Kilgore v. United States

121 Ct. Cl. 340, 1952 U.S. Ct. Cl. LEXIS 148, 1952 WL 5897
CourtUnited States Court of Claims
DecidedJanuary 8, 1952
DocketNo. 48851
StatusPublished
Cited by6 cases

This text of 121 Ct. Cl. 340 (Kilgore v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kilgore v. United States, 121 Ct. Cl. 340, 1952 U.S. Ct. Cl. LEXIS 148, 1952 WL 5897 (cc 1952).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

On June 19, 1942, plaintiffs entered into a contract with defendant for the grading, paving, draining, and fencing of the Jefferson County Airport near Beaumont, Texas. The project was to be completed within 120 days after receipt of notice to proceed. . The 120 days expired on October 25,1942. The contract was terminated by defendant on December 15, 1942, “because,” as stated in the contracting officer’s letter, “of your failure to complete the contract within the contract time.” Plaintiffs claim that the termination was wrongful and they sue for damages which they say they sustained.

From the outset plaintiffs encountered excessive rainfall. In July 1942 there were eight inches of rainfall in excess of normal, and in both August and September there were more than three inches in excess of normal. In all, there were thirty-three days between July 3 and October 25,1942 when rain fell at the project.

The airport was to be constructed .on marshy clay soil formerly used for the production of rice. Old terraces and levees, which had been constructed to retain water for the rice paddies, were still in place when plaintiffs commenced the work. The area was filled with deep ruts left by rice harvesting machinery, which, together with the terraces, blocked the normal drainage of the area, and also rendered partially ineffective plaintiffs’ attempts to provide temporary drainage. Consequently, water frequently covered the field to a depth of two feet during this period, making excavation work practically impossible. The only work which progressed under such conditions was the installation of the storm drainage system. The water and mud did not substantially interfere with this work because draglines were used for excavating the ditches and sleds were used for hauling the drain pipes.

Plaintiffs’ excavation subcontractor araived on the project after the rainy period had begun, and although he worked whenever weather conditions permitted, he made very little [367]*367progress, not only because of the rain, but also because of his lack of adequate equipment. On September 6,1942, plaintiffs relieved the excavation subcontractor and assumed that portion of the work themselves.

As a result of the adverse weather and the lack of adequate machinery, plaintiffs had completed only 2.03 per cent of the contract by August 1, 9.3 per cent by September 1, and 15.3 per cent by October 1,1942. The District Engineer was dissatisfied with this showing by plaintiffs, notwithstanding the adverse weather conditions, and by letter of September 10 threatened to terminate plaintiffs’ right to proceed unless they effected considerable improvement by September 15. Plaintiffs told the District Engineer that they had additional scrapers enroute to the project, which they felt would enable them to increase the rate of progress and, because of this, they were permitted to proceed.

Plaintiffs encountered no abnormal weather conditions from September 18 to October 25, 1942.

On October 22, just prior to the contract completion date, Colonel Hewitt, the District Engineer, who was the superior of the contracting officer, conferred with plaintiffs to determine whether they could complete the contract within a reasonable time. Plaintiffs stated that they could complete it within 45 days, and upon this assurance Colonel Hewitt orally agreed that they might proceed with the work provided that they would put adequate machinery on the job and replace the present superintendent in charge of the work with a competent one and would furnish a progress chart showing the manner in which they proposed to complete the project.

Plaintiffs complied with these requests, and by November 1, 1942, had completed 20.6 per cent of the work. On November 7, plaintiffs began to work day and night shifts. Substantial progress was made thereafter and by November 20 plaintiffs had placed the base course on one runway over an area 1,600 feet long and 30 feet wide. (The contract called for two runways, each 4,000 feet long and 150 feet wide, and for 6,800 linear feet of taxiways.) On this date plaintiffs requested permission for their subcontractor to begin [368]*368pa.vi.ng the runway, but this permission was denied by the resident engineer on the ground that plaintiffs had not properly compacted the base course.

On November 23,1942, plaintiffs and their paving subcontractor visited the District Engineer to protest the refusal to permit them to begin paving. At this visit plaintiffs delivered to him a letter requesting that “the contracting officer” grant an additional eighty-day extension due to adverse weather conditions, scarcity of materials, and labor shortages. The District Engineer orally refused plaintiffs’ request and informed them that he intended to terminate their right to proceed because of their failure to maintain the rate of progress promised on October 22,1942, and that, therefore, it would be inadvisable to permit plaintiffs’ subcontractor to begin paving the runways. Colonel Hewitt, the District Engineer, also' told plaintiffs that the Civil Aeronautics Administration had authorized the enlargement of the airport, and that he had been ordered to proceed with plans for the additional work.

Following this meeting. Colonel Hewitt wrote a letter to plaintiffs, on December 2, 1942, denying their request of November 23 for an eighty-day extension of time, and terminating their right to proceed under the contract, effective December 15, because of plaintiffs’ “failure to complete the contract within the required time.” Another reason for terminating the contract, although this reason was not given in the letter of the District Engineer, was the fact that the additional work for the enlargement of the project was to be contracted for immediately, and plaintiffs’ past rate of progress did not indicate that they would be able to complete the enlarged project within a l’easonable time.

Plaintiffs did not appeal from either the denial of the request for an extension of time or from the order of termination. Instead, plaintiffs wrote to the District Engineer on December 5,1942, stating that they would attempt to cooperate in all respects with the new prime contractor. On December 15 plaintiffs discontinued work on the project, which at that time, 171 days after the starting date, and 51 days after the contract completion date, was only about 2'9 percent completed.

[369]*369On January 15, 1943, defendant contracted with the firm of Euss Mitchellj Inc.$ to complete the remainder of the plaintiffs’ work, and also to perform the additional work involved in enlarging the airport.

On January 20, 1943, plaintiffs wrote to the new District Engineer, Colonel Saville, requesting that he waive their failure to appeal within the time limit from the denial of their request for an extension of time, and to reconsider the data attached to their letter. This request was granted, and as a result of a detailed investigation, a contract modification was issued on February 26,1943, granting plaintiffs an extension of 51 days for weather delays, which extended the completion date until December 15, 1942, thus making it coincide with the effective date of termination. On May 11, 1943, plaintiffs signed the modification without protest, and again did not appeal from the decision.

By April 18, 1944, the new contractor had completed the work, enabling the defendant to issue a final estimate and settlement statement for plaintiffs’ contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fairchild Industries, Inc. v. United States
620 F.2d 807 (Court of Claims, 1980)
H. R. Henderson & Co. v. United States
169 Ct. Cl. 228 (Court of Claims, 1965)
Friedman v. United States
310 F.2d 381 (Court of Claims, 1962)
Poloron Products, Inc. v. United States
116 F. Supp. 588 (Court of Claims, 1953)
Warren Bros. Roads Co. v. United States
105 F. Supp. 826 (Court of Claims, 1952)
Olsen v. United States
122 Ct. Cl. 106 (Court of Claims, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
121 Ct. Cl. 340, 1952 U.S. Ct. Cl. LEXIS 148, 1952 WL 5897, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kilgore-v-united-states-cc-1952.