NAN, INC. v. WOOD ENVIRONMENT & INFRASTRUCTURE SOLUTIONS, INC.

CourtDistrict Court, D. New Jersey
DecidedFebruary 2, 2022
Docket3:21-cv-00707
StatusUnknown

This text of NAN, INC. v. WOOD ENVIRONMENT & INFRASTRUCTURE SOLUTIONS, INC. (NAN, INC. v. WOOD ENVIRONMENT & INFRASTRUCTURE SOLUTIONS, INC.) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NAN, INC. v. WOOD ENVIRONMENT & INFRASTRUCTURE SOLUTIONS, INC., (D.N.J. 2022).

Opinion

NOT FOR PUBLICATION

UNITED STATES DISTRICT COURT DISTRICT OF NEW JERSEY

NAN, INC., Plaintiff, Civil Action No. 21-707 (MAS) (DEA) " MEMORANDUM OPINION WOOD ENVIRONMENT & INFRASTRUCTURE SOLUTIONS, INC., Defendant.

SHIPP, District Judge This matter comes before the Court on Defendant Wood Environment & Infrastructure Solutions, Inc.’s (“Wood”) Partial Motion to Dismiss Plaintiff Nan, Inc.’s (“Nan”) Amended Complaint. (ECF No. 19.) Nan opposed (ECF No. 22), and Wood replied (ECF No. 23). The Court has carefully considered the parties’ submissions and decides this matter without oral argument under Local Civil Rule 78.1. For the reasons below, the Court grants in-part and denies in-part Wood’s Partial Motion to Dismiss. L. BACKGROUND This dispute arises out of a construction project in the Marshall Islands commissioned by the U.S. Air Force. The U.S. Air Force selected Lockheed Martin to serve as the project’s prime contractor, meaning it would manage the project and hire any necessary subcontractors. (See Am. Compl. {J 8-9.) Lockheed Martin hired Wood, an engineering firm, as one such subcontractor. (/d.

{ 9.) Wood in turn hired another subcontractor, Nan, for “construction, labor, materials, equipment, and supervision” of the project. Ud. 12.) As relevant here, Nan’s Amended Complaint alleges that it entered into six contracts with Wood pertaining to Nan’s work on the project. (id. § 17.) Under those contracts, the Amended Complaint alleges that Nan submitted to Wood fifty-two change orders, which are requests for various changes to the originally agreed-upon scope of work. (See id.) The Amended Complaint further alleges that at least some of the change orders resulted from delays caused by Wood or its agents. (See id. {J 25-30.) Further, Nan’s Amended Complaint alleges that thirteen of the fifty-two change orders stemmed from monies Nan owed its subcontractor, Photonworks. Ud. J 44-45; see also id. § 16 (alleging that Photonworks has asserted claims against Nan’s surety).) Rounding out the allegations, the Amended Complaint asserts that Wood never reimbursed Nan for these fifty-two change orders. (See id. § 47; Def.’s Moving Br. 4-5, ECF No. 19-1 (“The change order requests seek money for alleged damages due to Project delays, extra costs associated with the construction, rental payments for equipment and containers, and monies allegedly owed to Nan for rest and relaxation.” (citation omitted)).) Based on Wood’s alleged nonpayment, Nan sued in January 2021. Nan later filed an Amended Complaint, asserting four counts against Wood: (1) breach of contract (Count J), (2) breach of the covenant of good faith and fair dealing (Count ID), (3) unjust enrichment (Count V), and (4) violation of the New Jersey Prompt Payment Act (the “Act,” Count VI). (See generally Am. Compl.)' Wood moved to partially dismiss the Amended Complaint’s breach-of-contract claim insofar as it asserts claims on behalf of non-party Photonworks, and to fully dismiss the remaining claims. (See generally Def.’s Mot. to Dismiss, ECF No. 19.)

' The Amended Complaint does not contain Count ITI or Count IV.

