Hsh Nordbank Ag v. United States

121 Fed. Cl. 332, 2015 U.S. Claims LEXIS 621, 2015 WL 2398192
CourtUnited States Court of Federal Claims
DecidedMay 19, 2015
Docket14-899 C
StatusPublished
Cited by2 cases

This text of 121 Fed. Cl. 332 (Hsh Nordbank Ag v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hsh Nordbank Ag v. United States, 121 Fed. Cl. 332, 2015 U.S. Claims LEXIS 621, 2015 WL 2398192 (uscfc 2015).

Opinion

Assignment of Claims Act, 31 U.S.C. § 3727; Breach of Contract; Debt Collection Improvement Act, 31 U.S.C. § 3701; Equal Access to Justice Act, 28 U.S.C. § 2412; Implied Duty of Good Faith and.Fair Dealing; Motion to Dismiss, RCFC 12(b)(1), RCFC 12(b)(6); Summary Judgment, RCFC 56(e).

MEMORANDUM OPINION AND FINAL ORDER

BRADEN, Judge.

I. RELEVANT FACTUAL BACKGROUND. 1

CEP Funding, LLC and Columbia Energy Partners, LLC (collectively “CEP”) were *335 created to develop energy projects in the Pacific Northwest, including, a wind-energy project in Oregon, known as the Echanis Wind Project (“the Project”). Compl. ¶ 6. HSH Nordbank AG (“Plaintiff’) loaned CEP $25 million for the Project, secured by all of CEP’s assets. PI. App’x at 85-90 (February 26, 2010 Amendment No. 3 to Secured Promissory Note).

On January 9, 2008, CEP submitted a Large Generator Interconnection Request to the Bonneville Power Administration (“BPA”) to connect the Project to BPA’s power transmission grid via the Harney County, Oregon substation. Compl. ¶ 8. To accommodate this request, BPA needed to upgrade its local power infrastructure, requiring substantial study, engineering, and construction work. Compl. ¶ 9.

On September 17, 2008, CEP and BPA entered into Engineering and Procurement Agreement No. 08TX-13748 (“E&P Agreement”). Compl. ¶ 11. Pursuant to the E&P Agreement, BPA agreed to conduct engineering studies and design facilities for the interconnection at CEP’s expense. Compl. ¶ 11. Pursuant to the E&P Agreement and subsequent modifications, CEP paid BPA: $250,000 on September 25, 2008; $100,000 on December 2, 2008; $500,000 on October 20, 2010; $300,000 on March 6, 2012; and $475,000 on March 20, 2012. Compl. ¶ 11. The E&P Agreement required BPA, within a reasonable time after completion or termination of the interconnection, to provide CEP with an accounting of all expenses charged against CEP’s deposits and to refund any residual payments not spent. Compl. ¶ 13.

On October 21,2008, CEP and BPA entered into Point-to-Point Transmission Service Agreement No. 08TX-13707 (“TSA”). Gov’t App’x at 5-14. The TSA allowed CEP to purchase and manage transmission servicé from BPA, pursuant to Transmission Service Requests (“TSRs”). Compl. ¶ 16. BPA approved four TSRs, referred to as Tables 1A, IB, 1C, and ID. Compl. ¶ 17. Each TSR reserved a specific quantity of transmission service for CEP on a monthly basis for a specific term. 2 Compl. ¶ 17. After service commenced, CEP was obligated to make monthly payments in advance. Compl. ¶ 18. If CEP failed to pay, BPA had the unilateral right to suspend service or terminate the TSA. Compl. ¶ 18.

In or around December 2008, the Project’s proponents applied for a right-of-way (“ROW”) from the Bureau of Land Management (“BLM”). Compl. ¶ 25. A ROW was necessary, because the Project required construction of a power transmission line across federally owned land. Compl. ¶24. Before the ROW was approved, however, the BLM was required to prepare an environmental impact study, pursuant to the National Environmental Policy Act, 42 U.S.C. § 4321 et seq. Compl. ¶ 24.

