Warren Bros. Roads Co. v. United States

105 F. Supp. 826, 123 Ct. Cl. 48, 1952 U.S. Ct. Cl. LEXIS 27
CourtUnited States Court of Claims
DecidedJuly 15, 1952
Docket47557
StatusPublished
Cited by36 cases

This text of 105 F. Supp. 826 (Warren Bros. Roads Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Warren Bros. Roads Co. v. United States, 105 F. Supp. 826, 123 Ct. Cl. 48, 1952 U.S. Ct. Cl. LEXIS 27 (cc 1952).

Opinion

*827 WHITAKER, Judge.

Plaintiff, Warren Brothers Roads Company, a paving contractor, sues to recover the losses which it and its subcontractor, A. G. Wimpy, allegedly incurred in constructing the Troy, Alabama, airport for the Civil Aeronautics Administration. Plaintiff’s claims are divided into three separate causes of action, each involving a separate period of performance. In addition, plaintiff presents a fourth cause of action consisting of Wimpy’s claims for each of these three periods.

First Cause of Action

In December 1943 plaintiff received from Civil Aeronautics Administration an invitation to bid on three schedules of work to be performed in constructing the Troy airport project. Schedule I called for bids on the clearing, grading, and draining of the site; Schedule II called for bids on the fine grading preparatory to paving, prime coating, and asphalt paving of the runways, and the seeding and fertilizing of conditioned areas surrounding the runways; and Schedule III requested bids upon a combination of Schedules I and II.

The specifications included in the bid proposal provided that if separate awards were made on Schedules I and II, it was intended that notice to proceed on Schedule II, the paving operations, would be issued not more than 70 calendar days after notice to proceed was issued on Schedule I, but the right was reserved to the Government to change the specifications prior to and during the negotiations for a contract or contracts. On the basis of this information contained in the invitation for bids, plaintiff submitted a bid to perform the work called for in Schedule II.

After plaintiff had submitted its bid, but before it entered into a contract with defendant, the Civil Aeronautics Administration on February 5, 1944, entered into a contract with Nolan-Dickerson Construction Company to clear, drain, and grade the airport site within 120 days from the effective date of notice to proceed, and further, to complete and deliver one runway, ready for paving, to the paving contractor within 40 days after notice to proceed, rather than within 70 days as provided in the original invitation for bids. This change in the completion time for the first runway was the result of negotiations which occurred between Nolan-Dickerson Construction Company and representatives of the Civil Aeronautics Administration following the opening of the bids, whereby Nolan-Dickerson Construction Company agreed to shorten the performance period in return for a $37,050 increase in its original ibid price.

Plaintiff, on February 9, 1944, executed a written contract with the Civil Aeronautics Administration to perform the seeding, fertilizing, and paving work called for in Schedule II within 80 days from the effective date of its notice to proceed for the sum of $454,802. 1 Plaintiff’s written contract incorporated the specification contained in the invitations for bids, which provided that notice to proceed on the paving work would be issued in not more them 70 days after the issuance of notice to proceed on Schedule I. However, the Civil Aeronautics Administration, in its letter of transmittal of the unsigned contract, advised plaintiff as follows:

“The Government will not be responsible for any action taken by you looking to the prosecution of this project until final award is made and notice to proceed is given.
“It is intended that notice to proceed will be issued not more than forty calendar days after notice to proceed is issued to the contractor under Schedule I.”

Notice to proceed was issued to Nolan-Dickerson Construction Company on February 22, 1944. In order to be ready to commence paving operations within 40 days thereafter, viz., by April 2, 1944, plaintiff immediately began to assemble its men and equipment. Plaintiff owned a large portable asphalt mixing plant which could be disassembled and shipped by rail from project to project. As the erection of this plant re *828 quired approximately 30 days in addition to the shipping time, and as the issuance of plaintiff’s notice to proceed was expected within 40 days, plaintiff shipped at once the plant to the Troy project, and sent with it the permanent crew which assembled, maintained, and operated it.

