Scott Timber Co. v. United States

97 Fed. Cl. 685, 2011 WL 1248653
CourtUnited States Court of Federal Claims
DecidedApril 5, 2011
DocketNo. 05-708C
StatusPublished
Cited by10 cases

This text of 97 Fed. Cl. 685 (Scott Timber Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scott Timber Co. v. United States, 97 Fed. Cl. 685, 2011 WL 1248653 (uscfc 2011).

Opinion

OPINION AND ORDER1

LETTOW, Judge.

This is a post-trial decision on damages in a timber-sale case. The relevant timber-sale contracts pertain to the “Jigsaw,” “White-bird,” and “Pigout” timber areas located in the Umpqua National Forest in Southern Oregon, within Region 6 of the National Forest System. See Scott Timber Co. v. United States, 86 Fed.Cl. 102, 103 (2009). Scott Timber Company (“Scott Timber” or “Scott”) filed suit in this court seeking damages based upon allegations that the United States Forest Service (“Forest Service”) had wrongfully [688]*688suspended and breached these three timber-sale contracts. At the behest of the parties, trial proceedings were bifurcated into separate phases, respectively, liability and damages. See id. at 103 n. 1. Following an eight-day trial held in Portland, Oregon, from June 30 through July 11, 2008, the court found the government liable to Scott Timber. See id. at 120-21. Thereafter, a seven-day trial on damages was held from August 16 through August 24, 2010. Upon the completion of post-trial briefing and closing argument, the claim for damages is ready for disposition.

FACTS2

At oral auctions held on October 21 and 28, 1998, Scott Timber was the high bidder on timber-sale contracts for the Pigout, Jigsaw, and Whitebird tracts, and, eventually, eight and one-half months later, on July 8, 1999, Scott was awarded those contracts. Scott Timber, 86 Fed.Cl. at 104. Each of the three contracts contained a standard clause, Section CT6.01, providing for the interruption or delay of operations to prevent environmental damage or to comply with a court order. Id. at 104-105. Each contract also contained a clause, Section BT8-21, permitting a Contract Term Adjustment if Scott Timber experienced an inteiTuption or delay in operations or if the Forest Service requested an interruption or delay of more than ten days. Id. at 105.

The three contracts were suspended before performance began due to an injunction issued by the United States District Court for the Western District of Washington in a litigation styled Oregon Natural Res. Council Action v. United States Forest Serv., 59 F.Supp.2d 1085 (W.D.Wash.1999) (“ONRC Action”). See Scott Timber, 86 Fed.Cl. at 105. In ONRC Action, plaintiffs challenged the Forest Service’s and the Bureau of Land Management’s compliance with survey requirements contained in the Northwest Forest Plan. Id. at 106 (citing ONRC Action, 59 F.Supp.2d at 1091-92). The Jigsaw, White-bird, and Pigout timber sales had not been identified as being at risk in the complaint or amended complaint filed in ONRC Action, or in any public filings in that case, but the environmental organizations who brought suit had informed the Justice Department during confidential settlement negotiations that they believed the three sales, among others, had been made in contravention of the Northwest Forest Plan. See Scott Timber, 86 Fed.Cl. at 106. Officials with the Forest Service had specifically withheld this information from Scott Timber, acting on the basis that they were obliged by the attorney-client privilege not to disclose the inclusion of the tracts on the list of “at risk” sales. Id. at 116.

The Northwest Forest Plan amended Land and Resource Management Plans governing the operation of nineteen National Forests and seven Bureau of Land Management districts in the Pacific Northwest, including the Umpqua National Forest where the tracts pertinent to Scott Timber’s sales were located. Scott Timber, 86 Fed.Cl. at 109. The Plan required surveys to be performed before ground-disturbing activities could be implemented in forest areas, to avoid harming species of concern that might be present in the forest. Id.

The Northwest Forest Plan was developed after a series of injunctions barring timber sales had been entered by federal district courts in the early 1990s. See Scott Timber, 86 Fed.Cl. at 109 & n. 9. Representatives of the Forest Service, Bureau of Land Management, Environmental Protection Agency, and other federal agencies undertook a study and drafted a report suggesting “patterns of protection, investment, and use that will provide the greatest possible economic and social contribution from the nation’s forests.” Id. at 109 (citing DX 2 at 5 Forest Ecosystem Management Team (“FEMAT”) Report (July 1999)) (internal quotations omitted).3 The [689]*689FEMAT report and farther environmental impact assessments were used to formulate the Plan.

In ONRC Action, the district court for the Western District of Washington on August 2, 1999, acting upon cross-motions for summary judgment, concluded that the Forest Service had failed to comply with survey requirements outlined in the Northwest Forest Plan and precluded the Forest Service from approving operations on the sales listed in the amended complaint until the required surveys had been performed. ONRC Action, 59 F.Supp.2d at 1093, 1097. Twenty-four days later, on August 26, 1999, the district court expanded its injunction to include twenty-five other timber-sales contracts not identified in the ONRC Action pleadings or other publicly available filings in the case; this subsequently enjoined group included the Pigout, Jigsaw, and Whitebird sales. Scott Timber, 86 Fed.Cl. at 107. The Forest Service suspended the timber sales that had been enjoined, including the three timber sales at issue here, and it began to undertake the requisite surveys of the sale areas.

All surveys on the Pigout, Jigsaw, and Whitebird properties were completed by August 7, 2001. Scott Timber, 86 Fed.Cl. at Ill. Nonetheless, the Pigout contract remained suspended until June 11, 2002, and the Jigsaw and Whitebird contracts remained suspended until June 9, 2003. Id. at 105-106. Once the suspensions were lifted, Scott Timber began harvesting the timber covered by the sales. Scott Timber completed performance of the Pigout contract in 2005, and of the Jigsaw and Whitebird contracts in 2008. See PX 244B (Attachments A-C: Timber Sales Statements of Account).

In November 2004, Scott Timber filed three claims under the Contract Disputes Act with Ms. Brenda L. Woodard, the Forest Service’s contracting officer for the Pigout, Jigsaw, and Whitebird contracts. Scott Timber, 86 Fed.Cl. at 106. She issued a decision granting Scott Timber interest on its deposits in the three sales but denied Scott’s claims for lost market opportunity and other costs and losses. Id.

On June 30,2005, Scott Timber filed suit in this court alleging that the Forest Service had wrongfully suspended and breached the Pigout, Jigsaw, and Whitebird timber-sale contracts and seeking damages. See Compl. at 17-18. Following the initial trial, the court found the government liable for damages to Scott Timber on three separate and independent grounds. First, the Forest Service unreasonably awarded the Pigout, Jigsaw, and Whitebird contracts to Scott Timber without informing Scott of the risks to the contracts posed by the ONRC Action litigation, which risks were known to the Forest Service but not to Scott Timber and which knowledge had been specifically and intentionally withheld from Scott Timber.4 These actions breached the Forest Service’s covenant of good faith and fair dealing and duty to cooperate. Scott Timber, 86 Fed.Cl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
97 Fed. Cl. 685, 2011 WL 1248653, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scott-timber-co-v-united-states-uscfc-2011.