Hughes Communications Galaxy, Inc. v. United States, Defendant-Cross

271 F.3d 1060, 46 U.C.C. Rep. Serv. 2d (West) 453, 2001 U.S. App. LEXIS 24358, 2001 WL 1403481
CourtCourt of Appeals for the Federal Circuit
DecidedNovember 13, 2001
Docket00-5109, 00-5119
StatusPublished
Cited by143 cases

This text of 271 F.3d 1060 (Hughes Communications Galaxy, Inc. v. United States, Defendant-Cross) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hughes Communications Galaxy, Inc. v. United States, Defendant-Cross, 271 F.3d 1060, 46 U.C.C. Rep. Serv. 2d (West) 453, 2001 U.S. App. LEXIS 24358, 2001 WL 1403481 (Fed. Cir. 2001).

Opinion

RADER, Circuit Judge.

Following a trial on damages for breach of contract, the United States Court of Federal Claims awarded Hughes Communications Galaxy, Inc. $102,680,625. Hughes Communications Galaxy, Inc. v. United States, 47 Fed.Cl. 236 (2000) (Hughes V). Because the Court of Federal Claims did not abuse its discretion in calculating damages, this court affirms.

I.

This case has received extensive factual analysis in prior opinions. See Hughes Communications Galaxy, Inc. v. United States, 998 F.2d 953 (Fed.Cir.1993) CHughes II); Hughes V, 47 Fed.Cl. 236; Hughes Communications Galaxy, Inc. v. United States, 38 Fed.Cl. 578 (1997) (.Hughes IV); Hughes Communications Galaxy, Inc. v. United States, 34 Fed.Cl. 623 (1995) (.Hughes III); Hughes Communications Galaxy, Inc. v. United States, 26 Cl.Ct. 123 (1992) (Hughes I). This appeal addresses only the Court of Federal Claims’ breach of contract damage determination in Hughes IV and Hughes V.

In December 1985, NASA and Hughes entered into a Launch Services Agreement (LSA), which required NASA to use its “best efforts” to launch ten of Hughes’ HS-393 satellites on space shuttles. The LSA required NASA to continue using its best efforts to launch Hughes’ HS-393s until it launched all ten HS-393s or until September 30,1994, whichever was earlier.

NASA compiled “manifests” of all shuttle payloads scheduled for launch on shuttles. NASA reissued these manifests periodically to account for changed circumstances. The manifests listed commercial payloads in order of their planned or firm launch dates and scheduled a shuttle for each launch. After NASA and Hughes entered the LSA, NASA assigned Hughes’ satellites specific slots on a manifest.

In January 1986, the space shuttle Challenger exploded. Following the Challenger explosion, NASA suspended operation of the shuttles until September 1988. Further, .in August 1986, President Reagan announced that NASA would no longer launch commercial satellites on shuttles. On July 10,1986, NASA completed the last manifest before President Reagan’s announcement. It projected that NASA would launch eight Hughes satellites on shuttles by September 1994. Thereafter, NASA compiled a new manifest that only included “shuttle unique” and “national security and foreign policy” payloads. That manifest did not list any Hughes satellites. Later NASA informed Hughes that it would almost certainly not launch any Hughes satellites on shuttles.

After 1986, Hughes launched three of its HS-393s on expendable launch vehicles (ELVs), one of which was the JCSAT-1. Hughes also launched several similar satellites on ELVs, including six HS-601 satellites. The HS-601s are similar to the HS~ 393s, except they are more powerful and better suited for ELV launches. While the ELV launches provided an alternative to shuttle launch services under the LSA, *1065 Hughes incurred more costs by launching satellites on ELVs rather than on shuttles.

Hughes sued the United States Government for breach of contract and for taking its property without providing just compensation. The Court of Federal Claims granted summary judgment to the Government on both claims based on the sovereign act defense. Hughes I, 26 Cl.Ct. at 144-46. This court reversed that summary judgment and remanded. Hughes II, 998 F.2d at 959. On remand, the Court of Federal Claims granted summary judgment for Hughes for breach of contract. Hughes III, 34 Fed.Cl. at 634. Before holding a trial on damages, the Court of Federal Claims ruled that the Government could not produce evidence to reduce its damages by the amount Hughes had passed on to its customers in increased prices. Hughes IV, 38 Fed.Cl. at 582.

At the damages trial, Hughes sought to prove damages by showing its increased costs in launching satellites on ELVs, rather than on shuttles. Hughes presented two main methods for calculating the increased costs. The first method, the Ten HS-393 Satellites Method, compared the costs of launching ten HS-393s on shuttles under the LSA with the costs of launching ten HS-393s on ELVs. Because Hughes had actually launched only three HS-393s on ELVs, the method based the ELV launch costs on the actual costs of launching the three HS-393s. The second method, the Primary Method, compared Hughes’ actual costs of launching ten satellites on ELVs with the costs that Hughes would have incurred by launching ten satellites on shuttles under the LSA. The ten satellites included the three HS-393s, the six HS~601s, and one HS-376.

The Court of Federal Claims used the Ten HS-393 Satellites Method to calculate Hughes’ increased costs of “cover.” Hughes V, 47 Fed.Cl. at 244. However, the court modified the method in several important respects. First, the court found that even using its best efforts, NASA would have only launched five HS-393s under the LSA. Accordingly, the court only awarded Hughes increased costs for five satellites, rather than ten. Id. Second, the court averaged the costs of launching on shuttles the three HS-393s that were actually launched on ELVs and used that average for the fourth and fifth satellites, rather than individually calculating the cost of launching each satellite on a shuttle, as Hughes’ expert had done. Id. at 244 n. 12. Third, in calculating the ELV launch costs for the fourth and fifth satellites, the court escalated the costs using the midpoint between March 1989 and September 1994, rather than the midpoint between March 1989 and December 1995, as Hughes’ expert had done. Id. at 244. Fourth, the court refused to award Hughes prejudgment interest on its damages. Id. at 2M-45. Fifth, the court refused to award Hughes reflight insurance costs and increased launch insurance costs for the five satellites. Id. at 245-46.

Based on its modified HS-393 method, the court awarded Hughes $102,680,625 in damages for its increased launch costs. Id. at 247. Hughes and the Government both appeal. This court has jurisdiction under 28 U.S.C. § 1295(a)(3) (1994).

II.

This court reviews damages determinations by the Court of Federal Claims for an abuse of discretion. Massie v. United States, 226 F.3d 1318, 1320 (Fed. Cir.2000). This court will consider a trial court to have abused its discretion when: “(1) the court’s decision is clearly unreasonable, arbitrary or fanciful; (2) the decision is based on an erroneous construction of the law; (3) the trial court’s factual findings are clearly erroneous; or (4) the *1066 record contains no evidence upon which the [trial] court rationally could have based its decision.” Air Land Forwarders, Inc. v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
271 F.3d 1060, 46 U.C.C. Rep. Serv. 2d (West) 453, 2001 U.S. App. LEXIS 24358, 2001 WL 1403481, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hughes-communications-galaxy-inc-v-united-states-defendant-cross-cafc-2001.