S. W. Electronics & Manufacturing Corp. v. United States

655 F.2d 1078, 29 Cont. Cas. Fed. 81,726, 228 Ct. Cl. 333, 1981 U.S. Ct. Cl. LEXIS 408
CourtUnited States Court of Claims
DecidedJuly 29, 1981
DocketNo. 207-78
StatusPublished
Cited by39 cases

This text of 655 F.2d 1078 (S. W. Electronics & Manufacturing Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S. W. Electronics & Manufacturing Corp. v. United States, 655 F.2d 1078, 29 Cont. Cas. Fed. 81,726, 228 Ct. Cl. 333, 1981 U.S. Ct. Cl. LEXIS 408 (cc 1981).

Opinion

BENNETT, Judge,

delivered the opinion of the court:

This contract case involves an appeal from a quantum decision of the Armed Services Board of Contract Appeals. In an earlier decision, the board determined that the plaintiff (S.W. Electronics & Manufacturing Corp., sometimes referred to as Swemco) was entitled to recover damages due to the defective design specification which the Government furnished for a rotary switch that was incorporated into a radio receiving set. S.W. Electronics & Mfg. Corp., ASBCA No. 17523, 74-2 BCA ¶ 10,650 (1974) (S. W. I— entitlement decision). In a subsequent decision, which is the subject of this appeal, the board determined that plaintiff was entitled to recover only $2,601 of its $269,299 quantum claim. S.W. Electronics & Mfg. Corp., ASBCA Nos. 20698 and 20860, 77-2 BCA ¶ 12,631 (1977) (S.W. II— quantum decision). The quantum decision was affirmed in an opinion based on plaintiffs motion for reconsideration. S.W. Elec-[335]*335ironies & Mfg. Corp., ASBCA Nos. 20698 and 20860, 77-2 BCA ¶ 12,785 (1977) (S. W. III — reconsideration decision).

The board found that plaintiff had failed in its burden of proof in establishing both the government’s responsibility for and the reasonableness of the quantum claimed. As part of its decision that the plaintiff had inappropriately proceeded on a total cost theory of recovery, the board found that the cost of reworking sets into which defective switches had knowingly been placed by plaintiff was not a cost attributable to the defective specification.

The quantum decision is presently before the court for review in accordance with the standards of the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1976). The plaintiff takes exceptions to the trial judge’s decision recommending affirmance of the board opinion. We agree with the trial judge’s rejection of the total cost claim.1 However, based on a review of the facts, we conclude that the board erred in failing to grant a "jury verdict” for plaintiff. The board misapplied the law and evidence relating to such verdicts, and we conclude that the contracting officer’s award should not have been reduced since it represented a reasonable estimate of plaintiffs damages under the facts of this case.

On January 12, 1971, plaintiff was awarded contract No. N00383-71-C-0061 by the Naval Aviation Supply Office (ASO). The ASO contract required plaintiff to manufacture and deliver 527 radio receiving sets for use in military aircraft at a contract price of $823,645. The radio receiving set is a complicated piece of electronic equipment composed of three modules of which only one, the Radio Frequency Module, is pertinent to the plaintiffs claim. That module is comprised of four subassemblies, one of which contains the rotary switch which is the source of this dispute. The rotary switch was manufactured according to specification control drawing No. 8525028/Rev. G, which was found to be part of the ASO contract in the entitlement decision in this case, S.W.I.

The problem developed several months after plaintiff began incorporating a rotary switch manufactured by [336]*336Ledex, Inc. In late September of 1971, finished sets failed to pass the required electrical tests and on October 22, 1971, plaintiff notified ASO of the problem. In order to understand the setting in which these problems developed, it is necessary to consider a prior and a concurrent contract which plaintiff performed.

In June 1971, plaintiff experienced a financial crisis that threatened the company’s continued existence. Plaintiff had nearly completed production of some sound ranging sets for the Government of Pakistan. However, plaintiffs export license had expired and could not be renewed due to a review of the U. S. military supply policy with respect to Pakistan.