Il. LEGAL STANDARD Federal Rule of Civil Procedure 8(a)(2)’ “requires only ‘a short and plain statement of the claim showing that the pleader is entitled to relief,’ in order to ‘give the defendant fair notice of what the .. . claim is and the grounds upon which it rests.’” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555 (2007) (alteration in original) (quoting Conley v. Gibson, 355 U.S. 41, 47 (1957). A district court conducts a three-part analysis when considering a motion to dismiss pursuant to Rule 12(b)(6). Malleus v. George, 641 F.3d 560, 563 (3d Cir. 2011). “First, the court must ‘tak[e] note of the elements a plaintiff must plead to state a claim.’” Jd. (alteration in original) (quoting Ashcroft v. Iqbal, 556 U.S. 662, 675 (2009)). Second, the court must accept as true all of the plaintiffs well-pleaded factual allegations and “construe the complaint in the light most favorable to the plaintiff.” Fowler v. UPMC Shadyside, 578 F.3d 203, 210 (3d Cir. 2009) (citation omitted). The court, however, may ignore legal conclusions or factually unsupported accusations that merely state “the-defendant-unlawfully-harmed-me.” Iqbal, 556 U.S. at 678 (citing Twombly, 550 U.S. at 555). Finally, the court must determine whether “the facts alleged in the complaint are sufficient to show that the plaintiff has a ‘plausible claim for relief.’” Fowler, 578 F.3d at 211 (quoting Jgbal, 556 U.S. at 679). A facially plausible claim “allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Jd at 210 (quoting /gbal, 556 U.S. at 678). On a Rule 12(b)(6) motion, the “defendant bears the burden of showing that no claim has been presented.” Hedges v. United States, 404 F.3d 744, 750 (d Cir. 2005) (citing Kehr Packages, Inc. v. Fidelcor, Inc., 926 F.2d 1406, 1409 (3d Cir. 1991)).

2 All references to a “Rule” ot “Rules” hereinafter refer to the Federal Rules of Civil Procedure.

IH. DISCUSSION Wood contends that the Court must dismiss Nan’s claims. Specifically, Wood argues that Nan’s breach-of-contract claim encompasses damages asserted by non-party Photonworks, with which Wood lacks privity of contract. (See Def.’s Moving Br. 7-9.) Wood further asserts that the Court should dismiss Nan’s breach-of-covenant and unjust enrichment claims as duplicative of Nan’s breach-of-contract claim. (See id. at 9-14.) Finally, Wood argues that Nan has not alleged the elements of a cause of action under the Act. (See id. at 14-15.) The Court addresses each of the Amended Complaint’s causes of action in turn. A. Count I: Breach of Contract Turning first to Nan’s breach-of-contract claim, at issue is whether the claim can include the thirteen change orders submitted by non-party Photonworks. Wood claims that Nan cannot seek these change orders as damages as a matter of law because no contract existed between Wood and Photonworks. (See Def.’s Moving Br. 7.) Nan counters that privity is irrelevant because it properly characterized the thirteen change orders as damages accruing to itself and resulting from Wood’s breach. (See Pl.’s Opp’n Br. 3-6.) The Court begins by noting that the parties cite few cases addressing this precise issue, particularly in the realm of downstream contractors in a government project. The Court thus addresses each of the arguments raised by the parties. To start, the Court agrees with Wood that breach-of-contract claims generally require privity of contract. A breach of contract claim under New Jersey law requires four elements: “(1) a contract between the parties; (2) a breach of that contract; (3) damages flowing therefrom; and (4) that the party stating the claim performed its own contractual obligations.” Cobra Enters. LLC v. All Phase Servs., Inc., No. 20-4750, 2020 WL 5407997, at *2 (D.N.J. Sept. 9, 2020) (citing Frederico v. Home Depot, 507 F.3d 188, 203 (3d Cir. 2007)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conley v. Gibson
355 U.S. 41 (Supreme Court, 1957)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Karen Malleus v. John George
641 F.3d 560 (Third Circuit, 2011)
Sloan & Co. v. Liberty Mutual Insurance
653 F.3d 175 (Third Circuit, 2011)
Louis Spano v. JP Morgan Chase Bank
521 F. App'x 66 (Third Circuit, 2013)
Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
Frederico v. Home Depot
507 F.3d 188 (Third Circuit, 2007)
Bak-A-Lum Corp. of America v. Alcoa Building Products, Inc.
351 A.2d 349 (Supreme Court of New Jersey, 1976)
Fowler v. UPMC SHADYSIDE
578 F.3d 203 (Third Circuit, 2009)
Pizzullo v. New Jersey Manufacturers Insurance
952 A.2d 1077 (Supreme Court of New Jersey, 2008)
Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
Barry, Bette & Led Duke, Inc. v. State
240 A.D.2d 54 (Appellate Division of the Supreme Court of New York, 1998)
George Hyman Construction Co. v. United States
39 Cont. Cas. Fed. 76,601 (Federal Claims, 1993)
Severin v. United States
99 Ct. Cl. 435 (Court of Claims, 1943)
Kehr Packages, Inc. v. Fidelcor, Inc.
926 F.2d 1406 (Third Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
NAN, INC. v. WOOD ENVIRONMENT & INFRASTRUCTURE SOLUTIONS, INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/nan-inc-v-wood-environment-infrastructure-solutions-inc-njd-2022.