United States Ex Rel. D'Ambra Construction Co. v. St. Paul Mercury Insurance

24 F. Supp. 2d 218, 1998 U.S. Dist. LEXIS 17256, 1998 WL 758698
CourtDistrict Court, D. Rhode Island
DecidedOctober 29, 1998
DocketCIV. A. 94-0215L
StatusPublished
Cited by2 cases

This text of 24 F. Supp. 2d 218 (United States Ex Rel. D'Ambra Construction Co. v. St. Paul Mercury Insurance) is published on Counsel Stack Legal Research, covering District Court, D. Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. D'Ambra Construction Co. v. St. Paul Mercury Insurance, 24 F. Supp. 2d 218, 1998 U.S. Dist. LEXIS 17256, 1998 WL 758698 (D.R.I. 1998).

Opinion

MEMORANDUM AND ORDER

LAGUEUX, Chief Judge.

Use plaintiff (“D’Ambra”), a subcontractor on a federal government construction project, seeks compensation for services performed from the project’s general contractor (“North American”) and the general contractor’s surety (“St. Paul”). This matter is before the Court on a motion by defendants’ styled “Motion for Summary Judgment.” Defendants seek a ruling as a matter of law that they are not liable beyond a certain amount. For this reason, the Court will treat the motion as one for partial summary judgment and grant it as indicated below.

BACKGROUND

For the purposes of this motion, the complicated facts of this dispute may be briefly stated. In 1991, the United States Navy awarded defendant North American the contract to construct two new buildings at the Navy’s Advanced Weapons Research Facility in Newport, Rhode Island. North American obtained a labor and material payment bond, as well as a performance bond, from defendant St. Paul to satisfy the requirements of the Miller Act. See 40 U.S.C. §§ 270a-270f (1994) (requiring the posting of a performance and payment bond by contractors awarded a federal government construction contract).

D’Ambra entered into a written agreement (the “Subcontract”) with North American on December 24, 1991 to be a subcontractor on this Navy project. Under this contract, D’Ambra agreed to provide labor, materials, and equipment for the site and utility work. The Subcontract called for a flat payment of $426,000 for these services. Over the course of several years, D’Ambra completed significant portions of its assigned task. In addition to carrying out the specifics of the original plan for the project, D’Ambra also worked on alterations of and additions to the original plans.

Before the project was completed, however, the Navy informed North American in February 1994 that it was terminating their contract through the agreement’s Termination for Convenience provision, an escape hatch common to federal government construction contracts. Shortly thereafter, North American informed D’Ambra that it was terminating the Subcontract.

North American sponsored a class on March 10, 1994 to explain the administrative procedures involved in making claims for payment following a Termination for Convenience. The class was intended for subcontractors who had worked on the project. D’Ambra was represented at the class by a company official and an attorney. On April 22, 1994, D’Ambra filed this action against North American and St. Paul, asserting jurisdiction under the Miller Act. See 40 U.S.C. § 270b(b) (vesting jurisdiction in the United States district courts for actions brought by persons who furnish labor and materials on federal construction projects and who seek to collect on a payment bond for services performed). In the Complaint, D’Ambra seeks compensation for work performed on the project for which it has not yet been paid by North American. D’Ambra also requests an award of monetary relief for damages it alleges were incurred as a result of delays in the construction project outside of its control.

*220 D’Ambra was not content to rely on its federal lawsuit for relief, however. It choose also to pursue its cause through the settlement process outlined in the Contract Disputes Act. See 41 U.S.C. §§ 601-613 (1994) (outlining the system of claims resolution under the Contract Disputes Act). Under this system, imposed upon contractors in their contracts with the federal government, contractors on federal government construction projects that have been terminated are required to submit certified claims to the government for payment. See 41 U.S.C. § 605(c)(1). Only general contractors typically may submit claims because only they are in privity of contract with the government. See United States v. Johnson Controls, Inc., 713 F.2d 1541, 1557 (Fed.Cir.1983). Subcontractors must submit claims to the general contractor who batches together all claims related to the project for which it is responsible and submits them to a government contract officer for review. See Arnold M. Diamond, Inc. v. Dalton, 25 F.3d 1006, 1009 (Fed.Cir.1994) (describing this “sponsorship” system). This was the procedure followed in this case.

On January 30, 1995, D’Ambra submitted to North American a claim asserting that North American was hable to plaintiff for an outstanding balance on the construction project of $608,917.55. This balance due was based on total expenses incurred by D’Am-bra of $1,212,087.16. North American responded with a request that D’Ambra submit a new certification of its claim in the form provided by North American. That form language required D’Ambra to assert that the United States government was liable for the full amount of the claim. The revised claim alleged that it “accurately reflects the contract adjustment for which the contractor believes the government is liable.” D’Ambra complied by submitting the revised claim to North American on February 21,1995.

North American submitted D’Ambra’s claim, along with its own claims and those of other subcontractors, to the federal government according to the procedures of the Contract Disputes Act. The Defense Contract Audit Agency audited D’Ambra’s certified claim and determined that it could not compensate D’Ambra for much of its alleged costs. Based on this audit, the Navy’s Contracting Officer responsible for the settlement negotiations between North American and the federal government determined that D’Ambra was entitled only to an additional $32,549.30 beyond what it had already been paid, and that D’Ambra was not entitled to the full $608,917.55 claimed.

Following further research by North American into all of the claims arising from the project, it resubmitted the claims to the Contracting Officer in October 1996. North American claimed $492,958 on D’Ambra’s behalf. Shortly thereafter, North American began global settlement negotiations with the federal government. The settlement was completed on December 23,1996. As part of this agreement, the Contracting Officer increased the amount to which it determined that D’Ambra was entitled to $87,161. Unsatisfied with that sum, D’Ambra has pursued this federal lawsuit.

In the Complaint, D’Ambra alleges simply that it performed over $1.2 million of work on the Navy project under a contract with North American and that it has only been paid approximately one-half of that amount. It holds North American responsible for the balance and relies on the Miller Act for authority to proceed against the bond issued by St. Paul to satisfy the shortfall in payments. Defendants deny responsibility for the full amount sought by D’Ambra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
24 F. Supp. 2d 218, 1998 U.S. Dist. LEXIS 17256, 1998 WL 758698, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-dambra-construction-co-v-st-paul-mercury-rid-1998.