Erickson Air Crane Company of Washington, Inc. v. The United States

731 F.2d 810, 32 Cont. Cas. Fed. 72,392, 1984 U.S. App. LEXIS 14879
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 26, 1984
DocketAppeal 83-891
StatusPublished
Cited by274 cases

This text of 731 F.2d 810 (Erickson Air Crane Company of Washington, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Erickson Air Crane Company of Washington, Inc. v. The United States, 731 F.2d 810, 32 Cont. Cas. Fed. 72,392, 1984 U.S. App. LEXIS 14879 (Fed. Cir. 1984).

Opinion

NICHOLS, Senior Circuit Judge.

This is an appeal from a United States Department of Energy Board of Contract Appeals (EBCA or board) decision, 83-1 BCA 1116,145 (1982), denying recovery to appellant of amounts allegedly due it under certain clauses and due to breaches of other clauses of United States Contract No. 6/07/DC/71720. We affirm.

I

Background

On January 12, 1976, the United States Department of the Interior’s Bureau of Reclamation (government) entered into Contract No. 6/07/DC/71720 with Erickson Air Crane Company of Washington, Inc. (Erickson) to construct approximately 136 miles of 345 kilovolt transmission line from a point near Steamboat Springs, Colorado to Ault, Colorado. The contract required Erickson to have the transmission line in service by November 30, 1977, or suffer liquidated damages of $5,250 per additional day.

*812 Since much of the transmission line’s route lay over mountainous and heavily timbered terrain, Erickson intended to assemble and erect the steel transmission towers with a Sikorsky S-64 Sky Crane helicopter. Erickson subcontracted for the other “more routine” parts of the project with Pacific States Clearing (PSC) to build access roads and to clear the structure sites and the right-of-way; with a joint venture of Professional Hole Drilling, Inc. and Caissons, Inc. (PHD/C) to construct foundations for the transmission towers; with Tri-O, Inc. to string the conductor and overhead ground wire on the towers; and with New Growth, Inc. to landscape and revegetate the tower sites and temporary roads.

Erickson developed a comprehensive schedule for it and its subcontractors to follow: in rapid succession, PSC would clear a site, PHD/C would lay a foundation, Erickson would erect a transmission tower, Tri-0 would begin wire stringing, and New Growth would begin revegetation. Due to Erickson’s tight scheduling, however, single problems during construction often multiplied into several problems affecting other subcontractors down the line. Subcontractors’ schedules became unsyn-chronized; costs rose for most of those involved in the project.

Erickson subsequently filed several dozen claims on its and its subcontractors’ (claimants) behalf with the government’s contracting officer, then in the Department of Energy (DOE). (DOE assumed responsibility for the project pursuant to the Department of Energy Organization Act, Pub.L. No. 95-91, 91 Stat. 565 (1977). DOE assigned the project’s administration to the Western Area Power Administration.) The contracting officer made his final decision on July 18, 1979, holding for the government on some claims, and against it on others.

Erickson, on behalf of all the claimants, appealed thirty-five of these adverse decisions to the EBCA pursuant to section 7 of the Contract Disputes Act of 1978, 41 U.S.C. § 606 (1982). The EBCA consolidated claimants’ appeals for the purpose of a hearing. Counsel represented each of the claimants, with Erickson’s counsel designated as “lead” counsel and called upon mostly for procedural matters.

Claimants’ claims fell into three general categories. The first category consisted of claims alleging that during construction, the government delayed the work and disrupted the work sequence, and thus breached its contractual obligations or constructively changed the terms of the contract. Claimants argued that these government actions caused them to incur additional time, labor, and equipment costs for which the government is liable. The government responded that it merely enforced the terms of the contract and that any damages claimants suffered were due to their own failure to observe, acknowledge, or reasonably interpret various contract provisions.

The second general category consisted of claims alleging that the government’s bid documents misrepresented the physical conditions under which claimants would work, and that this misrepresentation affected the required method and manner of performance. The government responded that the specifications clearly spelled out the required performance and the working conditions associated therewith.

The third category contained one claim for costs under the value engineering (VE) provisions of the contract. Erickson based this claim on the government’s acceptance of a proposal Erickson presented to it on behalf of PHD/C to allow the modification of a specified type of tower footing under certain conditions. The government denied that Erickson’s proposal for use of the particular footing was a VE proposal. The government also asserted that Erickson’s proposal did not meet the technical requirements of a VE change proposal but was merely a contract change proposed and approved under the contract’s “Changes” clause.

The EBCA issued its decision on September 30, 1982. Erickson, PHD/C, and Tri-0 each filed a notice of appeal of the board’s *813 decision adverse to them. Over the objection of the United States, we allowed PHD/C’s and Tri-O’s motions to attack through their own briefs the EBCA decisions adverse to them.

II

Standing of Subcontractors

It is a hornbook rule that, under ordinary government prime contracts, subcontractors do not have standing to sue the government under the Tucker Act, 28 U.S.C. § 1491, in the event of an alleged government breach or to enforce a claim for equitable adjustment under the Contract Disputes Act of 1978. United States v. Johnson Controls, Inc., 713 F.2d 1541 (Fed.Cir.1983); Putnam Mills Corp. v. United States, 479 F.2d 1334, 202 Ct.Cl. 1 (1973). The government consents to be sued only by those with whom it has privity of contract, which it does not have with subcontractors. Johnson Controls, Inc., 713 F.2d at 1550-52. Aggrieved subcontractors have the option of enforcing their subcontract rights against the prime contractor in appropriate proceedings, or of prosecuting a claim against the government through and in right of the prime contractor’s contract, and with the prime contractor’s consent and cooperation.

As a practical matter, prime contractors often do allow subcontractors to prosecute claims in the prime’s name when they perceive that the subcontractors really have more at stake in a claim and are therefore willing to work harder on its enforcement. Subcontractors may also be the only ones in full possession of the facts. In the former Court of Claims, in contract cases, it was quite usual for prime contractors to step aside and allow counsel retained by subcontractors to prosecute claims, though always in the name and right of the prime. It is to be noted, too, that bonding requirements are often for protection of subcontractors and give them better assurance of being paid, in compensation for their inability to enforce liens against work which has become property of the government. Johnson Controls, Inc., 713 F.2d at 1553-54; United States Fidelity & Guaranty Co. v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aci-Scc Jv v. United States
Federal Claims, 2018
B3 Solutions LLC
Armed Services Board of Contract Appeals, 2016
Ogunniyi v. United States
124 Fed. Cl. 525 (Federal Claims, 2015)
Authentic Apparel Group, LLC v. United States
123 Fed. Cl. 92 (Federal Claims, 2015)
Woodruff v. United States
122 Fed. Cl. 761 (Federal Claims, 2015)
Petro Mex, LLC v. United States
122 Fed. Cl. 536 (Federal Claims, 2015)
David Nassif Associates Liquidating Trust v. United States
122 Fed. Cl. 366 (Federal Claims, 2015)
Hsh Nordbank Ag v. United States
121 Fed. Cl. 332 (Federal Claims, 2015)
System Fuels, Inc. v. United States
120 Fed. Cl. 635 (Federal Claims, 2015)
Anchorage, a Municipal Corporation v. United States
119 Fed. Cl. 709 (Federal Claims, 2015)
New Hampshire Flight Procurement, LLC v. United States
118 Fed. Cl. 203 (Federal Claims, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
731 F.2d 810, 32 Cont. Cas. Fed. 72,392, 1984 U.S. App. LEXIS 14879, Counsel Stack Legal Research, https://law.counselstack.com/opinion/erickson-air-crane-company-of-washington-inc-v-the-united-states-cafc-1984.