George Hyman Construction Co. v. United States

39 Cont. Cas. Fed. 76,601, 30 Fed. Cl. 170, 1993 U.S. Claims LEXIS 316, 1993 WL 495967
CourtUnited States Court of Federal Claims
DecidedDecember 2, 1993
DocketNo. 90-87C
StatusPublished
Cited by20 cases

This text of 39 Cont. Cas. Fed. 76,601 (George Hyman Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George Hyman Construction Co. v. United States, 39 Cont. Cas. Fed. 76,601, 30 Fed. Cl. 170, 1993 U.S. Claims LEXIS 316, 1993 WL 495967 (uscfc 1993).

Opinion

WEINSTEIN, Judge.

Opinion1

Defendant has moved for summary judgment on the grounds that plaintiffs claim is barred by the Severin doctrine, which holds that a prime contractor may recover damages on behalf of its subcontractor only if the prime contractor alleges actual damages to itself. Following briefing by the parties, the court now grants the motion.

Facts

The following facts are not in dispute.

Plaintiff, the George Hyman Construction Company (Hyman), contracted with the General Services Administration (GSA) for the construction of the Smithsonian Museum Support Center in Suitland, Maryland. Hy-man subcontracted with Ratrie, Robbins & Schweizer, Inc. (Ratrie) for the concrete work on the project, including the construction of a sidewalk in front of the Support Center. Ratrie, through its subcontractors, had to pour the sidewalk, in whole or in part, four times before GSA found it acceptable. This additional work forms the basis of the damages alleged in the complaint.

[172]*172After GSA rejected the third sidewalk, Ra-trie sent Hyman a letter dated September 17,1985 stating that Ratrie would replace the sidewalk again, but that it intended to recover its additional costs. On October 29 of that year, Hyman asked Ratrie to send a final requisition and suggested that Ratrie sign a lien release that excluded the sidewalk claim. Ratrie’s assistant treasurer on November 4, 1985 executed a lien release, prepared by Hyman, that waived all claims Ratrie had against Hyman, except for the claim arising from the additional sidewalk expenses.

On December 9, Hyman issued a check to Ratrie for final payment on the subcontract. On the reverse of the cheek was stamped a printed endorsement releasing all claims against Hyman:

Deposit of this check constitutes acceptance of same as full and final payment for all work performed or material furnished by payee and its subcontractors and suppliers on Smithsonian Support Center located at Suitland, MD and payee hereby fully releases and indemnifies payor from any present or future obligation with regard to all said work performed or material furnished on said site.

Exhibit 6 to Plaintiffs Proposed Findings of Uncontroverted Fact, at 2 (the underlined material was typed into blanks provided in the stamped endorsement). Ratrie deposited the check without reservation on December 12, 1985.

Hyman’s subcontractor’s accountant states in an affidavit, uncontroverted by defendant, that the cheek was stamped “inadvertently].” Exhibit 7 to Plaintiffs Proposed Findings of Uncontroverted Fact, at 2. Similarly, Ratrie’s treasurer states in his affidavit that the check was deposited only because his assistant failed to bring the stamped language to his attention.

In March 1988, Hyman and Ratrie signed an agreement purporting to revive Ratrie’s claim against Hyman. The parties agreed to distributing the costs of pursuing the claim against defendant and any recovery. The agreement provided that Ratrie could proceed directly against Hyman only if Hyman failed to sponsor the claim, and tolled the statute of limitations on Ratrie’s claim against Hyman until the conclusion of all proceedings against the government.