Unable to ship the sets and receive payment of the $230,690 contract price, plaintiff was threatened by an impending financial disaster. Plaintiff applied for Pub. L. No. 85-804, 72 Stat. 972 (1958), relief, and a grant and loan totaling $250,000 was agreed upon. The Office of the Comptroller of the Department of the Navy granted the relief after a determination that plaintiffs continued performance on government contracts was essential to the national defense. The amount of relief was calculated as the minimum necessary to complete the NavAir (discussed infra) and ASO contracts.

Plaintiffs petition for relief was premised upon the cash flow problem caused by the Pakistani contract and substantial savings the Government would receive if plaintiff completed production. In an August 27, 1971, letter to the Navy Contract Adjustment Board, plaintiff stated:

Our poor present cash position increased current and future costs of manufacturing due to severe production inefficiencies resulting from layoffs of manufacturing and supporting personnel and running smaller production lots, both forced on us to conserve cash.

This relief was implemented by modification No. PO-0006 to the ASO contract. The modification was effective October 26, 1971, and included a release of all claims by plaintiff, arising prior to the date of the amendment, from [337]*337any cause of action out of any contract with the U. S. Government.2

Prior to award of the ASO contract, plaintiff was performing another government contract for the production of radio receiving sets. On June 26, 1969, plaintiff was awarded NavAir contract No. NOOO19-69-C-0678. NavAir supplied plaintiff with drawings, specifications, and two RCA models containing rotary switches supplied by Oak Manufacturing Company. It was these drawings which the board’s S. W. I decision found to be part of the ASO contract. The NavAir contract was a mixed performance and design specifications contract. It required a first article submission and contained a clause for the correction of patent and latent defects.

In August 1970, NavAir approved plaintiffs first articles which incorporated Oak switches. When the switch problem developed in the fall of 1971, NavAir was notified on October 19, 1971. An engineering change proposal (ECP) was submitted to NavAir and approved on March 17, 1972. In approving the ECP, NavAir granted plaintiff an equitable adjustment based on the latent defect in the rotary switch specification. This equitable adjustment of $38,300 compensated plaintiff for the one-time engineering effort to solve the problem and the cost of reworking 27 receiving sets.

In response to plaintiffs letter of October 22, 1971, advising ASO of the switch problem, the ASO contracting officer on November 17, 1971, advised plaintiff in part as follows:

A review of the letter of 19 October 1971 indicates that the Switch Assembly problem is a result of your procurement of the Switch Assembly Component for the production units from a supplier other than the supplier [Oak Manufacturing Company] who furnished the component for the First Article.
Please be advised that the First Article, and the components thereof, as approved under contract N00019-69-[338]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parsons Evergreene, LLC v. Secretary of the Air Force
968 F.3d 1359 (Federal Circuit, 2020)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
Spodek v. United States
73 Fed. Cl. 1 (Federal Claims, 2006)
Orlosky Inc. v. United States
68 Fed. Cl. 296 (Federal Claims, 2005)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
Hi-Shear Technology Corp. v. United States
53 Fed. Cl. 420 (Federal Claims, 2002)
Amelco Electric v. City of Thousand Oaks
38 P.3d 1120 (California Supreme Court, 2002)
Cavalier Clothes, Inc. v. United States
51 Fed. Cl. 399 (Federal Claims, 2001)
Doninger Metal Products, Corp. v. United States
50 Fed. Cl. 110 (Federal Claims, 2001)
Hughes Communications Galaxy, Inc. v. United States
47 Fed. Cl. 236 (Federal Claims, 2000)
Datalect Computer Services, Ltd. v. United States
42 Cont. Cas. Fed. 77,379 (Federal Claims, 1998)
Air Land Forwarders, Inc. v. United States
38 Fed. Cl. 547 (Federal Claims, 1997)
Bath Iron Works Corp. v. United States
40 Cont. Cas. Fed. 76,840 (Federal Claims, 1995)
Ralph L. Jones Co. v. United States
33 Fed. Cl. 327 (Federal Claims, 1995)
Blake Construction Company, Inc. v. The United States
987 F.2d 743 (Federal Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
655 F.2d 1078, 29 Cont. Cas. Fed. 81,726, 228 Ct. Cl. 333, 1981 U.S. Ct. Cl. LEXIS 408, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-w-electronics-manufacturing-corp-v-united-states-cc-1981.