United States v. Blair Ex Rel. Roanoke Marble & Granite Co.

321 U.S. 730, 64 S. Ct. 820, 88 L. Ed. 1039, 1944 U.S. LEXIS 1214
CourtSupreme Court of the United States
DecidedMay 8, 1944
Docket75
StatusPublished
Cited by224 cases

This text of 321 U.S. 730 (United States v. Blair Ex Rel. Roanoke Marble & Granite Co.) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Blair Ex Rel. Roanoke Marble & Granite Co., 321 U.S. 730, 64 S. Ct. 820, 88 L. Ed. 1039, 1944 U.S. LEXIS 1214 (1944).

Opinions

Mb. Justice Murphy

delivered the opinion of the Court.

Respondent, a general contractor of long experience in constructing federal buildings, was awarded a contract by the United States to construct certain buildings at the Veterans’ Administration Facility at Roanoke, Virginia. After completing the contract, respondent filed a claim with the Veterans’ Administration for certain expenses which he claimed were caused by the delay of a mechanical contractor and for other expenses alleged to have been imposed on him by the arbitrary, capricious and unfair conduct of Government agents at the work site. The claim was rejected and this suit in the Court of Claims followed. Judgment in the sum of $130,911.08 was awarded by that court to respondent, 99 Ct. Cls. 71. We granted certiorari because of important questions of interpretation of the Government construction contract used in this case.1

I.

Respondent’s contract provided that the construction work was to be completed within 420 days from the receipt of notice to proceed. Concurrently, one R. J. Redmon was awarded a mechanical contract2 by the United [732]*732States to perform the plumbing, heating and electrical work in the buildings to be constructed by respondent. Redmon’s work was to be commenced promptly after receipt of notice to proceed and was to be completed at a date not later than that provided in respondent’s contract.

Respondent proceeded promptly with the construction work. He planned to complete the work within 314 days instead of the 420 days allowed him by the contract. However, no representative of Redmon reported at the work site until nearly three months after he received notice to proceed. The contracting officer had previously made many urgent demands that Redmon proceed with his work and had advised him that the progress of respondent’s construction work was being delayed by hi» failure to start work; Redmon had also been threatened with termination of his contract. He finally started work, but made slow progress. At no time did Redmon have adequate equipment or a sufficient number of men on the job properly to carry on the work called for by his contract, nor was he financially able at this time to complete his work. The Court of Claims found that reasonable inquiry by the Government would have disclosed these facts but that no such inquiry was made because of false statements and reports made to the contracting officer by the Government agents in charge of the work at the site.

Several months later, Redmon advised the contracting officer that he was unable to proceed with his contract. Redmon’s surety secured a substitute and every effort was made to overcome the delay. As a result, respondent was able to finish his construction work within the required 420 days but not within the 314 days as he had planned. The court below found that respondent was unreasonably delayed for a period of three and one-half months due to the failure of the United States promptly to terminate [733]*733Redmon’s right to proceed, that the cost of the delay to respondent was $51,249.52, and that the United States was liable therefor.

We are of the opinion, however, that nothing in the Government construction contract used in this case imposed an obligation or duty on the Government to aid respondent in completing his contract prior to the stipulated completion date and that it was error for the Court of Claims to award damages to respondent based upon a breach of this non-existent obligation.

If the parties did intend to impose such an obligation or duty on the Government, they failed to embody that intention expressly in the contract. Article 13 of the contract merely obligates the contractor to cooperate with other Government contractors and to refrain from committing or permitting any act which would delay such other contractors. Article 9 imposes liquidated damages upon the contractor for delay in completing his work unless due to such unforeseeable causes as “acts of the Government.” Nowhere is there spelled out any duty on the Government to take affirmative steps to prevent a contractor from unreasonably delaying or interfering with the attempt of another contractor to finish ahead of his schedule.

Nor is there anything in the context of the contract to lead us to believe that the parties meant more than they said, or that the contract implies something that was not expressed. The Government and respondent covenanted that the construction work would be completed within 420 days; Redmon’s contract was grounded on this same time estimate. They cannot be said to have executed these contracts in contemplation of the then unrevealed intention of respondent to complete his work three and one-half months early. The fact that respondent subsequently gave notice of this intention to all the other parties con[734]*734cerned could not give rise to a new obligation on the Government to compel accelerated performance from Redmon.

Respondent had the undoubted right to finish his construction work in less time than the stipulated 420 days, but he could not be forced to do so under the terms of the contract. To hold that he can exact damages from the Government for failing to cooperate fully in changing the contract by shortening the time provisions would be to imply a grossly unequal obligation. We cannot sanction such liability without more explicit language in the contract. Compare Crook Co. v. United States, 270 U. S. 4; United States v. Rice, 317 U. S. 61.

II.

The Court of Claims, in addition to awarding damages for the Government’s delay in terminating Redmon’s contract, awarded respondent $79,661.56 damages for extra labor and materials, excess wages and miscellaneous costs found to be the result of unauthorized acts, rulings and instructions of the Government superintendent and his assistant. The court also found that these acts, rulings and instructions were unreasonable and in many instances arbitrary, capricious and so grossly erroneous as to imply bad faith.

Assuming without deciding that the actions complained of were unauthorized, unreasonable and arbitrary, we cannot conclude that recovery of the resulting damages was proper in this case. Article 15 of the contract in suit provides that all disputes “concerning questions arising under this contract shall be decided by the contracting officer or his duly authorized representative, subject to written appeal by the contractor within 30 days to the head of the department concerned or his duly authorized representative, whose decision shall be final and conclusive upon the parties thereto as to such questions.” All [735]*735of the items on which the recovery of $79,661.56 was based were the subject of “disputes concerning questions arising under this contract.” Respondent appealed some of the decisions or instructions of the Government superintendent to the contracting officer, which resulted in at least one ruling favorable to respondent.3 As to the adverse rulings, however, respondent made no further appeal to the head of the appropriate department or his authorized representative. Moreover, the remaining items which were the subject of sharp dispute between respondent and the superintendent were not even appealed by respondent to the contracting officer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sufi Network Services, Inc. v. United States
785 F.3d 585 (Federal Circuit, 2015)
Coffee Connections, Inc. v. United States
113 Fed. Cl. 741 (Federal Claims, 2013)
Paschen Contractors, Inc. v. City of Kankakee
Appellate Court of Illinois, 2004
Frank Briscoe Co., Inc. v. County of Clark
772 F. Supp. 513 (D. Nevada, 1991)
Farrell Construction Co. v. Jefferson Parish
693 F. Supp. 490 (E.D. Louisiana, 1988)
Havens Steel Co. v. Randolph Engineering Co.
613 F. Supp. 514 (W.D. Missouri, 1985)
Mitsui & Co. v. Puerto Rico Water Resources Authority
528 F. Supp. 768 (D. Puerto Rico, 1981)
Walter Kidde Constructors, Inc. v. State
434 A.2d 962 (Connecticut Superior Court, 1981)
Kyle Engineering Co. v. Kleppe
600 F.2d 226 (Ninth Circuit, 1979)
Sun Shipbuilding & Dry Dock Co. v. United States Lines, Inc.
439 F. Supp. 671 (E.D. Pennsylvania, 1977)
Banks Construction Company, Inc. v. The United States
364 F.2d 357 (Court of Claims, 1966)
Northern Metal Co. v. United States
350 F.2d 833 (Third Circuit, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
321 U.S. 730, 64 S. Ct. 820, 88 L. Ed. 1039, 1944 U.S. LEXIS 1214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-blair-ex-rel-roanoke-marble-granite-co-scotus-1944.