Plaintiffs March 29,1989 claim was denied by the contracting officer on June 28, 1989. On January 30,1990, Hyman filed this action in the United States Claims Court2 on behalf of itself and Ratrie, requesting money damages of $365,500.3

Discussion

Summary Judgment

Summary judgment is appropriate when there is no genuine issue as to a fact that is material to establishing the plaintiffs claim and the moving party is entitled to judgment as a matter of law. Rule 56(c) of the Rules of the United States Court of Federal Claims (RCFC); Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 2552, 91 L.Ed.2d 265 (1986); Anderson v. Liberty Lobby, 477 U.S. 242, 247-48, 106 S.Ct. 2505, 2509-10, 91 L.Ed.2d 202 (1986). As under Rule 56 of the Federal Rules of Civil Procedure, summary judgment under RCFC 56 is not considered “a disfavored procedural shortcut, but rather as an integral part of the Federal Rules as a whole, which [173]*173are designed ‘to secure the just, speedy and inexpensive determination of every action.’ ” Celotex, 477 U.S. at 327, 106 S.Ct. at 2555 (quoting Fed.R.Civ.P. 1).

If the moving party demonstrates the absence of evidence to support an essential element of the nonmovant’s claim, and the nonmovant fails to allege evidence sufficient to convince a reasonable trier of fact to find the existence of that element of the claim, the movant is entitled to summary judgment. Anderson, 477 U.S. at 248-49, 106 S.Ct. at 2510-11.

Subcontractor Claims and the Severin Doctrine

It has long been established that a subcontractor not in privity of contract with the government may not bring a direct action against the government in this court either for damages caused by the government’s breach of its contract with the prime contractor, Merritt v. United States, 267 U.S. 338, 340-41, 45 S.Ct. 278, 279, 69 L.Ed. 643 (1925); H. Herfurth, Jr., Inc. v. United States, 89 Ct.Cl. 122, 127, 1939 WL 4215 (1939), or for equitable adjustment under the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 601-13 (1988), see Erickson Air Crane Co. v. United States, 731 F.2d 810, 813 (Fed.Cir.1984). The most often stated rationale for this rule is that in these cases there is no contract with the government as to which the federal government has waived its sovereign immunity to suit under 28 U.S.C. § 1491 (1988), the statutory basis for this court’s assumption of jurisdiction over contract claims. See, e.g., Erickson Air Crane Co., 731 F.2d at 813. The other rationales are the avoidance of confusion or duplicative litigation against the government and of collusion between the prime and subcontractor. These purposes also are served by the Anti-Assignment Act, 31 U.S.C. § 3727 (1988), another often cited reason for the subcontractor privity requirement.

The privity requirement leaves “Aggrieved subcontractors [with] the option of enforcing their subcontract rights against the prime contractor in appropriate proceedings, or of prosecuting a claim against the government through and in right of the prime contractor’s contract, and with the prime contractor’s consent and cooperation.” Id.

Severin v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montano Electrical Contractor v. United States
114 Fed. Cl. 675 (Federal Claims, 2014)
Scott Timber Co. v. United States
97 Fed. Cl. 685 (Federal Claims, 2011)
ACE Constructors, Inc. v. United States
70 Fed. Cl. 253 (Federal Claims, 2006)
Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
Emerald International Corp. v. United States
54 Fed. Cl. 674 (Federal Claims, 2002)
General Dynamics Corp. v. United States
47 Fed. Cl. 514 (Federal Claims, 2000)
Perry-McCall Construction, Inc. v. United States
46 Fed. Cl. 664 (Federal Claims, 2000)
Morrison Knudsen Corp. v. Fireman's Fund Insurance
175 F.3d 1221 (Tenth Circuit, 1999)
Kentucky Bridge & Dam, Inc. v. United States
42 Cont. Cas. Fed. 77,404 (Federal Claims, 1998)
Supermex, Inc. v. United States
40 Cont. Cas. Fed. 76,897 (Federal Claims, 1996)
The George Hyman Construction Company v. United States
39 F.3d 1197 (Federal Circuit, 1994)
James Reeves Contractor, Inc. v. United States
39 Cont. Cas. Fed. 76,694 (Federal Claims, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cont. Cas. Fed. 76,601, 30 Fed. Cl. 170, 1993 U.S. Claims LEXIS 316, 1993 WL 495967, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-hyman-construction-co-v-united-states-uscfc-1993.