On July 30, 2010, CEP and BPA entered into Environmental Study Agreement No. 10TX-10511 (“ES Agreement”). Compl. ¶ 12. Under the ES Agreement, BPA would conduct the environmental study at CEP’s expense. Compl. ¶ 12. Pursuant to the ES Agreement, CEP made a deposit of at least $50,000. PI. Ex. B at 6. The ES Agreement also required BPA, within a reasonable time after completion or termination of the interconnection, to provide CEP with an accounting of all expenses charged against CEP’s deposits and to refund any unused funds. Compl. ¶ 13.

On October 21, 2011, BLM issued a Final Environmental Impact Statement regarding the proposed transmission line. Compl. ¶ 27.

*336 BPA required CEP to take transmission services pursuant to Tables IB and 1C beginning in December 2011 at a cost of $52,535 per month, 3 as required by Tables IB and 1C. Compl. ¶ 21. In December 2011, however, CEP was late in submitting a request to defer transmission service for 2012, pursuant to Tables IB and 1C. Compl. ¶ 21. Moreover, instead of using BPA’s service itself, CEP sold the service to third parties. Compl. ¶ 22.

On December 28, 2011, BLM approved the ROW request. Compl. ¶ 27.

On February 29, 2012, CEP and BPA executed Modification No. 4 to the September 17, 2008 E&P Agreement, under which BPA agreed to continue the work necessary to complete the interconnection at project capacity. Gov’t App’x at 1-2. CEP also increased its funding obligation from $850,000 to approximately $1,625 'million. Compl. ¶28. CEP made two additional deposits to BPA: $300,000 on March 6, 2012; and $475,000 on March 20, 2012. Compl. ¶30.

On April 5, 2012, the Oregon Natural Desert Association filed a lawsuit challenging' BLM’s environmental review of the ROW. Compl. ¶ 31 (citing Or. Natural Desert Ass’n v. Salazar, No. 12-cv-596 (D. Or. filed April 5, 2012)). In response, BPA informed CEP that it would suspend work on the interconnection while the lawsuit was pending. Compl. ¶¶ 32-33. On September 16, 2013, the United States District Court for the District of Oregon granted the Government’s motion for summary judgment. Compl. ¶ 31; see also Op. & Order, Dkt. No. 80, Or. Natural Desert Ass’n.

In mid-2012, CEP began to experience liquidity problems. Compl. ¶ 34. In early Fall 2012, CEP notified BPA that it was withdrawing its interconnection request. Compl. ¶36. On October 11, 2012, BPA informed CEP by email that it would refund CEP any unused funds. Compl. ¶ 37.

In November 2012, CEP requested to defer transmission service, pursuant to Tables 1A and ID. Compl. ¶ 39. BPA agreed to revise the TSA to effectuate the deferral, but CEP failed to pay the reservation fee. Compl. ¶ 39. Consequently, in December 2012, BPA required CEP to take transmission service, pursuant to Tables 1A and ID. Compl. ¶ 39. This brought CEP’s total monthly transmission fees to approximately $112,575 per month. Compl. ¶ 39. CEP, however, was unable to pay the entire monthly fee. Compl. ¶ 41.

On January 30, 2013, CEP requested that BPA provide an accounting of all interconnection deposits and return any unused funds. Gov’t App’x at 77-78. On March 28, 2013, BPA advised CEP that it owed BPA approximately $450,300 in transmission service fees. Gov’t App’x at 79-82. BPA also refused to pay CEP any refund until the outstanding transmission service fees were paid. Compl. ¶¶ 43-44. BPA responded that the Debt Collection Improvement Act, 31 U.S.C. § 3716

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
121 Fed. Cl. 332, 2015 U.S. Claims LEXIS 621, 2015 WL 2398192, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hsh-nordbank-ag-v-united-states-uscfc-2015.