By April 2, 1944, plaintiff could have had this plant ready for operation if there had been any areas ready for paving. However, abnormally heavy rains were encountered during March and April which rendered grading virtually impossible. Plains tiff’s representatives who were on the site realized that these rains, which were 10'.71 inches in excess of normal in March and 9.87 inches in excess of normal in April, would delay the start of paving operations. Accordingly, plaintiff prolonged the erection of the asphalt plant in order to provide work for its permanent crew, which could not be discharged because of wartime labor restrictions and shortages. These delays continued from April 2, 1944, the anticipated date of notice to proceed, through April 30, a period of 29 days. Plaintiff was finally able to begin paving operations on May 1, 1944, although notice to proceed was not actually issued until May 5, 1944.

During the 29 days of delay in April plaintiff endeavored to make work for its crew of men in order to keep them occupied. At times the workmen were kept busy cleaning, repairing and adjusting the equipment, which work normally would have been performed while the plant was in operation ; but plaintiff was unable to keep them busy all the time, although it had to pay them for the entire time.

Plaintiff insists that it is entitled to recover from defendant the losses which it suffered during the 29-day delay period, because of the fact that defendant advanced the completion date of the grading on Runway No. 1 from 70 to 40 days. Plaintiff says it was thereby compelled to immediately bring to the job its men and equipment; whereas, if the original period of 70 days had been left unchanged, it would have been unnecessary for it to have done so, and that it would not have done so until the rains had stopped and until after grading operations had begun.

Defendant’s position is that plaintiff’s losses are the result of the vagaries of the weather for which it is not responsible. Defendant also insists that the advancement of the date of issuance of notice to proceed to plaintiff was a proper exercise of the right reserved to it in the bid proposal to change or modify the specifications during the course of the negotiations. Defendant says there was no misrepresentation concerning the date of issuance of plaintiff’s notice to proceed since it informed plaintiff of these changes before the written contract was executed, and plaintiff registered no* protest.

Defendant had the right to change the specifications and it notified plaintiff it had done so before the contract was signed. Plaintiff’s losses were not due to any wrongful act of defendant’s, but were due solely to the adverse weather conditions which were unexpectedly encountered and which delayed the grading operations. The unusual quantities of rain which fell during March and April were an act of God, for which neither party to the contract was responsible. United States v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
Big Chief Drilling Co. v. United States
38 Cont. Cas. Fed. 76,418 (Court of Claims, 1992)
American Line Builders, Inc. v. United States
38 Cont. Cas. Fed. 76,406 (Court of Claims, 1992)
Fairchild Industries, Inc. v. United States
620 F.2d 807 (Court of Claims, 1980)
W. G. Cornell Co. v. Ceramic Coating Co.
626 F.2d 990 (D.C. Circuit, 1980)
Parker v. Department of Health, Education, & Welfare
478 F. Supp. 1156 (M.D. Tennessee, 1979)
Turnkey Enterprises, Inc. v. United States
597 F.2d 750 (Court of Claims, 1979)
Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
Wallingford Steel Co. v. Wire & Metal Specialties Corp.
347 F. Supp. 1310 (W.D. Pennsylvania, 1972)
Law v. United States
195 Ct. Cl. 370 (Court of Claims, 1971)
Dewey Jordan v. MD.-NAT'L CAP. P. & P.
265 A.2d 892 (Court of Appeals of Maryland, 1970)
Tombigbee Constructors v. The United States
420 F.2d 1037 (Court of Claims, 1970)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Jefferson Construction Company v. The United States
392 F.2d 1006 (Court of Claims, 1968)
Allied Contractors, Inc. v. The United States
381 F.2d 995 (Court of Claims, 1967)
Luria Brothers & Company, Inc. v. The United States
369 F.2d 701 (Court of Claims, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
105 F. Supp. 826, 123 Ct. Cl. 48, 1952 U.S. Ct. Cl. LEXIS 27, Counsel Stack Legal Research, https://law.counselstack.com/opinion/warren-bros-roads-co-v-united-states-cc-1952.