76,601 (Federal Claims, 1993)
Eastern Trans-Waste of Maryland, Inc. v. United States
27 Fed. Cl. 146 (Federal Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
304 F.2d 886, 158 Ct. Cl. 393, 1962 U.S. Ct. Cl. LEXIS 187, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-l-simmons-company-inc-a-corporation-v-the-united-states-cc-1962.